Post on 10-Mar-2020
Draft
Peoples’ Republic of Bangladesh Ministry of Power, Energy and Mineral Resources
Land Acquisition and
Resettlement Action Plan
Matarbari 2x600 MW Coal Fired Power Plant Project
(for Power Plant, Port Facility and Transmission
Line and Township Development)
October 2013
Reviewed and Prepared by
Bartika Beacon Consultancy Services Ltd. (BBCS)
Avenue-2/2, Block-G, Section-2, Mirpur, Dhaka-1216.
i
Table of Contents Section no Page
No. 1 Rationale 1.1 Objectives 1-1 1.2 Project Description 1-1 1.3 Project Components. 1-1 1.4 Location of the proposed site 1-1 1.5 Methodology for preparing LARAP 1-6 1.6 Brief Description of Social Impacts. 1-7 1.6.1 Brief Description. 1-7 1.6.2 Anticipated Impact by Power Plant and Port Facility Construction 1-8 1.6.3 Anticipated Impact caused by the Extension of Transmission Line 1-8 1.6.4 Anticipated Impact Caused by the Development of Township Site. 1-9 1.7 Specific Measures Taken to Minimize Adverse Impacts 1-10 1.7.1 Examination of Alternatives 1-10 1.7.2 Application of International Standards to Land Acquisition and
Resettlement 1-10
1.7.3 Entitlements of Affected People without Legal Claims to Land 1-11 1.7.4 Measures for Avoidance and Further Influx of Illegal Occupation 1-11 1.7.5 Methods of Valuing Affected Assets 1-11 1.7.6 Livelihood Restoration and Rehabilitation 1-11 2 Legislations in Bangladesh and GAPs From JICA's Policy
2.1 Key Legislations 2-1 2.2 JICA's Policy on Land Acquisition and Resettlement 2-2 2.3 Procedures for Land Acquisition 2-3 3 Social Impact 3.1 Socioeconomic Survey and Focus Group Discussions at Power Plant and Port
Facility Site 3-1
3.1.1 Survey Outline 3-1 3.1.2 Findings 3-3 3.2 Socioeconomic Survey and Focus Group Discussions at Transmission Line Site 3-14 3.2.1 Survey Outline 3-14 3.2.2 Findings 3-16 3.3 Socioeconomic Survey at Township Site 3-18 3.3.1 Survey Outline 3-18 3.3.2 Findings 3-19 3.4 Local Consultation 3-25 3.4.1 First Public Consultation Meeting 3-25 3.4.2 Second Public Consultation Meeting 3-28 3.4.3 Third Public Consultation Meeting 3-32 4 Detailed Description of Impact and Category of Project Affected Persons (PAPs)
4.1 Power Plant 4-1 4.1.1 Pre-construction Phase and Construction Phase 4-1 4.1.2 Operation Phase 4-4 4.2 Port Facility 4-6 4.2.1 Pre-construction Phase and Construction Phase 4-6 4.2.2 Operation phase 4-6 4.3 Transmission Line 4-7 4.3.1 Pre-construction Phase and Construction Phase 4-7 4.3.2 Operation Phase 4-8 4.4 Township Development 4-9 4.4.1 Pre-construction Phase and Construction Phase 4-9 4.5 Entitlement for Different Types of Losses. 4-11 5 Livelihood Restoration and Improvement Plan 5-1 6 Implementation Arrangement and Organizational Responsibilities 6.1 Coal Power Generation Company of Bangladesh Ltd. 6-1 6.2 Other Agencies Involved in the Process 6-4 6.2.1 Deputy Commissioners 6-4 6.2.2 Project Supervision Consultant 6-4 6.2.3 LARAP Implementing Agency 6-4 6.2.4 Ministry of Power, Energy and Mineral Resources (MOPEMR) 6-5
ii
List of Table and Figure
Table/ Figure No.
Page No.
Table 1-1 Area covered by the proposed transmission line 1-4 Table 1-2 Anticipated Land Acquisition 1-7 Table 1-3 Anticipated Impact (Power Plant and Port Facility) 1-8 Table 1-4 Breakdown of Land Acquisition (Transmission Line) 1-9 Table 1-5 Anticipated Impact on the Owners of Angle Tower Locations 1-9 Table 1-6 Anticipated Impact of Township Development 1-9 Table 2-1 Gap Analysis between Bangladeshi Laws and JICA Guidelines 2-3 Table 3-1 Interviewed Households 3-1 Table 3-2 Structure of Socioeconomic Survey 3-2 Table 3-3 Interviewed Population in Focus Group Discussion 3-3 Table 3-4 Total Surveyed Population 3-4 Table 3-5 Education Level of Heads and Household Size 3-5 Table 3-6 Literate Population 3-5 Table 3-7 Educational Levels and Literacy (FGD) 3-5 Table 3-8 Occupations of the Household Heads 3-6 Table 3-9 Incidence of Poverty (Head Count Ratio) by CBN Method in 2010 3-9 Table 3-10 Incidence of Poverty (by per capita monthly income) in 2010 3-9 Table 3-11 Incidence of Poverty (by per capita monthly expenditure) in 2010 3-9 Table 3-12 Household Head’s Per Capita Monthly Income and Expenditure 3-9 Table 3-13 Animals and Poultry owned by Households 3-10 Table 3-14 Energy Source by Purpose 3-11 Table 3-15 Availability of Medical Facilities 3-12 Table 3-16 Skill Development Requests 3-14 Table 3-17 Profile of Interviewed Households 3-14 Table 3-18 Interviewed Population in Focus Group Discussion 3-15 Table 3-19 Total Surveyed Population 3-19 Table 3-20 Education Level of Heads and Household Size 3-20 Table 3-21 Literate Population 3-20 Table 3-22 Occupations of the Household Heads 3-20 Table 3-23 Household Per Capita Monthly Income and Expenditure 3-22 Table 3-24 Animals and Poultry owned by Households 3-23 Table 3-25 Energy Source by Purpose 3-23 Table 3-26 Availability of Medical Facilities 3-24
6.2.5 Joint Verification Team 6-5 6.2.6 Property Valuation Advisory Team 6-5 6.2.7 Resettlement Advisory Committees (RACs) 6-6 6.2.8 Women Groups in Resettlement Process 6-7 6.3 Institutional Capacity Building 6-7 7 Grievance Redress Mechanisms 7.1 Entitlement for Different Types of Losses 7-1 8 Specific Measures provided to Vulnerable Groups and Income Rehabilitation
Assistance 8-1
9 Estimated Land Acquisition and Resettlement Cost
9.1 Power plant and port facility site 9-1 9.2 Transmission line route 9-4 9.3 Township Area 9-6 9.4 Compensation and Resettlement Budget 9-8 9.4.1 Finalization and Approval of the Compensation and Resettlement Budget 9-8 9.4.2 Management of Budget 9-8 10 Local Consultation, Participation and Disclosure
10.1 Project Stakeholders 10-1 10.2 Disclosure and Public Consultation 10-1 10.3 Stakeholder’s Participation Process 10-1 11 Implementation Schedule 11-1 12 Monitoring and Evaluation
12.1 Monitoring and Evaluation 12-1 12.2 Internal Monitoring 12-1 12.3 Overall Implementation Mechanism 12-2 12.4 External Monitoring & Evaluation 12-3 12.5 Post Evaluation by JICA 12-14
iii
Table/ Figure No.
Page No.
Table 3-27 Skill Development Requests 3-25 Table 3-28 Outcomes of First PCM 3-26 Table 3-29 Major Comments from Participants and Responses by the Project Owner 3-26 Table 3- 30 Outcomes of Second PCM 3-28 Table 3-31 Major Comments from Participants and Responses by the Project Owner 3-29 Table 3-32 Outcomes of Third PCM 3-33 Table 3-33 Major Comments from Participants and Responses by the Representative of
Project Owner 3-33
Table 4-1 Anticipated Social Impact to 343 Households (Power Plant) 4-1 Table 4-2 Affected people and land owners at angle tower points 4-7 Table 4-3 Anticipated Social Impact to 41 Households (Township Site) 4-9 Table 4-4 Entitlement matrix for PAPs (power plant, port facility, transmission line and
Township Sites) 4-11
Table 5-1 Livelihood restoration measures 5-1 Table 6-1 Institutional Roles and Responsibilities 6-3 Table 9-1 Acquisition of private land from legal owners 9-1 Table 9-2 Acquisition of private land from tenants and lessee 9-1 Table 9-3 Acquisition of government land from legal tenants and lessee 9-2 Table 9-4 Acquisition of government land from occupants without legal tenure 9-2 Table 9-5 Assistance for transition in recovering loss of income source of land owners 9-2 Table 9-6 Assistance for transition in recovering loss of income from livelihood activities 9-2 Table 9-7 Assistance for transition in recovering loss of income from own business or self-
employment 9-3
Table 9-8 Assistance for transition in recovering loss of income from residential / commercial structure
9-3
Table 9-9 Assistance for transition in recovering loss of income from livelihood means 9-3 Table 9-10 Assistance for transition in recovering loss of trees 9-4 Table 9-11 Compensation for PAPs at power plant site 9-4 Table 9-12 Anticipated Land Acquisition and Assistance 9-5 Table 9-13 Compensation for PAPs at power plant site 9-5 Table 9-14 Compensation for PAPs at power plant site 9-6 Table 9-15 Acquisition of private land from legal owners 9-6 Table 9-16 Assistance for restoration in recovering loss of income from livelihood activities 9-7 Table 9-17 Assistance for transition in recovering loss of income from livelihood means 9-7 Table 9-18 Compensation for PAPs at Township Site 9-8 Table 12-1 Potential Monitoring Indicators 12-2 Table 12-2 Contents of environmental management plan and monitoring plan 12-4 Table 12-3 Monitoring Form 1(for Performance Monitoring of Resettlement Action Plan) 12-6 Table 12-4 Monitoring Form 2 (for Impact Monitoring during Project Implementation) 12-9 Table 12-5 Monitoring Form 3 (for Impact Monitoring at Post-project Stage) 12-12 Figure 1-1 Location of the Power Plant 1-3 Figure 1-2 Route of the proposed transmission line 1-4 Figure 1-3 The Location of access roads 1-5 Figure 1-4 Location Map of Township Area 1-6 Figure 3-1 Length of Time Residing at the Site 3-4 Figure 3-2 Household Size 3-4 Figure 3-3 Types of Illness 3-6 Figure 3-4 Household Monthly Income 3-8 Figure 3-5 Household Monthly Expenditure 3-8 Figure 3-6 Average Expenditure Patterns 3-8 Figure 3-7 Ratio of Household Head’s Per Capita Monthly Income and Expenditure 3-10 Figure 3-8 Household Assets 3-10 Figure 3-9 Water Sources 3-11 Figure 3-10 Type of Toilet 3-12 Figure 3-11 Source of Information 3-13 Figure 3-12 Examples of Pollution Experienced in the Past 3-13 Figure 3-13 Household Size 3-19 Figure 3-14 Household Monthly Income 3-21 Figure 3-15 Household Monthly Expenditure 3-21 Figure 3-16 Line graph of household Per Capita Monthly Income and Expenditure 3-22 Figure 3-17 Household Assets 3-22 Figure 3-18 Water Sources 3-23 Figure 3-19 Type of Toilet 3-24
iv
Table/ Figure No.
Page No.
Figure 3-20 Source of Information 3-24 Figure 3-21 Examples of Pollution Experienced in the Past 3-25 Figure 6-1 LARAP Implementation Organogram 6-2 Figure 6-2 Procedure for Determining Valuation of Property. 6-6 Figure7-1 Flow of Grievance Redress 7-2 Figure 11-1 Tentative Schedule for Land Acquisition and Resettlement 11-2 Figure 12-1 Implementation Mechanism of Land Acquisition and Resettlement 12-3
v
Abbreviation
AB Acquiring Body AC land Assistant Commissioner Land ADC (Rev) Additional Deputy Commissioner (Revenue) AH Affected Household AG Additional Grant AP Affected Person BBS Bangladesh Bureau of Statistics BBCS Bartika Beacon Consultancy Services Limited CACFPPDP Chittagong Area Coal Fired Power Plant Development Project CBE Commercial and Business Enterprise CCL Cash Compensation Under Law CUL Compensation Under Law CPR Common Property Resource CPGCBL Coal Power Generation Company Bangladesh Ltd. DAE Department of Agriculture Extension DAM Department of Agriculture Marketing DC Deputy Commissioner DOF Department of Forest/ Department of Fisheries DP Displaced Person DOE Department of Environment DSC Designed and Supervision Consultant EA Executing Agency EMA External Monitoring Agency EC Entitlement Card EP Entitled Person FGD Focus Group Discussion GOB Government of Bangladesh GRC Grievance Redress Committee GRM Grievance Redress Mechanism ha Hectare HH Household IA Implementing Agency ID Card Identity Card IGP Income Generating Program IGA Income Generating Activities LIRP Livelihood and Income Restoration Program IOL Inventory of losses IR Involuntary Resettlement JICA Japan International Cooperation Agency JVS Joint Verification Survey JVT Joint Verification Team km Kilometer LA Land Acquisition LAO Land Acquisition Officer LA&R Land Acquisition and Resettlement LARAP Land Acquisition and Resettlement Action Plan LGI Local Government Institution LGED Local Government Engineering Department LMS Land Market Survey M&E Monitoring & Evaluation MARV Maximum Allowable Replacement Value MIS Management Information System MOL Ministry of Land MOPERMR Ministry of Power, Energy & Mineral Resources NGO Non-government Organization
vi
NRS National Resettlement Specialist PAH Project Affected Household PGCB Power Grid Company of Bangladesh Limited PAU Project Affected Unit PCM Public Consultation Meeting PIU Project Implementation Unit PD Project Director PIB Public Information Brochure PMO Project Management Office PMU Project Management Unit PWD Public Works Department PRA Participatory Rapid Appraisal PPR Project Progress Report PVAT Property Valuation Advisory Team R&R Resettlement and Rehabilitation RAC Resettlement Advisory Committee/Regional Accounting Centre RB Requiring Body/ Resettlement Benefits RHD Roads & Highways Department RPC Resettlement Policy Framework RP Resettlement Plan RF Resettlement Framework RO Resettlement Officer ROW Right-of-Way RU Resettlement Unit RV Replacement Value RRP Revised Resettlement Plan SES Socio-economic Survey TA Technical Assistance TOR Terms of Reference VH Vulnerable Household VPAPs Vulnerable Project Affected Persons WB World Bank XEN Executive Engineer
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1
Glossary of Terms
Affected Person (AP): includes any person, affected households (AHs), firms or private institutions who, on account of changes that result from the project will have their (i) standard of living adversely affected; (ii) right, title, or interest in any house, land (including residential, commercial, agricultural, forest, and/or grazing land), water resources, or any other moveable or fixed assets acquired, possessed, restricted, or otherwise adversely affected, in full or in part, permanently or temporarily; and/or (iii) business, occupation, place of work or residence, or habitat adversely affected, with or without displacement.
Assistance: means support, rehabilitation and restoration measures extended in cash and/or kind over and above the compensation for lost assets.
Awardee: means the person with interests in land to be acquired by the project after their ownership of said land has been confirmed by the respective Deputy Commissioner's office as well as persons with interests in other assets to be acquired by the project. Compensation for acquired assets is provided to ‘awardees’ through notification under Section 7 of the Land Acquisition Ordinance.
Asset Inventory: A complete count and description of all property that will be acquired.
Compensation: means payment in cash or kind for an asset to be acquired or affected by a project at replacement cost at current market value.
Cut-off Date: This is the date on and beyond which any persons who encroach on the area are not entitled to compensation or any other form of resettlement assistance. It is often established on the commencement date or last date of the census of APs.
Encroachers: mean those people who move into the project area after the cut-off date and are therefore not eligible for compensation or other rehabilitation measures provided by the project. The term also refers to those extending attached private land into public land or constructed structure on public land only for renting out.
Entitlement: means the range of measures comprising cash or kind compensation, relocation cost, income restoration assistance, transfer assistance, income substitution, and business restoration which are due to AHs, depending on the type and degree /nature of their losses, to restore their social and economic base.
