UTILITY REVIEW PROCESS
• Go to www.denvergov.org/pwpermits and download/save the documents under Utility Plan Review section titled:– UPR Application (PDF)
– UPR Submittal Checklist (PDF)
– Required Plan Notes (PDF)
– UPR Submittal Guide (PDF)
• Check if the following special requirements apply to your project:– Construction in a FEMA Floodplain – See slide No. 2
– Project has multiple, non-continuous conduit installations (bundled projects) – See Slide No. 3
• Use UPR Submittal Guide and Submittal Checklist to assist in preparing construction plans – Example plans are provided on Slide No. 4
• Refer to UPR Submittal Guide for the following: – Initial submittal requirements and fees
– Comment resolution process
– Final submittal requirements
1
PROJECTS LOCATED IN A FLOODPLAIN
Access Denver Floodplain Maps: https://denvergov.org/Maps/map/floodplain
2
Projects located within any
Flood Hazard Zone except
Zone X require an SUDP.
See link below for SUDP
requirements:
https://www.denvergov.org/co
ntent/denvergov/en/denver-
department-of-public-
works/projects/flood.html
BUNDLED PROJECTS
Refer to the UPR
Guidance Document
and illustration on this
slide for projects with
multiple conduit runs
submitted as one
application (Bundled
Projects).
Access Public Works Construction Inspection Districts Maps: https://denvergov.org/Maps/map/pwid3
EXAMPLE PLAN
4
Call-out surface
utilities
Call-out utility type, size, length
and installation method(s)
Show proposed utility
alignment with feasible
angles/curvature
Call-out appropriate City
details
Call-out depth(s)
Min. 36” required
Min. 48” preferred in landscape
areas/tree lawns
Display and label existing features such as trees, landscaping,
ROW, sidewalk, EOP, underground and surface utilities, poles,
encroachments, streets, alleys, driveways, etc.
Dimension ROW,
show clearance
from adjacent ex.
utilities, dimension
to accurately locate
alignment as
frequently as the
alignment changes
EXAMPLE FEE CALCULATION
Utility Plan Review fees are lump sum flat fees, due at the time of each submittal. The fee schedule is as follows:
Initial Resubmittal Project Type
Fee Fee
Any project with a proposed utility length of 750’ – 1,499’ $ 500 $ 250
Any project with a proposed utility length of 1500’ – 2249’ $ 750 $ 375
Any project with a proposed utility length of greater than 2,250’ $ 1,000 $ 500
Any other project requiring a Utility Plan Review $ 320 $ 160
Each resubmittal requires the additional fees noted. The fees for a project with a proposed utility length of 900’
that requires two resubmittals to gain approval would therefore be $500 + $250 + $250 = $1,000.
5