Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... •...

Post on 24-Aug-2020

4 views 0 download

Transcript of Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... •...

1 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)1

Joel DarringtonContracting CounselDPR ConstructionJoelDa@dpr.com

Brian PerlbergExecutive Director ConsensusDocsbperlberg@consensusdocs.org

Tom RichertPrincipal Lean Project Consulting, Inc.trichert@leanproject.com

Lean Contracting Practices without an IPD Contract and the New ConsensusDocs 305 Lean Construction Addendum

2 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)2

ConsensusDocs 12+ Years

$1,000,000+ In donated free educational licenses.

12Years publishes best practice contracts

100+ Standard contract documents.

40Leading construction associations participating in the Coalition.

3,000+Subscribers.

1 GoalImprove the design and construction industry with Best Practice Contracts

$40+ Billion in Construction Contracts

ZERO Reported Cases

What is the ConsensusDocs 305?

Owner/Design

ProfessionalContract

CD 305 Lean

ConstructionAddendum

Owner/Constructor

Contract

3 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)3

Ways to Contract for Lean Design + Construction

• Integrated Project Delivery (IPD) Agreement (a/k/a IFOA)• e.g., CD 300 (2016 edition)

• Custom-created IPD-ish design & construction agreements• Vague references to Lean added to an owner’s standard

contract• Now with CD305, an industry standard form outside of IPD

that addresses a wide spectrum of Lean practices

4 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)4

Addendum to What?

ConsensusDocs 305 can be used with:• ConsensusDocs 500 Agreement between Owner & CM• Other forms of CM at Risk contracts• Construction contracts under Design-Bid-Build• Owner contracts with Design Professional

• Not intended for Design-Build Prime Contracts, but … • ConsensusDocs 341 will be published this summer.

5 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)5

How is this Different than IPD?

Owner

CM/GC

Key Trades

Key Design Consultants

IPD

Owner

CM/GC

Design Prof.

Sub-contractors

CD 305

Specialty Designers

CD305

6 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)6

DesignProf.

Addendum vs. Silence

• Increase alignment among parties• First collaborative act• Parameters for Lean behavior and activities• Some Lean methods will conflict with standard contract

language, so Addendum overrides • Allows enforcement of Lean requirements, but take care

7 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)7

Using the CD 305

• When? • O/A/C are committed to Lean, but one or more are not

ready or able to enter an IPD Agreement• As early in the Project as the Owner will allow

• How?• Jointly negotiated, separately attached• Check-the-box

8 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)8

Typical Chronology of IPD Project

Allowable Cost

Preconstruction Phase Construction Phase

Expected Cost & Target Cost

Contract PriceActual Cost

Validation Phase

9 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)9

CD305 Check-the-Box Example 1

Preconstruction Phase

Construction Phase

Validation Phase

Joint Worksite Investigation (6.1)

Evaluate Owner’s Program (6.2)

Validation Study (6.3)

Continuous Cost Modeling (6.4)

Integrated Design/Target Value Design (6.5)

Risk Identification/Management (6.6)

(Always included; no check boxes)

10 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)10

CD305 Check-the-Box Example 2

Preconstruction Phase

Construction Phase

Validation Phase

Joint Worksite Investigation (6.1)

Evaluate Owner’s Program (6.2)

Validation Study (6.3)

Continuous Cost Modeling (6.4)

Integrated Design/Target Value Design (6.5)

Risk Identification/Management (6.6)

(Always included; no check boxes)

11 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)11

CD305 Check-the-Box Example 3

Preconstruction Phase

Construction Phase

Validation Phase

Joint Worksite Investigation (6.1)

Evaluate Owner’s Program (6.2)

Validation Study (6.3)

Continuous Cost Modeling (6.4)

Integrated Design/Target Value Design (6.5)

Risk Identification/Management (6.6)

(Always included; no check boxes)

12 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)12

What about Incentives?

• CD305 does not itself provide for incentive compensation

• Too much variability to standardize incentives

• CD305 does provide for Performance Improvement Program, which individual projects could use as a platform for incentive compensation

• Provide for incentives through amendment to Owner contracts

13 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)13

Reliable Promises 3.3

• Conditions of satisfaction must be clear

• Competent to perform

• Time estimated and reserved

• Performer sincere

• Performer accepts consequences

14 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)14

• Owner, Design Professional, and Constructor Reps, plus others invited

• Resolves problems through consensus decisions and best interests of the project

• Selects team• Provides daily leadership for the project• Manages budget and design process• Implements production control• Oversees personnel and team members.

15 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)15

Core Group Owner, Design Professional, Constructor

• Candor and thick skin

• Enthusiasm for change and improvement

• Commitment to goals and principles

• Ability to decide and commit

• No hierarchy

• Shared accountability and responsibility.

16 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)16

Core Group - Key Attributes

• 15 performance metrics

• Periodic evaluations

• A focus on team members’ behaviors

• Clear standards for evaluating performance

• Feedback mechanism on improvements.

17 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)17

Performance Improvement Program

• Aligning Personal, Team and Project Goals

• Focus on Clarity of Requests and Commitments

• Coaching

• Equip the Team for Rapid Learning

18 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)18

Implementing Team Leadership & Culture

Aligning Personal, Team and Project Goals

19 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)19

20 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)20

Focus on Clarity of Requests and Commitments

Presenter
Presentation Notes
Action results from conversations – poor conversations result in poor actions – excellent conversations result in excellent actions – clarity is key to excellence

21 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)21

Coaching

Where you are.

Where you want to be.