Eminent Domain: means the regulatory authority of the Government to obtain land for public purpose/interest or use as described in the 1982 Ordinance and Land Acquisition Law. Eligibility: The criteria for qualification to receive benefits under a resettlement program.
Grievance Procedures: The processes established under law, local regulations, or administrative decision to enable property owners and other displaced persons to redress issues related to acquisition, compensation, or other aspects of resettlement.
Household: A household includes all persons living and eating together (sharing the same kitchen and cooking food together as a single-family unit).
Household Survey: A complete and accurate survey of the project-affected population. The survey focuses on income-earning activities and other socioeconomic indicators.
Inventory of losses: means the pre-appraisal inventory of assets as a preliminary record of affected or lost assets.
Non-titled: means those who have no recognizable rights or claims to the land that they are occupying and includes people using private or public land without permission, permit or grant i.e. those people without legal title to land and/or structures occupied or used by them. JICA’s policy explicitly states that such people cannot be denied resettlement assistance.
Project Affected Unit: combines residential households (HHs), commercial and business
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
2
enterprises (CBEs), common property resources (CPRs) and other affected entities as a whole.
Project Affected Family: includes residential households and commercial & business enterprises except CPRS.
Project Affected Person (PAP): Any person (household) that loses their home, land, or business interests because of land acquisition.
Population Census: A complete and accurate count of the population that will be affected by land acquisition and related impacts. When properly conducted, the population census provides the basic information necessary for determining eligibility for compensation.
Relocation: means displacement or physical moving of the APs from the affected area to a new area/site and rebuilding homes, infrastructure, provision of assets, including productive land/employment and re-establishing income, livelihoods, living and social systems
Replacement cost: means the value of assets to replace the loss at current market price, or its nearest equivalent, and is the amount of cash or kind needed to replace an asset in its existing condition, without deduction of transaction costs or for any material salvaged.
Replacement Land: means the land affected by the project that is compensated through provision of alternative land, rather than cash, of the same size and/or productive capacity as the land lost and is acceptable to the AP.
Resettlement: means mitigation of all the impacts associated with land acquisition including restriction of access to, or use of land, acquisition of assets, or impacts on income generation as a result of land acquisition.
Resettlement Plan (RP) or Resettlement Action Plan (RAP): A resettlement plan (or resettlement action plan) is the planning document that describes what will be done to address the direct social and economic impacts associated with the involuntary taking of land.
Resettlement Entitlements: Resettlement entitlements with respect to a particular eligibility category are the sum total of compensation and other forms of assistance provided to displaced persons in the respective eligibility category.
Significant impact: means where 200 or more APs suffer a loss of 10% or more of productive assets (income generating) or physical displacement.
Squatters: means the same as non-titled and includes households, business and common establishments on land owned by the State. Under the project this includes land on part of the crest and slopes of canal dykes, flood control embankments, and similar areas of the drainage channels.
Structures: mean all buildings including primary and secondary structures including houses and ancillary buildings, commercial enterprises, living quarters, community facilities and infrastructures, shops, businesses, fences, and walls.
Socioeconomic Survey: The population census, asset inventory, and household survey together constitute the socioeconomic survey of the affected population.
Vulnerable Households: means households that are (i) headed by single woman or woman with dependents and low incomes; (ii) headed by elderly/ disabled people without means of support; (iii) households that fall on or below the poverty line (iv) losing last parcel of land (v) households of indigenous population or ethnic minority; and (vi) households of low social group or caste.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
3
A. Project Description
1. The proposed Chittagong Area Coal Fired Power Plant Development Project is an initiative to cope with a rapid increase in power demand in Bangladesh and supply power in a stable manner through the construction of a coal-fired power plant (2 x 600MW) in Chittagong Division in the southeast of Bangladesh.
2. To achieve the above objectives, the project components will be as follows: - construction of a coal-fired power plant (2 x 600MW) with ultra super critical technology
(Cox’s Bazar District) - construction of an excavated port including a fuel berth and a fuel transportation facility
to the power plant (Cox’s Bazar District) - construction of an access road (Cox’s Bazar District) - extension of a 400kV transmission line between Matarbari and Anowara (Cox’s Bazar
District and Chittagong District) - Construction of Township at Matarbari and Dhalghata union of Maheshkhali Upazila in
Cox's Bazar District.
3. Power plant and Port facility The proposed coal-fired power plant (CPCG Matarbari Coal-Fired Power Plant, 2 x 600MW) is located in Matarbari Union and Dhalghata Union in Maheshkhali Upazila in Cox’s Bazar District, Chittagong Division .
4. Transmission line The power plant will be connected to the substation facility in Anowara power plant, which will be constructed in the south of Chittagong, with a 400kV transmission line of approximately 60km. The transmission line will take a route along the local road . As land for construction of the transmission towers are subject to compensation, the final route will be determined so as to avoid any residential areas, taking into account the firmness of the land foundation.
5. Access Road The location and route of access road is in the area from the national highway running between Chittagong and Cox’s Bazar to the power plant site. Basically, existing road facilities will be utilized wherever possible. It is envisioned that the route segments to join the national highway in the north and the route from Maheshkhali Island to the power plant site will involve new road and bridge construction.
6. Township The proposed Township for building residential quarters and other facilities for staff is located at Matarbari and Dhalghata Union in Maheskhali Upazila, Cox's Bazar District, Chittagong Division
B. Objective
7. The Land Actuation and Resettlement Action Plan (LARAP) is prepared for large scale land acquisition and to address involuntary resettlement impacts with a time bound action plan and appropriate budget provisions that would be incorporated as an integral part of project design. The LARAP is based on the principle of the JICA Guidelines for Environmental and Social Considerations that development projects must serve the needs of the society and ensure that PAPs are not made worse off by the proposed intervention. It aims to clarifying resettlement principles, organizational arrangements, and design criteria to be applied to the Project. It also addresses and fills the gap between the existing legislations of Bangladesh and the JICA Guidelines. In response to the above principle, involuntary resettlement should
Executive Summary
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4
be an important consideration in project identification. Three important elements of involuntary resettlement are: 1) compensation for loss of assets, loss of income sources and livelihood means; 2) assistance for relocation including provision of relocation sites with appropriate facilities and services, and; 3) assistance for rehabilitation to achieve at least the same level of well-being. As warranted by policy requirement of JICA for involuntary resettlement the extent of losses has been identified and depending on estimation of losses LARAP is prepared.The LARAP will be translated into Bengali Language and disclosed for the reference of PAPs as well as other interested groups.
C. Methodology
8. Both the primary and secondary sources of information are used to prepare the Land Acquisition Resettlement Action Plan (LARAP) document. Primary data has been collected through holding 3 stakeholders meeting first one at Puran Bazar Government Primary School, Matarbari , Second meeting at Chakaria Upzila Parishad Auditorium and the third one at Matarbari Union Parishad Hall Room. Census and Socio Economic Survey, asset inventory, households survey and market survey of land, trees and structure have been conducted and focus group discussion held to gather primary information and develop a comprehensive socio-economic profile of AHs which contributed to provide primary data for preparation of the LARAP. In collecting secondary data the following legislation and policies have been overviewed and harmonized through gap analysis amongst them and made identification of gap – filling measures:
i. Relevant GOB legislation on land acquisition. ii. World Bank Operational Policies. iii. The Asian Development Bank (ADB) Safeguard Policies. iv. Japan International Agency (JICA) guideline for Environmental and Social
Considerations.
9. The study of “Best Practices” in resettlement of affected persons in Jamuna Multi Purpose Bridge Project and Padma Multi Purpose Bridge Project and related reports, documents, Resettlement Frame Works, Land Acquisition, Resettlement Action Plans, Social Action Plans for Involuntary Resettlement of Affected Persons and Environmental and Social Impact Assessment Report have also contributed to the preparation of this document. Moreover, LARAP/RAPs implemented by BWDB, RHD, LGED and Bridge Division have also been consulted and policy guidelines, institutional arrangements and entitlements for different kinds of losses stipulated in those LARAP/RAPs have been given due consideration. In order to enrich the socio- economic profile of the affected household Income and Expenditure Survey (HIES) 2010 report of Bangladesh Bureau of Statistics has been utilized.
D. Legal Frame work, Policy Commitments and Entitlements
10. As the Bangladesh legal system on mitigation of the loss of land and other assets remains focused on compensation payment of loss of assets to title holders and provides no compensation to APs without title, gaps between national laws and JICA Safeguard policies are identified and bridging measures and lessons learned from best practices in involuntary resettlement issues have been outlined in policy commitments.
11. The project policy commitments have been orchestrated to compensate lost assets and restore or improve livelihood of all categories of APS affected directly or indirectly with titles and without titles. The affected people will be entitled to cash compensation for land and other assets at replacement value if land assets cannot be replaced. Additional assistance also will be paid as resettlement benefits that include shifting/ reconstruction allowance, assistance for small business reestablishment, livelihood restoration and special assistance to female headed households and vulnerable groups.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
5
E. Entitlement Matrix
12. Based on the findings and analyses in the field surveys, the entitlement matrix for the PAPs at the construction site of power plant and port facility, and transmission line route and township site has been prepared. The Entitlement Matrix lists 10 types of losses and category of entitled persons and corresponding proposed entitlements to cover all possible losses to achieve at least the same level of livelihood of the affected households. Entitlement Matrix are as in the table below:
Table 1: Entitlement matrix for PAPs (power plant, port facility , transmission line and Township Sites)
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
1. Loss of private land
Legal owners of land � Cash compensation under the law (CUL) for all the private land stipulated by the Ordinance 1982 is the average of last 12 months’ sales values of same kind of land X 1.5 (50% premium). Cash grant that covers the difference between CUL and the replacement value (RV)
� Provision of stamp duty, land registration fee incurred for replacement land (15%)
� value added tax � One-time assistance for lost
income (based on monthly income for three years at minimum wage rates)
DC PVAT, JVT CPGCBL
Tenants and leaseholders
� Provision of another land including 50% premium
� Provision of stamp duty, land registration fee (15%) If land is purchase by the compensation money
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
2. Loss of government land including khas land
Tenants and lessee � Provision of another khas land (assuming tenants and lessee will seek private land, 50% premium is added)
� Provision of stamp duty, land registration fee (15%) If land is purchase by the compensation money
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
DC PVAT, JVT CPGCBL
Occupants without legal tenure
� Provision of another khas land (assuming tenants and lessee will seek private land, 50% premium is added)
� Provision of stamp duty, land registration fee (15%) If land is purchase by the compensation money
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
3. Permanent loss of means of livelihoods/ source of income
� Lessor (land owners who rent their land will lose income from land lease contract)
� One-time assistance for opportunity loss (based on the lease amount) (assuming the inflation rate stays 10%)
DC, DOF PVAT, JVT CPGCBL
� Permanent laborers
� Temporary laborers
� Sharecroppers
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
� Enrollment in vocational training courses based on assessment of skills (@300 taka / day for 120 days)
Businessmen, employers of salt farms, shrimp farms and fishing sites, self-employed people
� One-time assistance for opportunity loss (based on the lease amount) (assuming the inflation rate stays 10%)
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
4. Loss of residential/ commercial structures
Legal title holders Owners of structures
� Cash compensation for affected portion of the structure and other fixed assets at replacement cost ( plus 50% premium)
� Option to be compensated for entire structure if remaining structure is no longer viable
� Provision of all taxes, registration costs and other fees incurred for replacement structure (15%)
� Reconstruction grant for reconstruction / repair of the remaining structure (@15 taka / sft)
� Shifting allowance based on actual costs of moving (@10 taka / sft)
� Owners to take away all salvage materials
DC PVAT, JVT, PWD CPGCBL
Legal tenants/ lease holders of the structure
� Cash compensation equivalent to replacement cost of structure (or part of structure) for the portions of the structure constructed by the tenant/ leaseholder (plus 50% premium)
� Reconstruction grant for reconstruction / repair of the remaining structure (@15 taka / sft)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
7
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
� Shifting allowance based on actual cost of moving (@10 taka / sft)
� Owners to take away all salvage materials
Socially recognized owners/ unauthorized occupants
� Cash compensation equivalent to replacement cost of structure (or part of structure) erected by the displaced person (plus 50% premium)
� Reconstruction grant for reconstruction / repair of the remaining structure (@15 taka / sft)
� Shifting allowance based on actual cost of moving (@10 taka / sft)
� Owners to take away all salvage materials
5. Loss of access to Residential/ Commercial Structures
Tenants of rented leased properties (but not constructed the whole part of the structure
� One time cash grant for facilitating alternative housing/ CBEs TK. 15000/= per household
� Shifting allowance per household based on family members @ 3000/= per member minimum Tk. 9000/= maximum 12000/=
PVAT CPGCBL
6. Loss of standing crops at home gardens, shrimp, and fish
Land owners, Bargadar, Lessee and Unauthorized occupant of land
� One time assistance for opportunity loss (based on the lease amount) (assuming the inflation rate stays 10%)
DC PVAT, DOF,DAM CPGCBL
7. Loss of timber and fruit bearing trees
Legal owner of land/Socially recognised owner
� Market value of trees � Owner will be allowed to fell and
take away their trees
DC PVAT, BFD,DAM CPGCBL Non-titled user of
land
8. Temporary loss of land during construction
Owners with legal title, tenants, leaseholders
� Rental assistance for the period for which the land is temporarily requisitioned
� Temporarily requisitioned land will be returned to owners rehabilitated to original or preferably better condition
DC PVAT CPGCBL
9. Temporary loss of access to land, structure, utilities, common property resource during
Owners with legal title, tenants, leaseholders
� Provision of temporary access and relocation where possible
� Restoration of access to the land, structure, utilities
DC PVAT CPGCBL
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
8
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
construction
10. Temporary loss of livelihood/ source of income during construction
Business owners, tenants, leaseholders, employees, vendors
� One-time assistance for lost income based on monthly income for three years from products, minimum wage rates or based on actual income, verified through incomes of comparable businesses in the area
DC, DOF, DAM CPGCBL
(Source: JICA Study Team)
E. Consultation, Participation & Disclosure
13. The project recognizes the importance of consultation. It has arranged consultation with agriculture farmers, shrimp and salt cultivators agriculture land losers, fisherman, service holders, local traders, employees of commercial and business enterprise, vulnerable groups, women headed households and other stakeholders like teachers, imam, local community leaders, retired govt. officials, UP chairman/ members, EA, policy makers, donor and other government agencies concerned. Consultation should include disclosure of projects components, adverse impacts, compensation, resettlement, relocation issues and safeguard policies contained in LARAP. 12. This process will be continuing from the initial stage through the detailed design, land acquisition process and up to the end of implementation and monitoring of the LARAP. This participatory approach can ensure transparency and accountability and bring in positive outcome.
F. Grievance Redress Mechanism
14. The project will establish a grievance redress mechanism to resolve discontentment of the APs. Grievance will be settled with their full representation in the Grievance Redress Committee constituted by the Administrative Ministry (MOPEMR) with representative from EA, district administration, upzila administration, IA, local elected representative and representative of APs and legal advisers. The committee will meet regularly and keep record of the decisions taken. Grievances regarding titled land will be referred to the appropriate court of law for resolution.
G. Income Restoration Strategy 15. Vulnerable Project Affected Households (PAHs) including poor and female headed, elderly headed, the landless, the poor as well as PAHs losing productive assets will be given additional support for livelihood and income restoration. Long-term income restoration and livelihood reconstruction program will be designed in the form of Livelihood and Income Restoration Program (LIRP) for rehabilitation of the vulnerable PAHs by the Implementing Agency.
H. Implementation Arrangement
16. Coal Power Generation Company of Bangladesh Limited will establish, for the Project, a Project Management Unit (PMU) headed by a Project Director (PD) that will be responsible for the overall execution of the project including land acquisition, relocation, resettlement and other related matters. The PD will recruit and appoint an experienced Implementing Agency (NGO/Social Consulting Firm) as required for implementation of resettlement activities. The Executive Engineer, under the overall responsibility of the Project
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9
Director, will undertake day-to-day activities with the appointed Implementing Agency. Resettlement Advisory Committee (RACs) will be chaired by Assistant Engineer or equivalent officers and seek local inputs from the APs, communities in the implementation process of LARAP. Grievance redress committee will work for resolution of disputes. Grievance Redress Mechanism is detailed in Section 7 Joint Verification Team (JVT) and Property Valuation Advisory Team (PVAT) will be chaired by the Executive Engineer. JVT will compare and review the physical verification data conducted by the implementing Agency with DC's assessment of loss of physical assets and quantity of the loss assets corresponding to their owners and prepare final list of affected owners. PVAT will review the assessment of the market price of land and other properties by IA and determine their replacement cost.
