PROJECT STATUS JULY 2019
Overall view
Club House First Slab work in progress
Building 4–Final slab completed
Building 5-Final slab completed
Building 6-1st Floor With MIVAN in progress
Building 7-Parking-3 slab work in progress
Building 8-16th floor Roof slab Work in progress
Building 9-10th floor roof slab in progress
Building 2-(Parking-2) Roof slab shuttering in Progress
Building 3–Typical floor slab Completed
Building 1-2nd slab work in progress
Podium