22 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)22

Equip the Team for Rapid Learning

• Section 5.1• What is a Project Planning System• Weekly Planning Cycle• Daily Adjustments• Implied Practices

23 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)23

Project Planning System

Source: Ballard, Tommelein. 2016 Benchmark for the Last Planner System®

24 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)24

What is a Project Planning System

®

25 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)25

Weekly Planning Cycle

Daily Adjustments

26 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)26

27 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)27

Implied Practices

Allowable Cost

Expected Cost & Target Cost

Validation PhaseJoint Worksite Investigation (6.1)

Evaluate Owner’s Program (6.2)

Validation Study (6.3)

Program Services & Validation

28 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)28

Preconstruction Phase

Expected Cost & Target Cost

Continuous Cost Modeling (6.4)

Integrated Design/Target Value Design (6.5)

Risk Identification/Management (6.6)

29 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)29

Integrated Design & TVD

Preconstruction Phase: Constructor to:• Provide continuous cost modeling and analysis• Generate periodic cost model reports

Construction Phase: Constructor + Subcontractors to:• Provide cost information and estimates requested by Core Group

Core Group to:• Establish milestones for updating Project cost model• Direct actions if cost model exceeds Allowable Cost

Compare to lower design-assist option in CD 541.

30 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)30

Continuous Cost Modeling

• Collaborative – DP still in charge and responsible, but must coord. + integrate with Team

• Value, Cost and Schedule and constructability are basic components of design (6.5.1)

• Written Protocols for Target costs [6.5.7.3 (a-h)]

• Add value w/ VAPs, TVD Clusters, A-3s (6.5.8)

• Design phases – planning/programming, design, detailing,

and production planning

• Uses pull based design process to drive innovation

31 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)31

Target Value Design

Document Review

• Examine Design Documents with reasonable care

• Advise Core Group of issues prompting additional contingency

• Suggest options for additional investigation

Target Value Pricing 6.5.7

• Establish Expected Cost and Target Cost early

• Target Cost only exceeded by express approval of Core Group.

32 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)32

Target Value Design Processes

Continuing refinement of cost models

Cost analysis not to be deferred• Byproduct of continuing TVD process• Core Group jointly manages

Escalation addressed in:• Estimates• Expected Cost• Target CostExpected Cost and Target Cost adjusted• At Final Completion• Reflecting difference between escalation allowance and actual escalation

33 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)33

Target Value Pricing

• BIM (verb) as a process not a software application

• Interconnected models and databases

• The power of BIM makes the payoff of lean greater –Provide continuous, immediate, and

reliable informationRegarding design, scope, schedule,

and cost.

34 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)34

Building Information Modeling (B.I.M.)

Design Model As-Built

Design Model Vs As-Built

www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)

Presenter
Presentation Notes
Notice in the trade model is how steel plate connections are shown and systems are offset to avoid. Corridor is much more dense, systems are rerouted to get all to fit

Design As-Built

Des

www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)

Presenter
Presentation Notes
AE’s show one line for most systems, ignoring the reality that Pumps, valves, connections are all bigger. Then add in structural connections, hangers, and support steel…it gets ugly quick. Doug

• Identify material risks in early workshops

• Create risk identification report• Rank and focus on higher priority risksLikelihood of occurrenceTime and cost impacts

• Develop Risk Management Plan withContingency plansAssignment of primary responsibilityAddress roles of others in managing risk

37 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)37

Risk Assessment and Management 6.6

Article 7

• 5S Plan• Quality, Standardized Work, PDCA• Material Flow• Information Flow

38 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)38

Construction Phase Lean Features

5S Plan

39www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)39 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)39

Sort Set in Order Shine/Sweep

Standardize Sustain

40 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)40

Quality, Standardized Work, PDCA

41 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)41

Material Flow

Presenter
Presentation Notes
7.3 LOGISTICS PLAN Constructor shall order the material and equipment in accordance with an agreed- upon material logistics plan and the current phase plan and look ahead plan in an effort to promote just- in-time deliveries to the site and minimize handling costs and provide the least obstruction of the premises and any adjoining property.

42 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)42

Information Flow

ConsensusDocs 541 Design Assist Addendum• Addendum to prime agreements, consultant and subs• Optional tools from CD 305:

• BIM• Owner’s program evaluation• Value Analysis• Cost modeling• Optional risk analysis• Optional production planning

• Constructability (in 541 only) • Manpower analysis, design-build packages early

procurement packages, etc. (in 541 only) • Design Coordination (in 541 only).

43 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)43

Presenter
Presentation Notes
Design coordination, D-B packages, code review, schedule and manpower analysis, early procurement of materials and equip, prefabrication. Optional life cycle cost analysis, sustainability.

How do you Structure the ConsensusDocs 305 & 541?

Owner

Constructor

Key Trades

Key Design Consultants

DesignProf.

IPDCD 300

Owner

CM/GCDesign

Prof

Sub-contractors

CD 305CD 541

Specialty Designers

CD305

44 www.consensusdocs.org| support@consensusdocs.org | 866.925.DOCS (3627)44

CD 541or both

TheCollabometer

DesignAssist

“Collabometer” Courtesy of Jack Mumma Michigan State University

45

Design-Assist can help Prevent Against

www.consensusdocs.org| support@consensusdocs.org | 866.925.DOCS (3627)

47 www.consensusdocs.org | support@consensusdocs.org | 866.925.DOCS (3627)47

Joel DarringtonContracting CounselDPR ConstructionJoelDa@dpr.com

Brian PerlbergExecutive Director ConsensusDocsbperlberg@consensusdocs.org

Tom RichertPrincipal Lean Projecttrichert@leanproject.com

Lean Contracting w/o IPD & the New ConsensusDocs 305Download a sample by registering at www.consensusdocs.org.

Questions?