I. RP Implementation Schedule
17. A time bound implementation Schedule for the LARAP is prepared synchronized with project construction schedule. The LARAP implementation will be complete within 4 years. The overall schedule of implementation is based on the principle that resettlement benefits are paid to AHs before they are displaced and civil engineering works takes off.
J. Budget
18. All Resettlement funds will be provided by the EA based on the financing plan agreed by the Government and JICA. The budget included the following heads of expenditure:
i. Detailed costs of land acquisition, structure, trees, relocation and livelihood and income restoration and improvement.
ii. All training costs for the APs.
19. All costs associated with land acquisition & rehabilitation will be funded by GOB. At this initial stage it is not practicable to accurately estimate land acquisition and costs of resettlement benefits for the project. However, a provisional estimate of LARAP implementation costs for the project is provided based on Census and SES of Project Affected Persons and Market Survey of land, trees and structure (likely to be affected). However an indicative budget of land acquisition and compensation along with resettlement assistance (including restoration of livelihood and income sources) for the affected people of the project with breakup of each component are place below:-
Component Estimated Budget BDT (million)
1. Power Plant and Port Facility 3864
2. Transmission Line/ Angle Tower Location 3.1
3. Township Development 130.35
Total Budget 3997.45
J. Monitoring and Evaluation 20. The Project Management Unit will establish a monitoring system involving the Resettlement Unit, Project Supervision Consultant (PSC), and LARAP Implementing Agency for collection, analysis of and reporting on information about the progress of resettlement activities. Monitoring will also be done externally by an external monitoring agency/ resettlement specialist appointed by EA. The External Monitor will monitor and evaluate project activities intermittently over the project period and submit quarterly reports and a final evaluation report to EA and JICA after completion of the LARAP implementation.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-1
Section-1
Rationale
1.1 Objectives
Out of the project components of Chittagong Area Coal Fired Power Plant Development Project, this Land Acquisition and Resettlement Action Plan (LARAP) is being prepared for a large-scale land acquisition and resettlement under the construction of power plant and port facility and Township for accommodation of staff in Matarbari and Dhalghata Union of Maheshkhali Upazila in Cox’s Bazar District, and extension of transmission line from Maheshkhali Upazila to Anowara Upazila of Chittagong District.
The LARAP is based on the principle of the JICA Guidelines for Environmental and Social Considerations that development projects must serve the needs of the society and ensure that PAPs are not made worse off by the proposed intervention. It aims to clarifying resettlement principles, organizational arrangements, and design criteria to be applied to the Project. It also addresses and fills the gap between the existing legislations of Bangladesh and the JICA Guidelines. In response to the above principle, involuntary resettlement should be an important consideration in project identification. Three important elements of involuntary resettlement are: 1) compensation for loss of assets, loss of income sources and livelihood means; 2) assistance for relocation including provision of relocation sites with appropriate facilities and services, and; 3) assistance for rehabilitation to achieve at least the same level of well-being. As warranted by policy requirement of JICA for involuntary resettlement the extent of losses has been identified and depending on estimation of losses LARAP is prepared.
The LARAP will be translated into Bengali language and disclosed for the reference of PAPs as well as other interested groups. 1.2 Project Description
The proposed Chittagong Area Coal Fired Power Plant Development Project is an initiative to cope with a rapid increase in power demand in Bangladesh and supply power in a stable manner through the construction of a coal-fired power plant (2 x 600MW) in Chittagong Division in the southeast of Bangladesh.
1.3 Project Components. To achieve the above objectives, the project components will be as follows: - construction of a coal-fired power plant (2 x 600MW) with ultra super critical technology
(Cox’s Bazar District) - construction of an excavated port including a fuel berth and a fuel transportation facility
to the power plant (Cox’s Bazar District) - construction of an access road (Cox’s Bazar District) - extension of a 400kV transmission line between Matarbari and Anowara (Cox’s Bazar
District and Chittagong District) - Construction Township at Matarbari and Dhalghata union of Maheshkhali Upazila in
Cox's Bazar District.
1.4 Location of the proposed site
(1) Power plant and Port facility The proposed coal-fired power plant (CPCG Matarbari Coal-Fired Power Plant, 2 x 600MW) is located in Matarbari Union and Dhalghata Union in Maheshkhali Upazila in Cox’s Bazar District, Chittagong Division (Figure 1-1).
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-2
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-3
Source: http://www.in2bangla.com/upazilaMap.phpid=293 (accessed in March 2013) Note: The location is 21 42’15” N, 91 53’16” E
Figure 1-1 Location of the Power Plant
(2) Transmission line The power plant will be connected to the substation facility in Anowara power plant, which will be constructed in the south of Chittagong, with a 400kV transmission line of approximately 60km. The transmission line will take a route along the local road (R-170) as shown in Figure 1-2. As land for construction of the transmission towers are subject to compensation, the final route will be determined so as to avoid any residential areas, taking into account the firmness of the land foundation.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-4
(Source: JICA Study Team)
Figure 1-2 Route of the proposed transmission line
Table 1-1: Area covered by the proposed transmission line District Upazila Union
Chittagong
Anowara Barasat
Burumchhara
Banshkhali
Khankhanabad
Baharchhara
Kalikapur
Boilchori
Banshkhali
Sheakerkhil
Fulchari
Cox's Bazar Pekua
Bara Bakia
Pekua
Ujantia
Maheshkhali Matarbari
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-5
(Source: JICA Study Team)
(3) Access Road The location and route of access road is shown in Figure 1-3. The route of access road is in the area from the national highway running between Chittagong and Cox’s Bazar to the power plant site. Basically, existing road facilities will be utilized wherever possible. It is envisioned that the route segments to join the national highway in the north and the route from Maheshkhali Island to the power plant site will involve new road and bridge construction.
Figure Error! No text of specified style in document.-3 The location of access roads
Figure 1-3 The Location of access roads
(4) Location of Township
The proposed area of around 20 hectors is designated for a township consisting of
residential quarters for staff, medical facilities, school & college, shopping center,
staff club and recreational park. The 132/11 KV substation for electrification of
Matarbari area as well as to provide power to the township will be located within this
land (20hectors) adjacent to the township.
(Source: RHD web-site)
National Highway Regional Road
Power plant
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-6
Figure: 1-4 Location Map Township Area (Source: Socio-economic Survey Team)
1.5 Methodology for preparing LARAP
Both the primary and secondary sources of information are used to prepare the Land Acquisition Resettlement Action Plan (LARAP) document. Primary data has been collected through holding 3 stakeholders meeting first one at Puran Bazar Government Primary
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-7
School, Matarbari, Second meeting at Chakaria Upzila Parishad Auditorium and the third one at Matarbari Union Parishad Hall Room. Census and Socio Economic Survey, asset inventory, households survey and market survey of land, trees and structure have been conducted and focus group discussion held to gather primary information and develop a comprehensive socio-economic profile of AHs which contributed to provide primary data for preparation of the LARAP. In collecting secondary data the following legislation and policies have been overviewed and harmonized through gap analysis amongst them and made identification of gap – filling measures:
i. Relevant GOB legislation on land acquisition. ii. World Bank Operational Policies. iii. The Asian Development Bank (ADB) Safeguard Policies. iv. Japan International Agency (JICA) guideline for Environmental and Social
Considerations.
The study of “Best Practices” in resettlement of affected persons in Jamuna Multi Purpose Bridge Project and Padma Multi Purpose Bridge Project and related reports, documents, Resettlement Frame Works, Land Acquisition, Resettlement Action Plans, Social Action Plans for Involuntary Resettlement of Affected Persons and Environmental and Social Impact Assessment Report have also contributed to the preparation of this document. Moreover, LARAP/RAPs implemented by BWDB, RHD, LGED and Bridge Division have also been consulted and policy guidelines, institutional arrangements and entitlements for different kinds of losses stipulated in those LARAP/RAPs have been given due consideration. In order to enrich the socio- economic profile of the affected household of the project is developed largely based on information drawn from Census Report 2011 and Household Income and Expenditure Survey (HIES) 2010 prepared by Bangladesh Bureau of Statistics has been utilized.
1.6 Brief Description of Social Impacts.
1.6.1 Brief Description.
Among the above project components, the CPGCBL will acquire 455 ha of land for the construction of a coal-fired power plant and 20ha of land for development of Township. PGCB will acquire 157 locations for tower erection, and RHD will acquire 3.1 ha of land for bridge and road construction as shown in the following table:
Table 1-2: Anticipated Land Acquisition
Project Component Implementing Agency
Acquired Land
Location Area (Ha)
(1) Power Plant and Port Facility
CPGCBL Matarbari Union and Dhalghata Union of Maheshkhali Upazila (Cox’s Bazar District)
455
(2) Transmission Line PGCB 157 locations for tower erection from Anowara Upazila (Chittagong District) to Maheshkhali Upazila (Cox’s Bazar District)
0.13
(3) Access Road RHD Matarbari Union, Dhalghata Union and Kalarmarchara Union of Maheshkhali Upazila (Cox’s Bazar District)
3.1
(4) Township Development
CPGCBL Matarbari and Dhalghata Union, Maheshkhali Upazila, Cox’s Bazar District.
20.00
Total 478.23
(Source: JICA Study Team)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-8
1.6.2 Anticipated Impact by Power Plant and Port Facility Construction
At the site where the power plant and port facility are to be constructed, there are 343 households (2,031 members in total) who will be directly affected by the project implementation. These households own, rent or use private land within the site. There are certain households who rent or occupy government land for salt and shrimp cultivation. In addition, there are squatters living on government land without legal tenure, most of whom live along with the dyke road. About 70% of these 343 households’ heads that will be directly or indirectly affected are working in salt or shrimp farms as laborers, mazi, businessmen or cultivators. They conduct salt, shrimp and fish cultivation by employing laborers. They run salt and shrimp business. Some of them are involved in agriculture, boat business, tea selling and construction as carpenters. Apart from such land owners and users, there are also permanent and temporary laborers employed by them. Including laborers from outside, there are 165 permanent and 892 temporary employees involved in shrimp cultivation, salt farming, fishing activities and others. There are also twelve sharecroppers.
Table 1-3: Anticipated Impact (Power Plant and Port Facility)
No of household No of household members
Anticipated impact
343 2,031 - Lose land ownership to private land: 237 HHs - Lose shelters on their private land and will be physically displaced: 4 HHs - Lose tenant rights to private land: 77 HHs - Lose tenant rights to government land: 10 HHs - Lose occupancy of land to government land: 156 HHs - Lose occupancy of government land for living place: 16 HHs - Permanent loss of means of livelihood / sources of income: 34 HHs+ - Loss of standing crops at home gardens, shrimp and fish: 499 HHs - Loss of timber and fruit bearing trees: 274 HHs (Note) Numbers of HHs are all cumulative.
- 165 Permanent employees involved in shrimp cultivation, salt farming, fishing activities and others
- 892 Temporary employees involved in shrimp cultivation, salt farming, fishing activities and others
- 12 Sharecroppers of agriculture
(Source: JICA Study Team)
Total amount required for land acquisition, resettlement, and assistance for transition that includes the restoration of livelihood and income sources are 3.86 billion taka.
1.6.3 Anticipated Impact caused by the Extension of Transmission Line There will be 1,256 m2 of land required for the installation of tower bases as shown in the following table. Each tower will require 8 m2 for its base. There will be 157 towers for both angle towers and suspension towers from Anowara Upazila to Maheshkhali Upazila.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-9
Table 1-4: Breakdown of Land Acquisition (Transmission Line)
Tower Area (Per Tower)
Tower Base Area (Per Tower)
Acquired Land
Per Tower No. of Towers Total Area
11.1m x 11.1m 2m2 x 4 8 m
2 157 1,256 m
2
(Source: JICA Study Team)
The anticipated impact on the land owners will not last permanently or be critical, as the land area for tower bases are relatively small, and land owners’ livelihood activities will be hindered only during the construction period. The table below shows the anticipated impact on the owners of the angle tower locations from P1 to P10. There are no people living or using the P10 location (government land).
Table 1-5: Anticipated Impact on the Owners of Angle Tower Locations
Category Impact No. of HH No. of HH Members
Owners of private land (P1 to P8)
- Temporarily affected during construction period
8 83
Users of Government land with official agreement (P9)
- Temporarily affected during construction period
1 9
Total 9 92
(Note) There are no people living or using the P10 location (government land). (Source: JICA Study Team)
Total amount required for land acquisition of tower locations and compensation for the affected people is 3 million taka.
1.6.4 Anticipated Impact Caused by the Development of Township Site. At the designated area for township development, there are 41 HHs having 207 members in
all who will be directly affected by the project. Of 41 HHs, 14 (34.15%) HHs are salt and
shrimp cultivators. They are the owners and or lessees of salt/shrimp fields who invest
money in salt/shrimp cultivation. 8 among 14 cultivators belong to Matarbari Union and rest 6
cultivators are from Dhalghata union. There are also 14 businessman and among them 10
hail from Dhalgata and 4 from Matarbari. 3 HH heads from Dhalgata and 2 HH heads from
Matarbari are engaged in farming. Of the 41 total HH heads 5 are self -employed in
household activities and 3 are doing service.
Apart from such land owners and users, there are also permanent and temporary laborers employed by them. Including laborers from outside, there are 12 permanent and 52 temporary employees involved in shrimp cultivation, salt farming, fishing activities and others.
Table 1-6: Anticipated Impact of Township Development
No of household No of household members
Anticipated impact
41 207 - Lose land ownership to private land: 41 HHs - Permanent loss of means of livelihood / sources of income: 19 HHs+ -
- 12 Permanent employees involved in shrimp cultivation, salt farming, fishing activities and others
- 52 Temporary employees involved in shrimp cultivation, salt farming, fishing activities and others
(Source: Socio-economic Survey, 2013)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-10
Total amount required for land acquisition resettlement and assistance for rehabilitation livelihood restoration and income sources is BDT 130.35 million.
1.7 Specific Measures Taken to Minimize Adverse Impacts
1.7.1 Examination of Alternatives
For the construction of power plant and port facility, there had been two alternative locations for the CPGCBL to consider. One was the located 2 km south from the present one on Matarbari Island, and another on Maheshkhali Island. Large settlements with thousands of people on private lands were found on the first location (administrative location was Dhalghata Union), which required large-scale land acquisition and resettlement. In order to minimize such issues, the present site was discovered, which is located right on the north next to it. Although resettlement was indeed minimized (around 20 households), construction at the present site will cause losses of private land, livelihood and income sources such as salt and shrimp farming were still anticipated. Another alternative site on Maheshkhali Island (administrative location was Hoanak Union) was also considered. However, while no resettlement was anticipated, this was projected to lead to similar losses, i.e., losses of private land, livelihood and income sources such as salt and shrimp farming, and agriculture. The degree and scale of such adverse impacts remained same as the present one. After thorough analyses from numerous aspects, not only from social aspect but from environmental, financial, technical aspects, the present location was finally prioritized and accepted.
As per transmission line route between the expected Anowara substation site and the planned coal-fired power plant site in Matarbari, there were two candidates: one along the National Highway No. 1 (“N1”) and the other along Regional Road No. 170 (“R170”). As a result of route selection, the route in the western side of the “R170” running parallel to the “R170” was selected for this project. This route can avoid crossing with the planned transmission line between Maheskhali power station and Anowara substation in the future and secure space for the transmission line route. There is no reserve forest and existing extra high voltage transmission line to be crossed over in this area and the “R170” allows for relatively easy construction and maintenance work. The terrain surrounding the route is mostly flat area and covered with bushes, farmlands and salt fields. A route in parallel with the “N1” was found unsuitable because there are reserve forests and an existing 132 kV transmission line along the “N1” and the total route length increases up to approximately 80 km.
