NAVAL LIGHTERAGE R&D PROGRAM 30 JANUARY 2002 Sealift Support Program Office Naval Facilities...

Post on 22-Dec-2015

222 views 1 download

Tags:

Transcript of NAVAL LIGHTERAGE R&D PROGRAM 30 JANUARY 2002 Sealift Support Program Office Naval Facilities...

NAVAL LIGHTERAGE R&D

PROGRAM

30 JANUARY 2002

Sealift Support Program OfficeNaval Facilities Command

2

AGENDA

• ACTD Lesson’s Learned

• Navy R&D Accomplishments

• Plans For Next 12 Months

• Replacement System

• Questions?

3

ACTD LESSON’S LEARNED

• ISO sized modules increased weight/assembly time• Structure needed to be strengthened for SS5

survivability• Needed to improve alignment guides• Flexible connections required for larger platforms• Rigid connectors required strengthening and safety

improvement• Additional fendering required for safety• Mooring and anchoring improvements required• Additional speed and bollard pull required• Deck jewelry and increased winch capacity required• Interface with legacy systems critical• Bow ramp deployment improvements required

4

NAVY LIGHTERAGE R&D ACCOMPLISHMENTS

• Designed improved rigid connector• Automated development of flexor connector• Designed alignment wedge for improved assembly• Reduced weight by complete redesign of modules and

alternate material evaluation• Increased module strength based on hydrodynamic

analyses/modeling• Improved power module with fendering, deck jewelry,

and deck winch upgrades• Improved platform speed and bollard pull by optimizing

hull form, propulsion system, and reducing weight• Manufacturing 3 prototype modules for test at sea

5

IMPROVED RIGID CONNECTORS

• Designed by NSWCCD Carderock

• Remote activation/manual backup

• Improves safety through SS3

• Provides greater load transfer to hull

• Fabricated by CG Yard

• Load tested at NSWCCD Oct-Nov 01

• Government patent pending

• Incorporates all ACTD lessons learned

• SS5 survivable

• Incorporated in 3 prototype modules

• NSWCCD developing alignment/capture device works in conjunction with connectors to assist connection process

6

IMPROVED RIGID CONNECTORS

7

ALIGNMENT/CAPTURE DEVICE

8

FLEXIBLE CONNECTORS

• Required every 160’ to reduce sea state loads

• Sea State 5 survivable

• Designed by NFESC from existing NL flexor connectors

• Includes remote activation/manual backup

• Adapted shear connection as alignment device for high

sea states

• At-sea testing scheduled Mar – Apr 02

9

NEW GENERATION DECK WINCH

• Prototype procurement by NSWCCD Philadelphia (NAVSSES)

• Manufacturer – InterOcean Systems Company, San Diego, CA

• Delivery scheduled Feb 02

• At-sea testing scheduled Mar 02

• Replaces obsolete deck winch on SLWT– Same footprint – Increased load to 30,000 lbs– Increased capacity– Increased wire rope size to 1-1/4”– Larger and stronger capstan – Quieter

10

NEXT GENERATION DECK WINCH

11

ARTICULATING A-FRAME

• Designed by NFESC and NAVSSES

• Provides extension from 3 feet aft of WT bow to 5 feet forward of bow

• Improves operator safety

• Increased rated load to 30,000 lbs

12

SPANNING RAMP

• Concept development by NFESC

• Must permit rolling stock to move between platforms and craft

• Must be self contained, packaged in ISO flat-rack

• Must be Sea State 3 capable

• Must ensure ramp break-over angle permits traffic by all vehicles

13

WARPING TUG/CF POWER MODULE

• One piece unit 24’W x 8’H x 90’L

• WT and CFPM use similar hull form and propulsion system

• 2X more power than existing units

• Bow thruster to provide better maneuverability (WT Only)

• Improved handling– Pusher pads, better fendering, hogging-in winches (WT Only)

