05-11-2013 1
Q1-Q3 Cryostat Ideas
Mike Anerella / Paul Kovach / Jesse Schmalzle
November 5, 2013
05-11-2013 2
Relevant prior experience (1)
For RHIC arc dipoles & LHC D1 dipoles, cold masses are supported on 2 plastic posts separated by heat shield intercept plates within cryostat
05-11-2013 3
Relevant prior experience (2)
• For RHIC e-Lens superconducting solenoid, for cost savings spare standard “CQS” cryostats were used
• Cold mass barely fit, centered inside cryostat→ vertical cylinders; “spool pieces” were added
to cryostat, downward from existing port locations, to house support posts
05-11-2013 4
RHIC e-Lens magnet details
• Blue = standard RHIC cryostat
• Orange = standard RHIC upper & lower plastic support posts
• Grey = cryostat cylinder extension & standard port cover
• Silver = heat shield plate & extension
cradle
upper post
lower post
heat shield plate
cryostat extensioncylinder
cryostat port cover
O-ring
O-ring
stainless backing ring
stainless backing ring
05-11-2013 5
application to Q1-Q3 (1)
Review ofLHC D2/D4 Assembly:• Single support post,
bolted to cradle• Heat shield plate
epoxied to post o.d.• Sliding, keyed
support inside post spacer
• Weight supported by post spacer, retaining ring
05-11-2013 6
application to Q1-Q3 (2)
Ø890 ID cryostat
Ø106 He II out (pumping line)
Ø35 Shield cooling
Cold mass cradle
“short” upper post
Heat shield plate
“standard” lower post
Cryostat extension cylinder
QXF Assembly
Post spacerShim, retaining ring
Ø630 cold mass
Upper post, heat shield detail
05-11-2013 7
Existing (BNL) LHC insertion tooling
Cold mass buildup area
Cryostat support / post installation area
Tooling removal area
• Tooling used for LHC D2, D3, D4 production at BNL (D1 used separate tooling)
• Cryostat support / post installation tooling provided by CERN (shortened to 10 m length at BNL)
05-11-2013 8
insertion tooling / assembly detail
Cold mass sled
Tow plate
Cryostat extension cylinder fits within
existing tooling clearance hole
Cold mass / upper post / heat shield slide into cryostat
Lower post is bolted to upper post, and post spacer, shim & retaining ring are installed while cold mass is held by
jack / hoists
05-11-2013 9
Summary
• Cold mass can be installed in preferred “downward offset” location with standard diameter cryostat
• “short” upper post and “standard” lower post permit assembly while reducing heat load
• Cryostat cylinder extension retains full function of existing design and fits within clearance of present (BNL) LHC insertion tooling
Alternately, if desired cryostat extension could be used with slightly increased diameter cryostat & centered cold mass to reduce heat load (also favorable due to saturation?)