Regarding selection of site for Township development the rationale is that the township will be built for residential accommodation of the officials and staff of the power plant on an area of 20 ha land at Matarbari and Dhalgata Union of Maheskhali Upazila. It was selected after thorough analyses of various aspects. The proposed township needs to house residential and other facilities of schooling and medical treatment and related civic amenities for a huge number of officials, staff and employees of the power plant (and port facility) and to be constructed on the land adjacent to power plant. Most importantly social and environmental aspect and easy and quick travelling of the officials and staff from residence to work place and back were given due weightage. And also financial and other technical aspects were given due consideration and finally the present site of township was accepted.
1.7.2 Application of International Standards to Land Acquisition and Resettlement
As stipulated in the Acquisition and Requisition of Immovable Property Ordinance 1982, the CPGCBL will submit an application of land acquisition to the Government of Bangladesh (GOB), with sufficient data and information about the project design and cost, through the Deputy Commissioner (DC) of Cox’s Bazar. As this project will be financed by the Government of Japan, the CPGCBL will allocate its budget to fill the gap between the
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-11
Ordinance 1982 and JICA Guidelines for Environmental and Social Considerations in order to compensate not only titleholders but also non-titleholders for their loss of land ownership, relocation, and loss of their livelihood means in an internationally accepted manner. The DC Office will follow all the official procedures to acquire land and provide compensation as stipulated in the Ordinance 1982. It will take over eight months to complete all the procedures from the CPGCBL’s application to the payment of compensation through the DC Office to the project affected persons (PAPs).
1.7.3 Entitlements of Affected People without Legal Claims to Land
Lack of ownership does not imply ineligibility for compensation, if the JICA Guidelines and other internationally accepted practices are to be followed. CPGCBL will endeavor to provide suitable alternatives to resettle the squatters or to provide cash compensation on a replacement cost basis. PAPs that lose only a part of their physical assets will not be left with a portion that is inadequate to sustain their current standards of living. The minimum size of the remaining land and structures will be agreed to during the resettlement planning process. People temporarily affected will also be considered PAPs and resettlement plans shall address the issue of temporary acquisitions.
1.7.4 Measures for Avoidance and Further Influx of Illegal Occupation
All PAPs residing, working, doing business and/or cultivating land within the project impacted areas upon the cut-off date, will be entitled to compensation for their lost assets (land and/or non-land assets), at replacement cost, if known, and the restoration of incomes and businesses. Compensation will be provided with rehabilitation measures sufficient to assist the PAPs to improve or at least maintain their pre-project living standards, income-earning capacity and production levels. In the Project, the cut-off date for titleholders will be the date of notification under Section 3 of the Ordinance of 1982. For non-titled holders, CPGCBL declared a cut-off date on the last day of the population census (December 28, 2012) and on the occasion of organizing 2nd public consultation meeting (February 13, 2013). For Township cut off date would be October 1,2013. CPGCBL intended to fix the number of households and their members who occupy the government land without permission so as to limit encroachment for the purpose of qualifying for entitlement. CPGCBL will also take appropriate measures to ensure that all land cleared for the project remains clear of squatters.
1.7.5 Methods of Valuing Affected Assets All compensation for land and non-land assets owned by any households/shop owners who met the cut-off-date will be based on the principle of replacement costs. Replacement costs are the amounts calculated before displacement which are needed to replace any affected assets without depreciation and without deductions for taxes and/or costs of transaction. The Deputy Commissioner (DC) follows the rules laid down in the 1982 Ordinance to determine market prices for assets like land, structures trees and crops, with assistance from other relevant departments such as Public Works Department (PWD) for structures, Divisional Forest Office for trees, and Departments of Agricultural Extension for yields and Department of Agriculture Marketing for crop prices. The assessed value is typically lower than the replacement costs. To ensure that the project-affected persons can replace the lost property, replacement value will be determined by the Property Valuation Advisory Team (PVAT) constituted by Ministry of Power, Energy and Mineral Resources with representatives from CPGCBL, DC office concerned, and representative of implementing agency and finally approved by the CPGCBL.
1.7.6 Livelihood Restoration and Rehabilitation
The livelihood restoration and improvement program are based on consultation with PAPs and their socio-economic profile, living environment, level of education. Vulnerable project Affected household including poor and female headed, elderly household, the landless, the
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
1-12
poor as well as PAHs losing productive assets will be given additional support for livelihood and income restoration like vocational training, microfinance, and provision of job opportunities at the construction sites and new facilities. Long term income restoration and livelihood reconstruction program will need to be designed in the form of livelihood and income restoration program (LIRP) for rehabilitation of vulnerable and poor households by the implementing agency.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
2-1
Section-2 Legislations in Bangladesh and GAPs From JICA's Policy
2.1 Key Legislations The Acquisition and Requisition of Immovable Property Ordinance of 1982 and its subsequent amendments in 1993 and 1994 provide the key legal instrument for the acquisition of private land for development activities in Bangladesh. Salient provisions of the Ordinance which show tangible gaps with the JICA Guidelines for Environmental and Social Considerations are as follows:
Avoiding/ minimizing land acquisition: The Ordinance only implicitly discourages unnecessary acquisition as land acquired for one purpose cannot be used for a different purpose. There are, however, no mechanisms to monitor if this condition is actually adhered to.
Eligibility for compensation: The Ordinance stipulates compensation only for the persons who appear in the land administration records as the owners (i.e., titleholders). It does not recognize the rights of those without legal title to the land, who live in or make a living from it.
Compensation paid for: The Ordinance provides for compensation of land and other objects built and grown on it (structures, trees and orchards, crops and any other developments on the land like ponds, built amenities, etc.). There are no provisions to assess and restore lost income streams or income sources caused by the land acquisition to the PAPs.
Compensation standards: Landowners receive compensation under the law (CUL) as per the market value of the property at the publication date of the notice1 with a premium of 50% on the assessed price. Any damage to standing crops or trees on the property, expenses incidental to compelled changes to the residence or place of business, and reduction of profits of the property in the acquisition period are also entitled to a sum of 50% on top of such market value 2 . The 1994 amendment made provisions for payment of crop compensation to tenant cultivators (“bargadar”). Although the Ordinance stipulates ‘market prices’ of the acquired land as just compensation, the legal assessment method almost always results in prices far below the actual market prices. Certain pricing standards, which are regarded as unrealistic, are used to assess other losses like structures and various built amenities, trees, and crops, etc.
Relocation of homestead losers: There is no legal obligation to relocate, or assist with the relocation of, those whose homesteads have been acquired.
Ensuring payment/ receipt of compensation: Even with the given legal provision, the compensation process is time-consuming. There is, moreover, no certainty as to when an affected landowner will obtain the stipulated compensation or whether he will obtain it at all. Land is legally acquired and handed over to the project proponent as soon as the acquisition authority identifies the owners (‘awardees’) by examining the records, and sends a legal notice advising them to claim compensation (‘awards’). And it also turns out that it is an obligation of the PAPs to prove that the acquired land legally belongs to them.
Socio-economic rehabilitation: The provisions are so restricted that the Ordinance shows no concern about the long-term socio-economic changes the PAPs might undergo in the post-acquisition period. Except for the compensation at the legal ‘market price’, there are no other provisions in the acquisition or other-laws that require the government to mitigate the resultant adverse impacts caused by the acquisition. Socio-economic rehabilitation of the involuntarily displaced persons is absent in the legal regime of Bangladesh.
1 The average value of the properties of similar description and with similar advantages in the vicinity during the last twelve months prior to
the publication date of the notice. (Section 8 (1) of the Acquisition and Requisition of Immovable Property Ordinance 1982.) 2 The market value thus determined does not always reflect the actual market value.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
2-2
2.2 JICA's Policy on Land Acquisition and Resettlement The key principle of JICA policies on involuntary resettlement is summarized below. (1) Involuntary resettlement and loss of means of livelihood are to be avoided when
feasible by exploring all viable alternatives. (2) When, population displacement is unavoidable, effective measures to minimize the
impact and to compensate for losses should be taken. (3) People who must be resettled involuntarily and people whose means of livelihood will
be hindered or lost must be sufficiently compensated and supported, so that they can improve or at least restore their standard of living, income opportunities and production levels to pre-project levels.
(4) Compensation must be based on the full replacement cost as much as possible. (5) Compensation and other kinds of assistance must be provided prior to displacement. (6) For projects that entail large-scale involuntary resettlement, resettlement action plans
must be prepared and made available to the public. It is desirable that the resettlement action plan include elements laid out in the World Bank Safeguard Policy, OP 4.12, Annex A.
(7) In preparing a resettlement action plan, consultations must be held with the affected people and their communities based on sufficient information made available to them in advance. When consultations are held, explanations must be given in a form, manner, and language that are understandable to the affected people.
(8) Appropriate participation of affected people must be promoted in planning, implementation, and monitoring of resettlement action plans.
(9) Appropriate and accessible grievance mechanisms must be established for the affected people and their communities.
Above principles are complemented by World Bank OP 4.12, since it is stated in JICA Guideline that "JICA confirms that projects do not deviate significantly from the World Bank's Safeguard Policies". Additional key principle based on World Bank OP 4.12 is as follows.
(10) Affected people are to be identified and recorded as early as possible in order to establish their eligibility through an initial baseline survey (including population census that serves as an eligibility cut-off date, asset inventory, and socioeconomic survey), preferably at the project identification stage, to prevent a subsequent influx of encroachers of others who wish to take advance of such benefits.
(11) Eligibility of Benefits include, the PAPs who have formal legal rights to land (including customary and traditional land rights recognized under law), the PAPs who don't have formal legal rights to land at the time of census but have a claim to such land or assets and the PAPs who have no recognizable legal right to the land they are occupying.
(12) Preference should be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based.
(13) Provide support for the transition period (between displacement and livelihood restoration.
(14) Particular attention must be paid to the needs of the vulnerable groups among those displaced, especially those below the poverty line, landless, elderly, women and children, ethnic minorities etc.
(15) For projects that entail land acquisition or involuntary resettlement of fewer than 200 people, abbreviated resettlement plan is to be prepared.
In addition to the above core principles on the JICA policy, it also laid emphasis on a detailed resettlement policy inclusive of all the above points; project specific resettlement plan; institutional framework for implementation; monitoring and evaluation mechanism; time schedule for implementation; and, detailed Financial Plan etc.
In terms of categories of PAPs and types of lost assets, the gaps in the existing legal framework of Bangladesh and requirements of the JICA Guidelines are identified as presented in the table below.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
2-3
Table 2-1: Gap Analysis between Bangladeshi Laws and JICA Guidelines
No Category of PAPs / Types of Lost Assets
Bangladesh Laws JICA Guidelines
1
For all types of land and other assets for legal land
Acquired by DC as per legal requirements/ procedures
Preference should be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based
2
Land tenants Compensation for standing crops if harvesting of crops is not possible
People who must be resettled involuntarily and people whose means of livelihood will be hindered or lost must be sufficiently compensated and supported.
3 Land Users Squatters, encroachers and
unauthorized users/ occupiers are not recognized
Ditto
4 Owners of temporary structures
Only cash compensation under law (CUL)
Compensation must be based on the full replacement cost as much as possible.
5 Owners of permanent structure buildings
Ditto Ditto
6 Perennial crops Market prices of the standing
crops with value of plants Compensation must be based on the full replacement cost as much as possible.
7
Timing for payment of entitled compensation to the PAPs
No concern on the part of the project proponent. Land is handed over to the project proponent as soon as the compensation funds are placed with the DC.
On the completion of payment of compensation to the PAPs, the land is to be vacated and handed over to the project proponent.
8
The issue of relocation and income generation activities
No concern about relocation and income generation activities.
People who must be resettled involuntarily and whose livelihood will be hindered or lost must be sufficiently compensated and supported, so that they can improve or at least restore their standards of living, income opportunities and production levels to pre-project levels.
9
Vulnerability of PAPs No distinction between the PAPs
Particular attention must be paid to the needs of the vulnerable groups among those displaced, especially those below the poverty line, the landless, elderly, women and children, ethnic minorities, etc.
10
Role of DC, project proponent and PAPs
DC to acquire land, the project proponent to use the land, and PAPs to seek compensation from the DC.
DC and project proponent to assist the PAPs in getting the compensation, assist to collect the legal and required documents, and provide support for the transition period between displacement and livelihood restoration.
(Source: JICA Study Team)
2.3 Procedures for Land Acquisition Under the Ordinance of 1982 and its subsequent amendments 1989,1993, and 1994, the DC at District level is entrusted to acquire land for agencies requiring land for any public or private infrastructure projects. The procedures of land acquisition will follow the following steps:
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
2-4
Step 1: After identifying and selecting the exact ground locations of the required land, the project proponent will carry out detailed engineering surveys and design the construction work and lay them out on mauza maps. The project proponent will prepare the land acquisition proposals to obtain administrative approval by the line ministry.
Step 2: The project proponent, after obtaining the approval of the administrative ministry, will make a request to the DC, with sufficient information including the amount of land to be acquisitioned from each plot, and the ownership status such as private and public lands, for the acquisition of the land as per the proposal.
Step 3: Within 90 days, the DC will appraise the application through a) site observation, b) consultation with local politicians and residents, c) develop project profiles, and d) cost estimates. The DC will then develop and submit a proposal on land acquisition to the Ministry of Land for an appraisal by the central government within 90 days.
- The DC will publish a notice as stipulated in Section 3 of the Ordinance of 1982 stating that there is a proposal for the property to be acquired. The persons to be displaced may submit an objection to the land acquisition to the DC within 15 days after the notice is served. All the legal titleholders will be advised to show their ID cards and other documents that verify their rights. For those with no registrations, the DC Office will call for circumstantial evidence from community leaders, local elite people, and religious leaders, etc., to add these people to the list.
- The DC will consult with the Public Works Department (PWD), Forest Department (BFD), Department of Agricultural Marketing (DAM) and Department of Fisheries (DOF) to assess the value of structures, trees, crops and aqua products for their existing rates.
- Under Section 6, a second public notice will be served stating the GOB’s decision on the land acquisition and taking possession thereof. The DC Office will confirm the PAPs, exact land area and size for acquisition, number of relocated houses, agriculture land, forestry and fishing areas that will be lost. The persons to be displaced will be requested to submit their statements of property, amounts and particulars of the claims to compensation after 15 days of the second notice being served. The DC Office will respond to any grievances made by the PAPs in order to agree to the assistance package.
- The project proponent shall deposit the estimated amount of the award of compensation with the DC within 60 days from the receipt of the estimate given by the DC.
- Upon serving the last notice (Section 7), the DC shall pay the amount to the owners of the acquired property within another 60 days from the date of deposit by the project proponent. The DC will take possession of the property after completion of the compensation payment to the PAPs and immediately declare this in the official gazette, and hand the property over to the project proponent.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-1
Section-3 Social Impact
3.1 Socioeconomic Survey and Focus Group Discussions at Power Plant and Port Facility Site
3.1.1 Survey Outline (1) Socioeconomic Survey
a) Objective The survey aim was to collect the typical characteristics of the affected households, basic data of their livelihoods and living standards, and to gain a comprehensive idea of the socioeconomic conditions at the project site.
b) Main use of the results Analyze the socioeconomic conditions of the project site to draw the needs of the affected people for the livelihood restoration/ improvement program and the area development - Estimate the cost required for land acquisition, resettlement, compensation and the
implementation of the livelihood restoration program
c) Selection of interviewees The interviewees were the directly affected people who own/ lease/ use their private land (or lease government land) and who work within the site. Squatters were also surveyed as well as the indirectly affected people living around the project site. There were 343 household heads interviewed under the survey, and their major characteristics are as described below. Out of 343 household heads, 274 were from Matarbari Union, and the majority of these households lived in Shirar Dail village. The remaining 69 households were from Dhalghata Union, which is in southern part of the project site, and most of these households lived in Mohiraghona village.
Table 3-1: Interviewed Households
Union No. of Households
No. of Household Members Village
Matarbari 274
1,666
Matarbari 3
Maiz Para 1
Shirer Dail*1 270
Dhalghata 69
365
Mohiraghona*2 59
Sutaria Para 1
Nasir Mohammaddhil 9
TOTAL 343 2,031
Note 1) Shirer Dail includes “Shirer Dail” (149 HHs), “East Shirer Dail” (19 HHs), “Middle Shirer Dail”(21 HHs), “West Shirer Dail” (4 HHs), “Dakshin Shirer Dail” (74 HHs) and “Uttar Shirer Dail” (3 HHs).