• Calculated maximum craft speed full load: 11 KTS

• Current module weight estimates – WT 121 LT, CF 119 LT

14

WARPING TUG

15

CF POWER MODULE

16

WARPING TUG COMPARISON

Dimensions Weight Bow Thruster

Speed Bollard Pull

SLWT 21’ X 84’ X 5’ 104 LT No 7 kts 12,000 lbs

WT 24’ X 90’ X 8’ 121 LT Yes 11 kts 24,000 lbs

17

NON-POWERED MODULE TYPES

• 8’W x 8’H x 40’L ISO modules too lively/heavy

• Redesigned to larger 24’W x 8’W x 80’L to reduce weight and improve safety/assembly

• Four Non-powered module types

- Bow ramp

- Combination (male/female)

- Intermediate

- Ramp

• Improved rigid/flexor connectors and alignment wedge

18

BOW RAMP MODULE

• 24’W x 8’H x 80’L

• In concert with flexible connectors and hull shape, will provide for dry ramp on a 1:50 beach gradient

• Module will provide a bow thruster for greater maneuverability around vessels and control in cross-current

• Ramp break-over angle will permit all vehicles to transverse without incident

Female FlexConnection

Bow Thruster

Stowed Ramp

Rake Angle= 3:20

Sloping Deck @ 7 Deg Gunwale

Male FlexConnection

8’ Ramp Length18’

19

BOW RAMP MODULE

20

COMBINATION MODULE (MALE/FEMALE)

FlexorRigid connector

Female endMale end

- 24’W x 8’H x 80’L each- Provides stable FC/RRDF platforms

21

INTERMEDIATE MODULE

- 24’W x 8’H x 80’L - Provides flexibility to accommodate a variety of platform configurations

FlexorFlexor

Male end Female end

22

RAMP END MODULE

Flexor Ramp

- 24’W x 8’H x 80’L- Component of RRDF and Floating Causeway to accommodate watercraft interface

23

NSWCCD COMPOSITE MODULE

• Detailed design by NSWCCD

• 24’ W x 8’ H x 40’ L with rigid connectors at both ends

• ½ Length

• Fabrication by Litton Ingalls Shipbuilding, Gulfport, MS

• Delivery scheduled Feb 02

40’ Design 80’ Design(extrapolated values)

Module weight 107,000 lbs (47.8 LT) 165,000 lbs (73.7 LT)

Light Draft 23” 17”

Max load with 4 ft freeboard

121,000 lbs (54.0 LT) 300,000 lbs (134 LT)

24

NSWC COMPOSITE MODULE CONSTRUCTION

25

NSWC COMPOSITE MODULE CONSTRUCTION

26

ART ANDERSON COMPOSITE COMBINATION MODULE

• Detailed design by AAA with support from fabricator (Goodrich EPP) under phase II of SBIR• 24’ W x 8’ H x 40’ L Combination Module – ½ Length• Monocoque design/foam filled • Phase III SBIR awarded Oct 23 01• Delivery scheduled Apr 02

40’ Design 80’ Design (extrapolated values)

Module weight 121,232 lbs (54.1 LT) 209,331 lbs (93.5 LT)

Light Draft 25” 22”

Max load with 4 ft freeboard

102,638 lbs (45.8 LT) 243,452 lbs (109 LT)

27

AAA COMPOSITE MODULE

28

STEEL COMBINATION MODULE

• Designed by US Coast Guard Yard, Curtis Bay, MD• 24’ W x 8’ H x 80’ L Combination Module• Design validation by ABS• Fabrication by USCG Yard• Completion scheduled Feb 02

80’ Steel module

Module weight 190,800 lbs (85.2 LT)

Light Draft 20”

Max load with 4 ft freeboard

274,200 lbs (122.4 LT)

29

U.S. COAST GUARD YARD STEEL MODULE CONSTRUCTION

30

COMPARISON NON-POWERED MODULES

Dimensions Weight SS Unloaded Draft

Load Loaded Free- Board

NL CIN 21’ X 90’ X 5’ 66 LT 2 15” 89 LT 12”

