State Route 81 Widening, Phase I – Postmaster Drive to N. Bethany RoadFunding for Right-of-Way & Construction
Districts I & III$4,013,777.35
State Route 81 Widening, Phase II – N. Bethany Road to Keys Ferry RoadFunding for Design
Districts I & III$200,000.00
McDonough Parkway Extension – Henry Parkway to State Route 20/81Funding for Construction
$3,908,969.54
South Ola Road ExtensionDistrict I & District III
$1,591,764.35
IntersectionImprovements
Lester Mill Road @ Bill Gardner ParkwayDesign
$250,000.00
Dirt Road Projects
Peeksville Road(Bridge to Old Jackson)
$4,087,674.08
Burg RoadPeeksville Road to County Line
$4,054,000.00
Sandy Ridge RoadKeys Ferry to Stallsworth Road
Design$110,000.00