2) Mohiraghona includes “Mohiraghona” (7HHs) and “Uttar Mohiraghona” (52 HHs). (Source: JICA Study Team)
d) Survey Method The three pillars of the socioeconomic survey, i.e., population census, asset inventory, and household survey, were compiled into one set of questionnaires and targeted all the potential PAPs regardless of their entitlement of land ownership or whether they were affected/ displaced PAPs.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-2
Table 3-2: Structure of Socioeconomic Survey
Survey Achievements
Population Census
A complete and accurate count of the population was made in the population census to confirm who and how many of the people would be affected by land acquisition and related impacts.
The population census provided the basic information necessary for determining eligibility for compensation. A cut-off date was fixed as December 28, 2012, including the accurate/ exact number of PAPs, names, photos for identification, and assets. It was also declared on February 13, 2013 in the presence of such PAP.
Asset Inventory
In the asset inventory survey, a complete count and description of all property was undertaken for the property to be acquired.
An asset inventory of losses (IOL) involved a mapping of all households affected by land acquisition, agricultural, homestead and business, trees, crops, fish, structures of residential and business and other kinds of losses, i.e., wages and income. A list of the losses was remunerated into a database.
The IOL for each PAP recorded the following: - amount and type of land to be acquired (residential, commercial, agricultural) - type of trees and/ or crops to be acquired - residential houses to be acquired - commercial structures to be acquired - loss of livelihood (type and income loss) - other types of losses - types of community infrastructure or common property resources to be acquired
The IOL also recorded the legal status of the land, residential houses, shops and other structures to be acquired. In conjunction with the population census and IOL of the PAPs, household data was collected on the following items: - size, sex and age composition of each affected household - types of occupation/ livelihood for each economically active household member - assessment of income levels for each economically active household member - number of school age children attending school - ethnic, language, and religious identity of each affected household
PAPs attitudes (intentions/ opinions) towards the project, land acquisition and resettlement were also recorded.
Household Survey
The household survey focused on income-earning activities and other socioeconomic indicators to observe the social and economic conditions of PAPs, such as income, expenditure, employment, education, skills, livelihood, utilities, health services facilities, social services, and other socio-economic and cultural aspects that prevailed in the targeted areas.
The household survey also included an inventory of formal and informal community level organizations that represented the PAPs, which can be engaged in information dissemination and consultation related to the implementation of the resettlement plan.
e) Interviewers CPGCBL/ BPDB officials and researchers representing the Engineers Associates Ltd., who were commissioned by the JICA Study Team, conducted the survey. f) Survey period December 17 - 28, 2012.
g) Limitations of the survey: The severe time constraints during the survey period and geographical remoteness of the site made it unable for the surveyors to return to the interviewed households to reconfirm their answers before they left the site. Incoherency of answers done by a person therefore is
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-3
admitted in the data, which made it unable to implement a complete set of scientific analysis. The number of people for each occupation were as of December 2012. Land tenure, they insisted, could not be double-checked as they were reluctant to disclose their official registration including land registration certificate. Likewise, their household income and expenditure, land lease and lease amount stated by them were not certified.
(2) Focus Group Discussions
a) Objective The focus group discussions aimed to collect specific information from particular groups, such as women and children who were regarded as vulnerable, and laborers who were mostly found at the project site in order to evaluate their specific characteristics.
b) Main use of the results Analyze the specific conditions of particular clusters of populations, who were placed in such groups with or without their wishes - Draw specific needs of the vulnerable groups - Obtain local needs for the livelihood restoration/ improvement program and the area
development
c) Selection of interviewees Each population cluster had three groups in which 86 people were randomly sampled at the project site.
Table 3-3: Interviewed Population in Focus Group Discussion
Cluster No. of Groups No. of People in Total Age Range (as of Dec. 2012)
Children 3 21 6 to 11
Women 3 25 20 to 45
Salt laborers 3 19 13 to 50
Shrimp laborers 3 21 18 to 70
Total 86
(Source: JICA Study Team)
d) Survey Method Focus Group Discussions
e) Interviewers CPGCBL/ BPDB officials and researchers representing the Engineers Associates Ltd., who were commissioned by the JICA Study Team, conducted the FGDs.
f) Survey period December 18 - 25, 2012.
g) Limitation of the survey: Not applicable.
3.1.2. Findings
The followings are the major findings from socioeconomic survey and FGDs.
(1) Profile of Interviewees and their family members a) Surveyed Population Out of 2,031 people comprising 343 interviewed households, 1,663 were from Matarbari union, of whom males shared 54.6%, and adults did 50.3%. In Dhalghata Union, on the other hand, males comprised of 57.3% and adults shared 56.0%.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-4
Table 3-4: Total Surveyed Population
Total Surveyed Population Matarbari Union Dhalghata Union
Male Female Total Male Female Total Male Female Total
Adult 599 444 1,043 474 363 837 125 81 206
Child 520 468 988 434 392 826 86 76 162
Total 1,119 912 2,031 908 755 1,663 211 157 368
(Source: JICA Study Team)
b) Length of Residing at the Site The length of time of households residing at the site varied. Those residing for over 50 years were 64 households, and the maximum length of time reached 300 years. This means that there are households residing at the site over generations.
Note: The median is amount of time is 25 years, and the mode is 15 years. (Source: JICA Study Team)
Figure 3-1 Length of Time Residing at the Site
c) Size of Household Average household size was 5.92 people, which is close to the median (6.0) and the mode (6.0). The minimum number of household member was 1, and the maximum number was 11.
(Source: JICA Study Team)
Figure 3-2 Household Size
(2) Education Level and Literacy Taking a look at the education level of the household heads, 33.5% were illiterate, and 38.8% could only write their own names (signature). This implies that 72.3% of household heads live without reading or writing as part of their day-to-day activities. The household
-
10
20
30
40
50
60
70
80
90
Less than 5
years
5 to 10
years
10 to 20
years
20 to 30
years
30 to 40
years
40 to 50
years
More than
50 years
0
10
20
30
40
50
60
70
80
1 2 3 4 5 6 7 8 9 10 11
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-5
heads under these two clusters had a slightly larger number of household members than the other categories that had graduated from University.
Table 3-5: Education Level of Heads and Household Size
Education Degree/ Level No. of HH Heads % Average of HH Size
Illiterate 115 33.5% 6.17
Write name 133 38.8% 6.14
Class I-V 25 7.3% 5.20
Class VI-X 40 11.7% 5.35
SSC 9 2.6% 5.33
HSC 9 2.6% 4.44
BA 5 1.5% 5.80
BA (Hons) 1 0.3% 7.00
MA 2 0.6% 6.00
Other 1 3 0.9% 7.33
Other 2 1 0.3% 3.00
TOTAL 343 100.0% 5.92
(Source: JICA Study Team)
Among the literate population, who comprised of 40.9% of the total surveyed population, males were 52.3%, and adults 34.1%. In Matarbari, 69.4% of the literate population were children under 18 years old, and more female than male children were literate. In Dhalghata, on the contrary, more males than females were literate (for both adults and children), and the literate population children shared half (50.9%). Although literacy rates of Matarbari and Dhalghata were similar in total (40.3% and 43.2% respectively), 56.4e% of children in Matarbari were literate, whereas 50.0% were in Dhalghata.
Table 3-6: Literate Population
Total Surveyed Population Matarbari Union Dhalghata Union
Male Female Total Male Female Total Male Female Total
Adult 170 113 283 118 87 205 52 26 78
Child 264 283 547 222 244 466 42 39 81
Total 434 396 830 340 331 671 94 65 159
(Source: JICA Study Team)
According to the FGD, females, salt laborers and shrimp laborers did not have sufficient opportunities for education. The number of government primary schools around the site was reported to be not sufficient, although there were Islamic schools. Due to households being poor, many people dropped out of school when they were children, even before they completed primary education. There was no major difference found in education levels between male and female children.
Table 3-7: Educational Levels and Literacy (FGD) Educational Qualifications Literacy Levels
Clusters Primary Secondary ≤
Unknown Read & Write
Signature Only
Illiterate & N/A
Children 15 1 5 19 0 2
Women 4 3 18 9 12 4
Salt laborers 3 4 12 6 11 2
Shrimp laborers 9 3 9 13 7 1
Total 31 11 44 47 30 9
(Source: JICA Study Team)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-6
(3) Health Conditions of Affected People From the total households, 325 households (94.8%) answered that they suffered from general fevers. They also suffered from diarrhea/ stomachaches (244 households, 71.1%) and respiratory infections such as colds (187 households, 54.5%).
Note: Household heads were asked to select as many illnesses as they experienced.
(Source: JICA Study Team)
Figure 3-3 Types of Illness
(4) Occupations of Household Heads Among the interviewed household heads, over 30% (108 household heads) were salt cultivators. These household heads are the owners and/or lessees of salt fields who invest money in salt cultivation. Sixty out of the 62 salt laborers (18%) were from Matarbari Union, being laborers who prepared the salt beds. These laborers always work under the guidance of salt cultivators, receiving wages. There was a lower number of shrimp cultivators, businessmen, mazi and laborers as the survey was conducted in December 2012 when salt cultivation was taking place. However, the majority of most types of laborers were from Matarbari, not Dhalghata.
Table 3-8: Occupations of the Household Heads
Occupations Matarbari Dhalghata Total
Cultivators 113 32.9%
Salt Cultivators 66 42 108
Shrimp cultivators 5 0 5
Businessman 36 10.5%
Salt Businessmen 12 2 14
Fish Businessman 11 0 11
Businessmen (other) 10 1 11
Mazi 35 10.2%
Mazi (Salt) 18 10 28
Mazi (Shrimp) 5 2 7
Laborers 94 27.4%
Salt Laborers 63 2 65
Shrimp Laborers 15 0 15
Day Laborers 12 2 14
Fishing 28 8.2%
Fishermen 18 1 19
0
50
100
150
200
250
300
350
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-7
Occupations Matarbari Dhalghata Total
Boatmen 5 3 8
Crab Catchers 1 0 1
Agriculture 1 0.3%
Orchardists/ gardeners 1 0 1
Others 36 10.5%
Teachers 4 1 5
Grocery Shop Owners 4 0 4
Masons 4 0 4
Service Industry Workers 2 2 4
Housewives 4 0 4
Master Tailors 3 0 3
Quack Doctors 2 1 3
Carpenters 2 0 2
Beggars 2 0 2
Security Guards 1 0 1
Singers 1 0 1
Students 1 0 1
Home Makers 1 0 1
TOTAL 274 69 343 100.0%
Note: Cultivators are the owners or lessees of the salt, shrimp or fish fields who invest their own money for cultivation. Businessmen in salt, shrimp and fish are those who purchase the products from the fields and local markets, and sell them at different markets and other places. Laborers are those who sell their labor and prepare the fields. They work under the guidance of cultivators and receives wages from them. “Mazi” refers to middleman in Bengalese who recruit day laborers to introduce to businessmen, land owners and employers who need laborers.
(Source: JICA Study Team)
According to the FGD, salt laborers and shrimp laborers mentioned that they had fewer job opportunities because of their low education and literacy levels. They responded in the group interviews that discontinuation of education and school drop-out rates continued to increase due to the involvement of their children into these income generation activities. Women, on the contrary, gave up looking for jobs because of their low literacy levels and social barriers. Fishing occurs throughout the year at the site, and the fish selected are of bigger size, good quality, or large quantity although smaller sized fish are sold at the fish markets in Cox’s Bazar and Chittagong from vehicles and engine boats. Fish of lower quality and smaller sizes are retailed by local businessmen at local markets.
(5) Household Incomes and Expenditure a) Household Incomes For monthly income, 119 households (34.7%) had 10,000 to 20,000 taka, and 82 (23.9%) had 20,000 to 30,000 taka. The average household monthly income was approximately 26,500 taka, but the median was 19,000 taka. There were 29 households receiving more than 50,000 taka per month, among whom the largest income was 842,000 taka.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-8
(Source: JICA Study Team)
Figure 3-4 Household Monthly Income
b) Household Expenditure For household expenditure, 156 households (45.5%) spent 10,000 to 20,000 taka per month, 74 (21.6%) spent between 5,000 to 10,000 taka, and 65 (19.0%) spent from 20,000 to 30,000 taka. The average household monthly expenditure was approximately 18,000 taka, but the median was as much as 15,000 taka. There were three households which spent more than 50,000 taka per month, among whom the largest expenditure was 104,200 taka.
(Source: JICA Study Team)
Figure 3-5 Household Monthly Expenditure
A glance at the breakdown of average expenditure shows that approximately 10,000 taka (56.1%) was spent for food consumption, 1,522 taka (8.5%) on health, around 1,261 taka for clothes and 1,249taka (7.0%) for transportation.
(Source: JICA Study Team)
Figure 3-6 Average Expenditure Patterns
c) Per Capita Monthly Income and Expenditure According to the Household Income & Expenditure Survey 2010 issued by the Bangladesh Bureau of Statistics (BBS) 1 , the population below the upper poverty line was 31.5%
1 BBS has conducted the HIES since the 1970s, and it has collected 12,240 households from the entire nation as samples for
the HIES 2010. They have received technical and financial support from the World Bank for conducting the survey. They
estimate the upper and lower poverty line taking into consideration the cost of basic needs (CBN) that include both food
and non-food items.
2.3%
13.1%
34.7%
23.9%
13.7%
3.8% 8.5%
<5,000
5,000≤ <10,000
10,000≤ <20,000
20,000≤ <30,000
30,000≤ <40,000
40,000≤ <50,000
50,000≤
2.0%
21.6%
45.5%
19.0%
8.2%
2.9% 0.9%
<5,000
5,000≤<10,000
10,000≤<20,000
20,000≤<30,000
30,000≤<40,000
40,000≤<50,000
50,000≤
56.1%
7.0%
7.0%
8.5%
4.2%
3.3%
3.5%
4.6%
2.5% 1.3% 2.0%
food
transporation
clothes
health
education
communication
social functions
agriculture
fuel consumption
electricity bill
others
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-9
nationwide and 26.2% in Chittagong Division that includes Chittagong District and Cox’s Bazar District. The population below the lower poverty line, on the other hand, was 17.5% nationwide and 13.1% in the Chittagong Division.
Table 3-9: Incidence of Poverty (Head Count Ratio) by CBN Method in 2010 Nationwide Chittagong
Average Urban Rural Average Urban Rural
Upper poverty line
31.5 21.3 35.2 26.2 11.8 31.0
Lower poverty line
17.5 7.7 21.1 13.1 4.0 16.2
(Source: Bangladesh Bureau of Statistics (2011) Household Income & Expenditure Survey 2010)
In both cases, the incidence of poverty occurred more in rural areas, and 35.2% of the population were below the upper poverty line nationwide and 31.0% in Chittagong Division respectively. Those who received 1,270.93 taka nationwide was 31.5% and 1,307.27 taka (26.2%) in Chittagong Division, and the population below the lower poverty line was estimated to receive as much as 1,102.84 taka nationwide, 17.5% of the population, and 1,051.67 taka in Chittagong Division (13.1%).
Table 3-10: Incidence of Poverty (by per capita monthly income) in 2010 Nationwide Chittagong
Average Urban Rural Average Urban Rural
Upper poverty line
1,270.93 1,545.96 1,211.57 1,307.27 1,328.03 1,304.64
Lower poverty line
1,102.84 1,240.18 1,083.72 1,051.67 1,259.46 1,034.62
(Source: Bangladesh Bureau of Statistics (2011) Household Income & Expenditure Survey 2010)
Table 3-11: Incidence of Poverty (by per capita monthly expenditure) in 2010 Nationwide Chittagong
Average Urban Rural Average Urban Rural
Upper poverty line
1,245.76 1,457.65 1,200.02 1,381.76 1,540.60 1,361.68
Lower poverty line
1,064.92 1,133.41 1,056.03 1,174.50 1,231.87 1,169.79
(Source: Bangladesh Bureau of Statistics (2011) Household Income & Expenditure Survey 2010)
Taking the geographical location of the project site and the inflation rates of FY 2010 and FY 2011 into consideration2, the surveyed population whose per capita income and expenditure were below 1,500 taka were assumed as the poor in this report. Therefore, 31 surveyed households (9.0%) were categorized as poor households on monthly income basis, and 44 households (12.8%) on monthly expenditure basis.