USCG Steel CM 24’ X 80’ X 8’ 85.2 LT 3 20” 122.4 LT 48”

NSWC Composite CM

24’ X 80’ X 8’ 73.7 LT 3 17” 134 LT 48”

AAA Composite CM 24’ X 80’ X 8’ 93.5 LT 3 22” 109 LT 48”

31

250’ CAUSEWAY FERRY

• Power module flexed to (1) intermediate module flexed to (1) bow ramp module

PM IM BRM

32

CAUSEWAY/BARGE FERRY COMPARISONS

Dimensions Capacity Speed Bollard Pull

NL Barge Ferry

21’ X 266’ X 5’ 205 LT 3 kts 12,000 lbs

CF Steel 24’ X 250’ X 8’ 280 LT 11 kts 24,000 lbs

CF Composite 24’ X 250’ X 8’ 290 LT 11+ kts 24,000 lbs

33

fcm

fcm

mcm

1200’ FLOATING CAUSEWAY

IM IM

mcm

(2) CM(2) CM(2) CMIM RMRM (2) CM

FLOATING CAUSEWAY KIT2- RM- ramp module (80’)5- IM- intermediate module (80’)7- CM/M - combination module (80’)5- CM/F- combination module (80’)24- M/M CONNECTORS2- SPANNING RAMPS1- CREW SHELTER3- LIGHT CARTS

FlexorRigid side connector

IMIM

1200’

72’

34

(2) CM(2) CM

(2) CM

(2) CM

STERN RRDF

FlexorRigid side connector

RM

IM

mcm

fcm

RRDF KIT1- RM- ramp module (80’)1- IM- intermediate module (80’)5- CM/M - combination module (80’)5- CM/F- combination module (80’)42- M/M CONNECTORS2- SPANNING RAMPS1- CREW SHELTER3- LIGHT CARTS

96’

400’

35

(2) CM

SIDE RRDF

(2) CM(2) CM IM

RM

(2) FlexorsRigid side connector

mcm

fcm

RRDF KIT1of 1- RM- ramp module (80’)1of 1- IM- intermediate module (80’)4 of 5- CM/M - combination module (80’)4 of 5- CM/F- combination module (80’)30 of 42- M/M CONNECTORS2 of 2- SPANNING RAMPS1 of 1- CREW SHELTER3 of 3- LIGHT CARTS

400’

72’

36

PLANS FOR NEXT 12 MONTHS

• Complete manufacture of 3 prototype modules

• Validate designs with at sea tests

• Complete solicitation for replacement system

• Request industry review/comment of specification requirements

• Recapitalize legacy system to extend capability until replacement system delivered

• Award low rate initial production contract incorporating R&D lessons learned (upon availability of funding)

37

REPLACEMENT SYSTEM• Surf Entry and Barge Offload Systems (SEABOSS)

– Incorporates all JMLS and NL safety and product improvements24’ W x 8’ H x 80’ L NPS

24’ W x 8’ H x 90’ L WT/CSP

Use Improved Rigid and Flexible Connector System

Improved A Frame

Upgraded engines and propulsors

Spanning Ramps

Improved Deck Fittings and Deck Strength

Next Generation Winch

Hogging In Winches w/ Tensioning Device

SS3 Objective

Increased Speed, Load Capacity and Bollard Pull – ACAT III NAVFAC SYSCOM and Milestone Decision Authority

38

SEABOSS ACQUISITION SCHEDULEFY02 FY03 FY04 FY05 FY06 FY07 FY08

OPEVAL

FULL RATE PRODUCTION

SystemIOC

MS C DECISION

BRIEF

PROCUREMENT PACKAGE ACQUISITION DOCUMENTS

FRP

PROD & DEV LRIP

EWTGPAC DEL

OPTION 1

PARTIAL BG1/2

FINISH EWTGPAC

OPTION 2

BG1/2 & MPS3

OPTION 3

MPS1

OPTION 4

MPS2 & BIC

LRIP

Contract

System FOC

SystemIOC

FY10FY09

39

QUESTIONS?