A very generous anonymous donor gives 1.5 million dollars

Matching funds bring budget to around 3 million dollars

Don Johnson hired as the architect

Remodel Core Team has first of many meetings

Greenberry Construction chosen as contractor The move-out happens over Summer Break Constructions begins in July

Construction ends

Move-in happens over Spring Break

Ready for patrons first day of Spring Term

Donor

Don Johnson – Architect

Greenberry Construction – Chuck Taylor, Superintendent

Core Team MembersAnn Adams Anne GreenAnn Smart Audrey PerkinsBob Schapper Carlena WeeksChareane Wimbley-Gouveia Elizabeth LundyJorry Rolfe Kathy ClarkKevin Nicholson Kristen JonesLynn Trimpe Roger Maurer

FacilitiesKevin Nicholson, Director

Kevin Lacey, Associate Director

Maintenance Crew Custodial Crew

Media Services – for putting up with the construction

Fred Haynes – for letting the library use IB120 during construction

LBCC Foundation For Reading Room Furniture

LBCC Associated Student Government

For Collaborative Computer Workstations

Chambers FamilyFor Group Study / Conference

Room Furniture