Table 3-12: Household Head’s Per Capita Monthly Income and Expenditure
<1,000
1,000≤<1,500
1,500≤<2,000
2,000≤<3,000
3,000≤<4,000
4,000≤<5,000
5,000≤
Total
Per capita income
8 23 30 71 81 32 98 343
Per capita expenditure
11 33 42 105 76 33 43 343
(Source: JICA Study Team)
2 The inflation rate of FY 2010 in rural areas was 11.73% and for FY 2011 it was 8.69% on the year 2005 basis.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-10
(Source: JICA Study Team)
Figure 3-7 Ratio of Household Head’s Per Capita Monthly Income and Expenditure
(6) Assets Out of 343 households, 295 (86.0%) had at least one mobile phone. There was one household head who said he had six phones at home, and the average number of mobile phones among 295 households was 1.23 phones. In addition, 212 households had fishing nets (1.91 on average) and 195 households had more than one kind of agriculture tool (average was 3.92 tools). Only 76 household had radios, and 15 had TV sets.
Note: Household heads were asked to choose as many assets as they had.
(Source: JICA Study Team) Figure 3-8 Household Assets
In regards to animals and poultry, 149 interviewed households (37.3%) kept chickens at home, followed by ducks (95 households) and goats (81 households).
Table 3-13: Animals and Poultry owned by Households
Livestock Household Ownership
Total Number Average No. Per Household No. of Households %
Cows 74 18.5% 118 1.6
Pigs 1 0.3% 5 5.0
Ducks 95 23.8% 604 6.4
Chickens 149 37.3% 1,707 11.5
Goats 81 20.3% 389 4.8
Note: Household heads were asked to choose as many livestock as they owned. (Source: JICA Study Team)
(7) Basic Infrastructure for Living a) Energy Source There were 332 household heads that responded that they did not have electricity yet. In fact, no single electric wire has been extended to Dhalghata Union as of March 2013, so that
3.2%
2.3%
9.6%
6.7%
12.2%
8.7%
30.6%
20.7%
22.2%
23.6%
9.6%
9.3%
12.5%
28.6%
0.0% 20.0% 40.0% 60.0% 80.0% 100.0%
per capitaexpenditure
per capitaincome
<1,000
1,000≤<1,500
1,500≤<2,000
2,000≤<3,000
3,000≤<4,000
4,000≤<5,000
5,000≤
0
50
100
150
200
250
300
350
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-11
all interviewed households in Dhalghata Union had no choice but to depend on energy sources other than electricity. Some 341 households (99.4%) used firewood for cooking, and 301 (87.8%) exclusively depended on kerosene lamps for lighting. There were 22 households who owned solar panels on their roofs.
Table 3-14: Energy Source by Purpose
Energy Source Cooking Lighting Irrigation Other
Electricity 0 7 1 1
Gas 0 0 0 0
Kerosene 1 301 19 0
Firewood 341 0 0 0
Solar 0 0 0 22
Diesel 0 0 3 0
None 1 2 320 320
Electricity + Kerosene 0 1 0 0
Kerosene + Solar 0 32 0 0
Total 343 343 343 343
Note: Household heads were asked to choose as many sources as they had. (Source: JICA Study Team)
Deteriorating living environments were commonly observed in the FGD as well. Sixty six out of 86 interviewees did not have electricity at home, whereas the remaining 20 had solar panels installed with the assistance of Rahimafrooz (Bangladesh) Ltd. Since there was no REB or BPDB distribution network available at the project site, solar systems were introduced for lighting. Rahimafrooz works all over Bangladesh installing solar systems without charging the initial cost. However, households are supposed to make monthly repayments of the installment costs ranging from 200 to 800 taka depending on the actual costs until the full costs are recovered.
b) Water and Sanitation All affected households depended on tube wells for water. Along with tube well water, some of them also used pucca wells and kacha wells of which water quality was not secured. Seven households used pond water and one used public piped water.
Note: Household heads were asked to choose as many facilities as they used.
(Source: JICA Study Team) Figure 3-9 Water Sources
No household heads said they had the habit of boiling water before drinking3. And 13 household heads said that they had experienced arsenic contamination.
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-12
Out of 343 households, 35 (10.2%) used pucca toilets. In addition, 176 (51.5%) used slab toilets, and the remaining 129 used temporary facilities and one household did not use toilet facilities at all.
(Source: JICA Study Team)
Figure 3-10 Type of Toilet
c) Medical Facilities Asked where they consult with doctors, quack doctors and other sources of medical and health treatment, over 80% of household heads responded that they had medical consultations at the local markets. Nearly 50% of households also went to town for medical consultations.
Table 3-15: Availability of Medical Facilities Availability of Medical Facilities
Village Market Town
Number % Number % Number %
Yes 13 3.8% 275 80.2% 169 49.3%
No 330 96.2% 68 19.8% 174 50.7%
TOTAL 343 100.0% 343 100.0% 343 100.0%
Note: Household heads were asked to choose as many facilities as they used. (Source: JICA Study Team)
According to the FGD, local people usually saw quack doctors for normal cases such as general fevers, and they went to Chakaria Upazila to consult private doctors for more complicated symptoms. They faced difficulty in traveling to Chakaria due to the deteriorated road access and transportation. Although men had more mobility in terms of access to private clinics and doctors, women and children had less such mobility.
d) Tidal Waves There were 304 household heads (88.6%) that said they had experienced tidal waves. Of these households, 303 said they experienced such tidal waves once or twice a year. And 263 people mentioned the floods of 1991 and 1997 as the biggest ones which they remembered.
(8) Others a) Source of Information There were 257 households that responded that they collected information through neighbors, and another 181 collected information from their friends. Not many of the households collected information from TV or radio as they did not have these items at home (see Assets above), but they often listened to radio or watched TV at tea stands or in the local markets.
10.2%
51.5%
0.3%
37.7%
0.3%
Pucca (permanent) toilet
Slab toilet
Kacha+slab toilet
Kacha (temp) toilet
None
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-13
Note: Household heads were asked to choose as many sources as they used.
(Source: JICA Study Team) Figure 3-11 Source of Information
b) Type of Pollution As types of pollution, 210 household heads (61.2%) recognized noise, water shortages (204 households, 59.5%), air pollution (197 households, 57.4%) and snow mats (196 households, 57.1%). Complaints regarding water related issues were raised most among households. Not only water shortages, but also bad smells, bad tastes of water, colored water and contaminated water were mentioned.
Note: Household heads were asked to choose as many sources as they had liked.
(Source: JICA Study Team) Figure 3-12 Examples of Pollution Experienced in the Past
(9) Available Job Opportunities Responding to whether there were any job opportunities available around the project site, 19 household heads said fishing cultivation, 16 domestic animal husbandries, six said poultry and two stated tailoring work. As stated in the FGD, people living or working at the site had fewer job opportunities because of their low education and low literacy levels.
(10) Skill Development Needs In response to the needs for skill development, household heads answered that they would like a wider variety of training skills. The skills demanded by the household heads were in fishing cultivation, followed by domestic animal husbandry, poultry, tailor, and technical work.
0
50
100
150
200
250
300
0
50
100
150
200
250
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-14
Table 3-16: Skill Development Requests
Rank Skill Development Requests No. of HH Heads who Show their Interests
1 Fishing cultivation 100
2 Domestic animal husbandry 79
3 Poultry 64
4 Tailor 53
5 Technical work 50
6 Social development 38
7 Vehicle licenses 20
8 Salt cultivation 15
9 Computer 14
10 Education (coaching) 5
11 Training for going abroad 3
12 Shrimp cultivation 2
13 Agriculture farming 1
14 Music 1
15 Hatchery 1
Note: Household heads were asked to select as many needs as they liked. (Source: JICA Study Team)
In the FGD, women were interested in receiving training for tailoring, making puppets and Nakashi Katha (hand-stitched bed covers) although they were not given any job opportunities.
3.2. Socioeconomic Survey and Focus Group Discussions at Transmission Line Site
3.2.1 Survey Outline
(1) Socioeconomic Survey a) Objective The survey aim was to collect the typical characteristics of the households who owned the
potential locations of angle towers from Anowara Upazila to Maheshkhali Upazila, basic data of their livelihoods and living standards, and to gain a comprehensive idea of the socioeconomic conditions there.
b) Main use of the results - Analyze the socioeconomic conditions of the angle tower locations - Estimate the cost required for involuntary land acquisition for the base area of each tower
and compensation.
c) Selection of interviewees The interviewees were the land owners of angle tower locations:
Table 3-17: Profile of Interviewed Households Angle Tower No.
House-holdNo.
Location Main Occupation Village Union Mauza Upazila
Chittagong District
P1 No.1 Boalia Borashat Boalia Anowara Agriculture
P2 No.2 Barumchara Barumchara West Barumchoda
Anowara Agriculture
P3 No.3 Barumchara Barumchara Barumchara Banshkhali Agriculture
P4 No.4 Raichatta khankhana bad
Raichatta Banshkhali Agriculture
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-15
Angle Tower No.
House-holdNo.
Location Main Occupation Village Union Mauza Upazila
P5 No.5 Chechuria 6 No. Ka, Katharia
Purbo Katharia
Banshkhali Businessman
Cox’s Bazar District
P6 No.6 Barabakia Barabakia Fasiakhali Rahatali para
Pekua Agriculture
P7 No.7 Barabakia Barabakia Fasiakhali Pekua Service provider
P8 No.8 Uzantia Uzantia Sutachuda Pekua Shrimp cultivator
P9 No.9 Matarbari Matarbari Maiz Para Maheshkhali Businessman
P10 - Matarbari Matarbari Maiz Para Maheshkhali -
Note: Land area of P9 and P10 belong to government, and there was nobody renting the land on P10. (Source: JICA Study Team)
d) Survey Method A questionnaire-based survey was conducted at household. The survey focused on
income-earning activities and other socioeconomic indicators to observe the social and economic conditions of land owners / lessees, such as income, expenditure, employment, education, skills, livelihood, utilities, health services facilities, social services, and other socio-economic and cultural aspects that prevailed in the locations of angle towers.
e) Interviewers Researchers representing the Engineers Associates Ltd., who were commissioned by the
JICA Study Team, conducted the survey on behalf of PGCB.
f) Survey period December 2012.
g) Limitation of the survey: Locations of suspension towers were not surveyed as the locations were not identified yet at this stage. Findings at the angle tower locations through household interviews and focus group discussions therefore do not represent the local context throughout the transmission line route.
(2) Focus Group Discussions a) Objective The focus group discussions aimed to collect specific information from particular groups, such as women and children who were regarded as vulnerable, and agricultural farmers, who were mostly found at the transmission line route, in order to evaluate their specific characteristics.
b) Main use of the results - Analyze the specific conditions of particular clusters of populations, who were placed in
such groups with or without their wishes - Draw specific needs of the vulnerable groups
c) Selection of interviewees Eighteen people were randomly sampled (five children, five women and eight farmers) at either of angle tower locations.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-16
Table 3-18: Interviewed Population in Focus Group Discussion Cluster Location Number of People Age Range (as of Dec. 2012)
Children P8 5 7 to 10
Female P7 5 29 to 40
Farmers P3 8 28 to 65
Total 18
Source: JICA Study Team
d) Survey Method Focus Group Discussions
e) Interviewers Researchers representing the Engineers Associates Ltd., who were commissioned by the JICA Study Team, conducted the FGDs on behalf of PGCB.
f) Survey period December 2012. g) Limitation of the survey: Not applicable.
3.2.2 Findings (1) Profile of Interviewees a) Length of Time Residing at the Site The length of time of households residing at the site varied from 20 to 100 years from one generation to the next.
b) Size of Household The number of household members varied from five to eighteen, and the average size was 10.2.
c) Education Level and Literacy Three out of nine respondents were illiterate or could write their own signature only. Others varied from Class VI-X to MA. Out of total members of nine families, 92 people, 61 were literate. 67.4% of adults and 65.3% of children were literate. Compared between male and female, 72.9% of male population were literate, whereas literate female remained 59.1% of total female population. Gender gap in literacy was caused by the low literacy of female adult (55.0%). This tendency was also found among female respondents in the FGDs. Among three different groups (female at P7, children at P8 and male farmers at P3), no women of five members were literate, whereas all five children and eight farmers were literate.
d) Health Conditions of Affected People Of nine respondents, all of them said they suffered from general fever, seven suffered from respiratory infection such as cold, six suffered from diarrhea and stomachache, and five from eye problem. In the FGDs, four women had suffered from malaria. Respiratory problems, general fevers were commonly seen. Among children, respiratory problems and general fevers were commonly admitted. Three of them suffered from diarrhea and stomachache. Farmers’ group members also showed similar tendency: six of them suffered from general fevers, diarrhea/stomachache, and respiratory diseases.
(2) Occupations of Household Heads Among the interviewed household heads, five were involved in agriculture. Two were businessmen (P5 and P9). One was involved in service industry (P7), and the other (P8) was a shrimp cultivator. Their secondary livelihood means varied from Imam, UP member, travel agent, and construction worker. According to the ad-hoc interviews at P3, P4, P5, P7 and P8 locations, most of the population in the villages depended on agriculture as farmers and agricultural laborers.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-17
People working abroad, business and services industry were also found. At P8, however, shrimp and salt cultivation were found as their secondary occupations. The husbands’ occupations of female group of FGD at P7 were: two salt laborers, two daily laborers, and one agriculture laborer. The fathers’ occupations of children group at P8 were: two involved in fishing industry, two daily laborers, and one rickshaw puller.
(3) Household Incomes and Expenditure a) Household Incomes For monthly income, five households involved in agriculture of socioeconomic survey had 20,000 to 60,000 taka per month. Two involved in business had 40,000 taka and 43,000 taka. One involved in service industry only had 12,000 taka. The biggest income was found at a household whose occupation was shrimp cultivator: 80,000 taka per month. Female group of FGD (P7) said that their husbands’ income varied from 4,500 to 6,000 taka per month who were all laborers. Among fathers of children group (P8), laborers and rickshaw puller received 5,000 to 7,000 taka, while two involved in fishing industry earned either 10,000 or 20,000 taka per month.
b) Household Expenditure Household expenditure ranged from 11,750 to 57,250 taka. The average household expenditure was approximately 32,000 taka. Of all items, respondents spent most for food (average: 17,000 taka, max: 30,000 taka and min: 6,000 taka), followed by expenditure for agriculture activities (average: 5,000 taka, max: 13,000), health (average: 2,700 taka, max: 8,500 taka, min: 300 taka) and education (average: 2,000 taka, max: 5,000 taka, min: 350 taka).
c) Per Capita Income and Expenditure Taking the geographical location of the project site and the inflation rates of FY 2010 and FY 2011 into consideration, the surveyed population whose per capita income and expenditure were below 1,500 taka were assumed as the poor in this report. The owners and a lessee, and their family members of the angle tower locations from P1 to P9 are not assumed as poor both on income and expenditure basis. Their per capita income ranged from 3,000 to 8,000 taka, and their per capita expenditure ranged from 1,958 to 4,250 taka.
(4) Assets Out of nine interviewed households, all of them had at least one mobile phone and agriculture tools. Six of them had fishing nets and five of them had either table fan or ceiling fan. In regards to animals and poultry, six kept chickens at home, followed by cow (five households), ducks and goats (four).
