OLYMPUS
U.Schneekloth/R.Beck
PRC closed session6.05.2009
OLYMPUS U. Schneekloth/R.Beck 2
OLYMPUS Approval
Recommended by PRC in Oct. 2008, provided funding
Approved by DESY directorate in Dec. 2008 subject to
schedule for installation and running and necessary funding
OLYMPUS U. Schneekloth/R.Beck 3
Schedule
Remove ARGUS experiment in Summer 2009 Disassemble and pack BLAST detector Jan.-March 2010 Ship and assemble BLAST/OLYMPUS detector and OLYMPUS target
in spring-fall 2010 Modify DORIS beam-line and install OLYMPUS target in DORIS in
winter 2010/11 shutdown. OLYMPUS commissioning in parking position winter-summer 2011 Install complete OLYMPUS experiment in summer 2011 Commission in fall 2011
Parasitic mode and some dedicated shits during service weeks Take data in 2012
Schedule discussed/agreed with DESY M, FS and FH directors
OLYMPUS U. Schneekloth/R.Beck 4
Schedule Milestones
OLYMPUS U. Schneekloth/R.Beck 5
Schedule
OLYMPUS U. Schneekloth/R.Beck 6
Schedule
Background studies
Parasitic studies + some days (~5)
full operation
OLYMPUS U. Schneekloth/R.Beck 7
Cost Estimate – Operation
OLYMPUS
OLYMPUS U. Schneekloth/R.Beck 8
Cost Estimate – Investments
OLYMPUS U. Schneekloth/R.Beck 9
Cost Estimate – Investments
OLYMPUS U. Schneekloth/R.Beck 10
Cost Estimate – Investments Possible in-kind contributions of institutes
Cooling system (design, ordering, setup,…) Cabling from power supply to toroid Polarity switches (assembly in workshop) Modification of vacuum system Send technicians (ARGUS removal, modification of IR,…)
Presently about 500 – 600k€
Could save about 100k€ in power costs in case of early modification of quads