(5) Basic Infrastructure for Living a) Housing condition Among participants of FGDs, houses of women were made of clay and thesis. Children’s houses were made of clay: two had tin as their roof material, and three had thesis. Among farmers, two lived in bamboo-made houses, three lived in permanent houses, two lived in clay-walled house, and the last one lived in a house made of thesis and tin.
b) Energy Source Five of nine land owners and a lessee of the angle towers had electricity at home. All of them use firewoods for cooking. They use electricity or kerosene for lighting. They use diesel for irrigation purpose. Among female group members at P7 location, three had no electricity yet and two had lighting only by solar panels. Children group at P8, three had no electricity yet, and two had lighting only by solar panels. One of farmers of P3 location had solar panels at home, but others had no lights at home.
c) Water and Sanitation All land owners and a lessee used tube wells for water. They had no habit of boiling water before drinking. No respondent said their water was contaminated with arsenic. Six of them had pucca latrine, and three had ring-slab latrines.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-18
Among members of FGDs, all women, children and farmers in the groups took water from tube wells for cooking and drinking purposes. All women and children had ring-slab latrine (hygienic latrine).
d) Medical Facilities People under the socioeconomic survey went to either markets or towns for medical treatment. Women and children of FGDs went to Upazila Health Complex for medical treatment. All farmers saw quack doctors for general diseases. They went to private doctors in Bottoli and Chittagong for more complex diseases.
e) Tidal Waves All nine interviewed household heads said they had experienced tidal waves once to three times a year. They mentioned the floods of 1991 and 1997 as the biggest ones which they remembered. (6) Others a) Source of Information As source of information, all respondents said they collected from their neighbors. Seven of them collected information from TV as they watched TV at tea stands or in the local markets, followed by mosque imam (five people), community leader (four people) and friends (three). Among FGD participants, women collect information through NGO workers and neighbors, but not from TV or radio. Children collected information through TV, neighbors and their teachers.
b) Type of Pollution No major pollutions were recognized among nine respondents in the socioeconomic survey, except snow mat.
c) Available Job Opportunities Responding to whether there were any job opportunities available around the project site, the land owners from P1 to P7 stated that there was no job opportunity available. The land owner of P8 said that there would be job opportunities in shrimp farming.
d) Skill Development Needs In response to the needs for skill development, household heads answered that they would like to learn tailoring, salt farming technique, shrimp farming technique, training for working abroad, computer skill, and agriculture farming technique.
3.3 Socioeconomic Survey at Township Site
3.3.1 Survey Outline
(1) Socio-economic Survey a) Objective
The survey aim was to collect the typical characteristics of the households who owned the potential locations of Township at Materbari and Dhalghata union of Maheshkhali Upazila, basic data of their livelihoods and living standards, and to gain a comprehensive idea of the socioeconomic conditions there.
b) Main use of the results - Analyze the socioeconomic conditions of the Township site - Estimate the cost required for involuntary land acquisition for the base area of each tower
and compensation.
c) Selection of interviewees The interviewees were the land owners of Township site
d) Survey Method A questionnaire-based survey was conducted at household. The survey focused on
income-earning activities and other socioeconomic indicators to observe the social and economic conditions of land owners / lessees, such as income, expenditure, employment, education, skills, livelihood, utilities, health services facilities, social services, and other socio-economic and cultural aspects that prevailed in the locations of Township Site.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-19
e) Interviewers Researchers representing the Bartika Beacon Consultancy Services Ltd. were engaged by
CPGCBL, conducted the survey on behalf of CPGCBL.
f) Survey period September-October 2013.
3.3.2 Findings The followings are the major findings from socioeconomic survey
(1) Profile of Interviewees and their family members
a) Surveyed Population Of 207 people comprising 41 interviewed households, 87 (42..03%) were from Matarbari union, of whom males constitute 56.32%, and adults are 69.38% and 120 (57.97%) from Dhalghata Union , where males comprise 56.66% and adults shared 73.29%.
Table 3-19: Total Surveyed Population
Total Surveyed Population Matarbari Union Dhalghata Union
Male Female Total Male Female Total Male Female Total
Adult 84 63 147 34 27 61 50 36 86
Adolescent 11 4 15 5 1 6 6 3 9
Child 22 23 45 10 10 20 12 13 25
Total 117 90 207 49 38 87 68 52 120
(Source: Socioeconomic Survey,2013)
b) Size of Household Average household size was 5.05 people, which is close to the median (6.0) and the mode
(6.0). The minimum number of household member was 1, and the maximum number was
13.
(Source: Socioeconomic Survey,2013) Figure 3-13 Household Size
(2) Education Level and Literacy About the education level of the household heads, survey reveals that 14.63% were illiterate, and 85.37% literate among the literate of the total surveyed household heads (56.10%) 7.32% can write name, 9.75% falls within class i to v and 24.39% within VI-SSC, 4.87% are HSC passed and graduates 7.32% and only 2.44% got post graduation degree.
0
2
4
6
8
10
1' 2' 3' 4' 5' 6' 7' 8' 9' 10' 11' 12' 13'
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-20
Table 3-20: Education Level of Heads and Household Size
Education Degree/ Level No. of HH Heads % Average of HH Size
Illiterate 18 43.90 5.83
Write name 3 7.32 4.00
Class I-V 4 9.75 6.13
Class VI-SSC 10 24.39 5.00
HSC 2 4.87 4.25
Graduation 3 7.32 3.5
Post Graduation 1 2.44 5.00
TOTAL 41 100 5.04
(Source: Socioeconomic Survey,2013)
Of total survey population (207) 103 (49.75%) people are Literate. Among the literate adult 27 (26.21%) are male, 20 (19.42%) are female, adolescent 13(12.62%) are male , 12(11.65%) are female and 15(14.56%), 16(15.53%) are male and female child respectively
Table 3-21: Literate Population
Total Surveyed Population Matarbari Union Dhalghata Union
Male Female Total Male
Female
Total
Male
Female
Total
Adult 27 20 47 12 8 20 17 10 27 Adolescent 13 12 25 9 2 11 11 3 14
Child 15 16 31 7 7 14 8 9 17
Total 55 48 103 28 17 45 36 22 58 (Source: Socioeconomic Survey,2013)
(3) Occupations of Household Heads Survey found that 34.15% (14) household heads are salt and shrimp cultivators. These
household heads are the owners and/or lessees of salt/shrimp fields who invest money in
salt/shrimp cultivation. Eight out of the 14 cultivators are from Matarbari Union and the rest 6
cultivators belong to Dhalghata Union. Out of 14 businessmen 10 are from Dhalghata the
rest 4 persons belong to Matarbari, 3 household heads from Dhalghata and 2 from Matarbari
are engaged in farming. Two are from Matarbari and 3 from Dhalgahta are self-employed in
household activities. Only one person from Matarbari and 2 from Dhalghata are doing
service.
Table 3-22: Occupations of the Household Heads
Occupations Matarbari Dhalghata Total
Cultivators 14 34.15%
Salt Cultivators 3 5 8
Shrimp cultivators 5 1 6
Businessman 14 34.15%
Salt Businessmen 2 6 8
Businessmen (other) 2 4 6
Agriculture 5 12.20%
Farming 2 3 5
Others 8 19.50%
Households Work 2 3 5
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-21
Occupations Matarbari Dhalghata Total
Service 1 2 3
TOTAL 17 24 41 100.0%
(4) Household Income and Expenditure a) Household Income
Regarding monthly income, 17 households (41.46%) had 10,000 to 20,000 taka, and 7 (17.07%) had 20,000 to 30,000 taka, 8 (19%) 30000 to 40000 taka, 3 (71%) 40000 to 50000 taka. The average household monthly income was approximately 24634 taka. There were 4 households earning more than 50,000 taka per month, among whom the largest income was 70,000 taka.
(Source: Socioeconomic Survey,2013)
Figure 3-14 Household Monthly Income
b) Household Expenditure About household expenditure one household (2%) spent less than 5000 taka, 15 households
(36.58%) spent 10,000 to 20,000 taka per month, 5 (12.20%) spent between 5,000 to 10,000
taka, and 9 (21.95%) spent from 20,000 to 30,000 taka, 8 (19%) spent from 30000 to 40000
taka. The average household monthly expenditure was approximately 20219 taka. There
are three households whose monthly expenditure is more than 50,000 and taka among
whom the largest expenditure was more than 50,000 taka.
(Source: Socioeconomic Survey-2013)
Figure 3-15 Household Monthly Expenditure
c) Household per Capita Monthly Income and Expenditure Of 41 HHs, 14 have per capita monthly income ranging from 3000-4000 and 1 has less than taka 1000/- and 8 have between taka 2000 and taka 3000. About per capita expenditure 12 HHs have monthly per capita expenditure between taka 2000 and taka 3000 and another 12
2% 2%
42%
17%
20%
7%
10%<5000
5000≤<10000
10000≤<20000
20000≤<30000
30000≤<40000
40000≤<50000
50000≤
2%12%
37%
22%
20%
0%7% <5000
5000≤<10000
10000≤<20000
20000≤<30000
30000≤<40000
40000≤<50000
50000≤
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-22
HH spent more than taka 5000/- and 2 HHs expenditure comes below taka1000. Details are shown in table and figure below:
Table 3-23: Household Per Capita Monthly Income and Expenditure
<1,000
1,000≤<1,500
1,500≤<2,000
2,000≤<3,000
3,000≤<4,000
4,000≤<5,000
5,000≤
Total
Per capita income
1 0 1 8 14 3 14 41
Per capita expenditure
2 0 2 12 10 3 12 41
(Source: Socioeconomic Survey, 2013
(Source: Socioeconomic Survey, 2013)
Figure 3-16 Line graph of household Per Capita Monthly Income and Expenditure
(5) Assets
Of affected 41 households, 35 (82.92%) had at least one mobile phone. There was one household head who said he had 3 phones at home, and the average number of mobile phones among 35 households was 1.09 phones. In addition, 20 households had fishing nets (1.35 on average) and 18 households had more than one kind of agriculture tool (average was 1.39 tools). Only 10 household had radios, and 6 had TV sets. However, there are households amongst them who have more than one type of assets.
Figure 3-17 Household Assets
(Source: Socioeconomic Survey, 2013)
Animals and Poultry owned by Households
In respect of animals and poultry, 25 HHs households (42.37%) kept chickens at home, followed by ducks (15 households) , goats (9 households) and cows (10 HHs)
02468
10121416
Per Capita
Income
Per Capita
Expenditure
05
10152025303540
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-23
Table 3-24: Animals and Poultry owned by Households
Livestock Household Ownership
Total Number Average No. Per Household No. of Households %
Cows 10 16.94 18 1.8
Ducks 15 25.42 101 6.7
Chickens 25 42.37 271 10.84
Goats 9 15.27 37 4.11
(Source: Socioeconomic Survey, 2013)
(6) Basic Infrastructure for Living a) Energy Source 9 household heads that responded that they did not have electricity yet. In fact, no single electric wire has been extended to Dhalghata Union as of October 2013, so that all interviewed households in Dhalghata Union had no choice but to depend on energy sources other than electricity. All the 41 households 100% used firewood for cooking, and 28 (68.29%) exclusively depended on kerosene lamps for lighting. There were 4 households who owned solar panels on their roofs.
Table 3-25: Energy Source by Purpose
Energy Source Cooking Lighting Irrigation Other
Electricity 9
Kerosene 28 4
Firewood 41
Solar 8
Diesel 1
None 36 33
Kerosene + Solar 4
Total 41 41 41 41
(Source: Socioeconomic Survey, 2013)
b) Water and Sanitation All affected households depended on tube wells for water. Along with tube well water, some
of them also used pucca wells and kacha wells of which water quality was not secured.
Three households used pond water.
(Source: Socioeconomic Survey, 2013) Figure 3-18 Water Sources
No household heads said they had the habit of boiling water before drinking4. And 13 household heads said that they had experienced arsenic contamination. Out of 41 households, 4 (19.51%) used pucca toilets. In addition, 19 (46.34%) used slab toilets, and the remaining 14 used temporary facilities.
0 10 20 30 40 50
Tubewell
Well (Pucca)
Well (Katcha)
Pond
Pipe water
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-24
(Source: Socioeconomic Survey, 2013)
Figure 3-19 Type of Toilet
c) Medical Facilities On query, over 85.36% households heads responded that they can consult physicians at the local markets. Nearly 50.09% of households also go to town for medical treatments.
Table 3-26: Availability of Medical Facilities Availability of Medical Facilities
Village Market Town
Number % Number % Number %
Yes 3 7.32 35 85.36 23 56.09
No 38 92.62 6 14.64 18 43.91
TOTAL 41 100.00 41 100.00 41 100.00
(Source: Socioeconomic Survey, 2013)
d) Tidal Waves 30 household heads (73.17%) responded that they had experienced tidal waves. Of them 27 said they experienced such tidal waves once or twice a year. And 22 people mentioned that they have the memory of biggest floods of 1991 and 1997.
(7) Others
a) Source of Information 15 households responded that they collected information through neighbors, and another 20 collected information from their friends. Of them 16 households collected information from TV or radio as they did have these items at home. But they at times of necessity listened to radio or watched TV at restaurants in the local markets.
(Source: Socioeconomic Survey, 2013) Figure 3-20 Source of Information
20%
46%
34%
0%
Pucca Latrine
Slab Latrine
Katcha Latrine
None Latrine
05
101520253035
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-25
b) Type of Pollution As types of pollution, 25 household heads (60.97%) recognized noise, water shortages (22 households, 53.66%), air pollution (23 households, 56.09%) and snow mats (15 households, 36.58%). Complaints regarding water related issues were raised most among households. Not only water shortages, but also bad smells, bad tastes of water, colored water and contaminated water were mentioned.
(Source: Socioeconomic Survey, 2013) Figure 3-21 Examples of Pollution Experienced in the Past
(8) Availability of Job Opportunities 10 HH heads told that there were job opportunities in fish and salt cultivation, 12 said about domestic animal husbandry, 7 said about poultry and 2 reported tailoring. (9) Skill Development Needs In response to the needs for skill development, household heads answered that they would like a wider variety of training skills. The skills demanded by the household heads were in fishing cultivation, followed by domestic animal husbandry, poultry, tailoring, and technical work.
Table 3-27: Skill Development Requests
Rank Skill Development Requests No. of HH Heads who Show their Interests
1 Fishing cultivation 15
2 Domestic animal husbandry 10
3 Poultry 9
4 Tailoring 4
5 Technical work 16
6 Salt cultivation 5
7 Computer 4
8 Shrimp cultivation 5
9 Agriculture farming 1
(Source: Socioeconomic Survey, 2013)
3.4 Local Consultation
CPGCBL has so far conducted three public consultation meetings (PCM), two with the support of the JICA Study Team and EAL. Another PCM was conducted in October 01, 2013 with the assistance of BBCS Ltd. Summaries of the meetings are given below: 3.4.1 First Public Consultation Meeting (1) Objectives - Disclose information about the project - Collect opinions and comments from individuals and organizations regarding the project - Appropriately reflect such opinions, etc., into the LARAP
0
5
10
15
20
25
30
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-26
(2) Consultation Results The first PCM was held at the scoping stage of the Feasibility Study of the Coal-fired Power Plant Development Project. CPGCBL hosted the meeting assisted by the JICA Study Team. Notification letters were distributed to all key stakeholders prior to the meeting. Outcomes of the meeting were shown below. Table 3-28: Outcomes of First PCM
Date & Time From 10am to 2pm, November 14, 2012
Venue Puran Bazar Government Primary School, Matarbari, Maheshkhali
Upazila, Cox’s Bazar District
Host and Chair Mr. Aloke Kimar Sarker, Managing Director of CPGCBL
Participants Local affected residents, community leaders, local elite people, local
government officers, local NGOs, etc., a total of 115
Agenda
- Registration - Recitation of Quran - Welcome Speech by MD, CPGC - Background of the project by CPGC - Presentation on Project Description by CPGC - Question & Answer Session - Closing Speech by CPGC - Lunch
(Source: JICA Study Team)
At the meeting, a power-point presentation with a full explanation of the project was given to
the participants in their local language, to allow the audience to fully understand the project
and to contribute valuable comments. Major comments raised by the participants and the
responses made by CPGCBL are shown in the table below, as per the meeting minutes and
list of participants attached in the Annex..
Table 3-29: Major Comments from Participants and Responses by the Project Owner
Comments Response Reflection to LARAP (or EIA)
Mr. Nazrul Islam, teacher, local school, wanted to know the exact location of the proposed power plant. He suggested selecting a site towards the Bay of Bengal.
The project owner replied that the site for the power plant had been primarily selected between Matarbari and Dhalghata Union. The site will be finalized after the social and environmental survey.
[Water pollution] (EIA)
- Cover installation on conveyor for coal transportation to coal yard.
- Unloading of coal will be minimized (e.g., reduce the frequency of activity, etc.) during times of high speed winds.
- Watering coal yard to keep the surface wet and prevent wind blowing coal and dust.
- Installation of a dust control fence
- Re-greening especially along boundary of project, surrounding coal yard with domestic
Mr. Saiful islam, job holder, LGED, Matarbari, commented that the main profession of local people of Matarbari is sea fishing. If hot water from the power plant is discharged into the sea, it will harm the fish. Therefore, the fishing profession will be affected.
The project owner replied that hot water will be cooled down to almost normal temperatures and then it will be released submerged into the sea without any harm to fish or other aquatic animals.
Mr. Nurul Islam, Ex-Chairman Matarbari Union Council, wanted to know whether priority will be given to the affected people who will lose
The project owner assured the audience that local people will be given high priority for employment in the project and related industries as well.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-27
Comments Response Reflection to LARAP (or EIA)
their livelihoods due to the power plant in Matarbari.
plants
- Water quality of tube wells and others will be checked periodically for the safety of local residents.
[Employment]
- Employ local residents as much as possible.
- Developing an appropriate “land acquisition and resettlement action plan”, including “livelihood restoration program”
- Enrollment in vocational training courses based on assessment of skills
[Air pollution] (EIA)
- To reduce PM emissions, Electrostatic Precipitator (EP; around 99.8% efficiency) will be installed.
- Duct will be provided with CEMS (Continuous Emission Monitoring System) with the supported infrastructure as required under the gas emission standards and IFC guideline
[Protective structure]
-Coordination will be continuously made with local authorities to improve the local infrastructure.
Mr. Kamrul Hassan Hanif, student, Matarbari, pointed out that agricultural land is normally affected by fly ash or dust produced from the coal-based power plants. As a result, agriculture is also affected. He also pointed out that people may suffer from respiratory problems.
The project owner replied that this power plant will be constructed using Ultra Super Critical (USC) technology and only negligible dust will be produced. As a result, agricultural land, agriculture and public health will not be affected.
Mr. G.M. Somi Uddin, Chairman of Matarbari Union Awami league, requested to hold the next meeting in the project area to motivate more people of the area to participate in the meeting. He also demanded the following points:
a. Local residents should be given high priority for employment in the project.
b. Local competent people should be employed in the project.
c. Roads, schools, colleges, fishery jetties, and health centers shall be developed. Roads along the east side and west side of Matarbari island should be made of pucca.
d. The protective structure along the west coast of Matarbari island should be made very strong and permanent to protect the people of Matarbari from cyclones, tidal waves and erosion.
e. Compensation for acquisition of land should be paid at least three times the present rate.
f. No households should be
The project owner gave assurances that the next stakeholder meeting will be held at the project site.
He also confirmed that local people will be given priority for employment in the project based on their skills.
The affected salt farmers and fishermen will be compensated and rehabilitated.
Regarding social facilities, he was told that the plant authority will establish a school, college and hospitals, etc., for the staff of the plant.
Local people will also be able to use the above facilities.
Apart from this, other infrastructure shall be developed in the Matarbari area to attract tourists as well.
The compensation of the land shall be paid as per prevailing rules of the Government of Bangladesh.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-28
Comments Response Reflection to LARAP (or EIA)
damaged.
g. All affected fishermen and salt farmers should be compensated and rehabilitated.
h. The road from Matarbari to Chittagong should be improved.
i. Electricity should be supplied to the people of Matarbari at a subsidized rate.
j. The plant should be constructed in such a way that it does not cause any damage to the environment and location.
[Compensation]
- Compensation under the Law (CUL) for all the private land as stipulated by the Ordinance 1982: average of last 12 months’ sales values of same kind of land X 1.5 (50% premium)
- Cash grant that covers the difference between CUL and the replacement value (RV)
- Provision of stamp duty, land registration fee, capital gains tax and value added tax incurred for replacement land
[Electrification]
Electrification of surrounding area will be examined.
(Source: JICA Study Team)
3.4.2. Second Public Consultation Meeting (1) Objectives - To update information on study progress (location of Power plant and anticipated social
impact) - To discuss possible actions and measures for the local residents - To discuss implementation mechanisms (2) Consultation Results The meeting was presided over by Mr. ATM Zahirul Islam, Managing Director, CPGCBL, assisted by the JICA Study Team. Notification letters were distributed to selected representatives of the affected people prior to the meeting. Chairmen of Matarbari Union and Dhalghata Union, UNO of Maheshkhali Upazila, DOE of Cox’s Bazar District, and a local NGO were consulted prior to the PCM. Results of the meeting are shown below.
Table 3- 30: Outcomes of Second PCM
Date & Time From 11:30 a.m. to 2:00 p.m., February 13, 2013
Venue: Chakaria Upazila Parishad Auditorium
Host and Chair Mr. Aloke Kimar Sarker, Managing Director of CPGCBL
Participants Local affected residents, Union Chairmen, local elites, local government officers, local NGOs, etc., a total of approximately 50
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-29
Agenda
- Registration - Recitation of Quran - Welcome Speech by MD, CPGCBL - Opening Remarks by Team Leader of JICA Study Team - Presentation on Project Description by EAL - Question & Answer Session - Closing Speech by CPGCBL - Lunch
(Source: JICA Study Team)
Table 3-31: Major Comments from Participants and Responses by the Project Owner
Comments Response
Reflection to LARAP (or
EIA)
Md. Aminul Haque Choudhury,
teacher, Dhalghata Ideal High
School, worried that there were
rumors about the negative
impacts on ecological balance, air
quality, water quality, biodiversity,
fish cultivation, livelihood, etc., in
the project area if the power plant
was constructed. He said that the
affected people must be relocated
as well. He wanted to know the
extent of impacts if the power
plant was constructed.
CPGCBL responded that the JICA
Study Team was conducting a
social and environmental survey in
the project area to assess the
impacts of the power plant. He
also mentioned that the power
plant would be environmentally
friendly and the quality of the
environment would be ensured by
the department of environment. He
mentioned the access road to be
constructed for the power plant
which would ease travel in the
area. He clearly stated that local
people would have employment
opportunities in the power plant
depending on their skills.
[Water pollution] (EIA)
- Cover installation on
conveyor for coal
transportation to coal
yard.
- Unloading of coal will be
minimized (e.g., reduce
the frequency of activity,
etc.) during times of high
speed winds.
- Watering coal yard to
keep the surface wet and
prevent wind blowing coal
and dust.
- Installation of a dust
control fence
- Re-greening especially
along boundary of project,
surrounding coal yard with
domestic plants
- Water quality of tube wells
and others will be checked
periodically for the safety
of local residents.
[Employment]
- Employ local residents as
much as possible.
Mr. Faridul Alam, an NGO worker,
pointed out that Matarbari was
famous for shrimp cultivation. If
the land was to be acquired,
shrimp cultivation would be
affected. Also, private land
owners would lose their land. On
the other hand, there was lot of
government land unused in
Chokoria Upazila and he
suggested acquiring the
government land in Chokoria
Upazila to construct the power
plant instead of Matarbari.
CPGCBL responded that there
were several selection criteria to
select the location of the power
plant. Availability of land was one
of the selection criteria. But the
availability of fuel was also another
criterion. In the proposed power
plant the primary fuel would be
imported coal which would require
transportation and unloading
facilities. In Matarbari, coal might
be imported from foreign counties
by large vessels and an unloading
jetty facility would be created
there. But Chokoria was far away
from the Bay of Bengal, so the
JICA Study Team selected the
Matarbari site for the power plant.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-30
Comments Response
Reflection to LARAP (or
EIA)
Mr. Faizul Karim, salt
businessman, Sairer Dail,
Matarbari, wanted to know
whether any embankment would
be constructed in Matarbari and
Dhalghata if the power plant was
to be constructed. The people
who were passing the
government land with their
livelihood from cultivating those
lands would be affected if the
power plant would be constructed.
He asked whether these affected
people would get compensation
or not. He also wanted to know
whether those who would lose
their houses in the project area
would be resettled or not.
CPGCBL responded that the
affected people would be
compensated as per Bangladesh
Laws (Ordinance 1982) through
the district administration. There
was no provision for compensating
illegal residents or occupants of
government land. But as per JICA
guidelines, illegal residents or
occupiers should also be
compensated. The JICA Study
Team was working on this issue
and the illegal residents/occupants
would also be compensated in
accordance with JICA’s guidelines
and Bangladesh government laws
through the district administration.
Regarding the embankment, he
was unable to comment, but gave
assurances that an access road
would be constructed along with
the power plant.
- Developing an
appropriate “land
acquisition and
resettlement action plan”,
including “livelihood
restoration program”
- Enrollment in vocational
training courses based on
assessment of skills
[Air pollution] (EIA)
- To reduce PM emissions,
Electrostatic Precipitator
(EP; around 99.8%
efficiency) will be installed.
- Duct will be provided with
CEMS (Continuous
Emission Monitoring
System) with the
supported infrastructure
as required under the gas
emission standards and
IFC guideline
[Protective structure]
-Coordination will be
continuously made with
local authorities to improve
the local infrastructure.
[Compensation]
- Compensation under the
Law (CUL) for all the
private land as stipulated
by the Ordinance 1982:
average of last 12 months’
sales values of same kind
of land X 1.5 (50%
premium)
- Cash grant that covers
the difference between
CUL and the replacement
value (RV)
- Provision of stamp duty,
land registration fee,
Mr. Nazrul Islam, a resident of
Sairer Dail, Matarbari, wanted to
know whether residents would
receive free electricity. He also
wanted to know whether they
would get employment
opportunities at the power plant.
CPGCBL responded that the
surrounding area of the power
plant would certainly get electricity
extended there, and the electricity
would be as per standard rates
fixed by the government.
Regarding employment
opportunities, assurances were
given that priority would be placed
on hiring local people in the power
plant depending on their skills.
Mr. Shariful Islam, Assistant
Director, DoE, Cox’s Bazar, said
that coal-based power plants had
negative impacts on the
environment. But, the negative
impacts could be mitigated by
using the latest technology.
He, however, raised the point that
some birds were observed flying
in the power plant area. He was
worried about the negative
impacts on the birds by the high
stack/ chimney of the power plant.
He then requested the JICA Study
Team to design the height of the
stack/chimney properly to avoid
any negative impacts on the birds.
He also suggested adopting
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-31
Comments Response
Reflection to LARAP (or
EIA)
adequate mitigation measures to
keep SOx and NOx of ambient air
quality within standard limits.
Warm water of the power plant
should be discharged into the sea
in such a way that aquatic
plants/animals were not affected.
He assured the local people not to
worry about the implementation of
this power plant as the DoE is the
enforcing agency of the GOB to
ensure a pollution free
environment.
capital gains tax and value
added tax incurred for
replacement land
[Electrification]
Electrification of
surrounding area will be
examined.
[Education]
School facilities at power
plant will be shared with the
local residents.
[Health]
Health facilities at power
plant will be shared with the
local residents.
Mr. Aminul Haque learnt that
forestation for 20 years was
needed if a coal-based power
plant was to be constructed. In
order to meet the present power
crisis in Bangladesh, he said that
nobody could wait 20 years to
construct a coal-based power
plant.
CPGCBL responded that the latest
coal-based power plant would be
environment friendly. Forestation
and other necessary mitigation
measures might be undertaken
during the construction/ operation
period.
Mr. Ahsanullah Bacchu,
Chairman, Dhalghata Union
Council, welcomed the initiative to
construct a coal-based power
plant in Matarbari. He expected
that an embankment, roads,
schools/ colleges, and hospitals
would be developed at Matarbari
island. He learned that an access
road would be constructed up to
the power plant site, and
requested the concerned authority
to extend this access road up to
Dhalghata via Mutila for about 5-6
km. He also requested the
construction of hospitals and
schools/ colleges around the
power plant area for area
development. He urged that
project affected people be
properly compensated.
CPGCBL responded that another
JICA Study Team was conducting
a feasibility study of the access
road for the power plant. A similar
public consultation meeting would
be held for the access road also.
He requested Mr. Bacchu to raise
this issue in that PCM to include
an additional 5-6 km road up to
Dhalghata via Mutila.
Regarding the construction of
schools/colleges and hospitals
outside the power plant, he said
that sincere cooperation would be
extended with other development
agencies to construct the above
facilities. However,
schools/colleges, hospitals. etc.,
would be constructed in the power
plant area for the power plant
employees. He gave assurance
that the above facilities would be
accessible to the public residing
around the power plant.
Mr. Enamul Haque Choudhury
Ruhul, Chairman, Matarbari Union
Council, told the meeting that
there were both positive and
negative perceptions for
CPGCBL responded that the
project would be implemented
after motivating the local people
and satisfying all criteria set by the
Government of Bangladesh and
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-32
Comments Response
Reflection to LARAP (or
EIA)
construction of a coal-based
power plant in Matarbari. The
local residents were very
concerned about the negative
impacts of the power plant. They
must be motivated before the
construction of this power plant so
that they would not raise any
objections against the
construction of this plant.
JICA as well.
Md. Anwarul Naser, UNO,
Maheshkhali Upazila, told the
meeting that electricity was a very
essential commodity for modern
civilization. In order to meet the
power crisis, he said that it would
be essential to construct a big
power plant. Some rental and
quick rental power plants had
been installed in Bangladesh to
overcome the immediate power
crisis, but the cost of energy of
these power plants was very high.
On the other hand, the cost of
energy of this coal-based power
plant would be very low. He
therefore urged everybody to
come forward with GOB to
implement this big power plant.
He gave assurances that the
project affected people would be
properly compensated and
resettled as per the government
and international rules.
(Source: JICA Study Team)
3.4.3 Third Public Consultation Meeting (1) Objectives - To update information on study progress (location of Power plant and anticipated social
impact) - To discuss possible actions and measures for the local residents - To discuss implementation mechanisms
(2) Consultation Results The meeting was presided over by Mr. Enamul Haque Chowdhury, Chairman, No-1, Matarbari Union Parisad, organized by BBCS Ltd a social consulting organization engaged by CPGCBL. MD, CPGCBL, Project Manager, Local School Teacher, NGO officials, Local Leaders, Selected Representatives of the affected people UP male and female members and other stakeholders were invited to attend the meeting prior to holding the meeting. Results of the meeting are shown below.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-33
Table 3-32: Outcomes of Third PCM
Date & Time From 4:30 p.m. to 7:00 p.m., October 01, 2013
Venue: Matarbari Union Parisad Hall Room
Chair Mr. Enamul Haque Chowdhury, Chairman, Matarbari Union Parisad
Participants Local affected residents, Union Parisad Male and Female members, Chairman, Ex-Chairman, local elites, Teachers, local NGOs, etc., a total of approximately 60.
Agenda
- Registration - Recitation of Quran - Welcome Speech & Opening Remarks by Team Leader of BBCS Ltd. - Presentation on Project Description & Entitlement Policy by MIS Specialist
BBCS Ltd. - Question & Answer Session - Closing Speech by Chairman, Matarbari Union Parisad - Thanks given by Team Leader BBCS Ltd.
(Source: Socio-economic Survey Team)
Table 3-33: Major Comments from Participants and Responses by the Representative of Project Owner
Comments Response Reflection to LARAP (or EIA)
Mr. Kabir Ahmad, Ex-Chairman, Matarbari Union Parisad expressed his anxiety that establishment of power plant, transmission line and township would have negative impacts on ecological balance, air quality, bio-diversity, fresh cultivation, livelihood etc. He wanted to know how these negative impacts and dislocation of affected people would be addressed. He opined that displaced person must be relocated.
Socio-economic Survey Team responded that a social as well as environmental survey were being conducted in the project area to assess the adverse impacts of the implementation of power plant project. Respondent also emphasized that the power plant would be environmentally friendly and quality of environment will be ensured by the department of environment. He also told that construction of access road and development of township would benefit the local people in easy transportation and travelling and getting developed service sector and thus they would have better windfall employment opportunities in the power plant and construction of township and also business opportunities.
[Water pollution] (EIA)
- Cover installation on conveyor for coal transportation to coal yard.
- Unloading of coal will be minimized (e.g., reduce the frequency of activity, etc.) during times of high speed winds.
- Watering coal yard to keep the surface wet and prevent wind blowing coal and dust.
- Installation of a dust control fence
- Re-greening especially along boundary of project, surrounding coal yard with domestic plants
- Water quality of tube wells and others will be checked periodically for the safety of local residents.
[Employment] - Employ local residents as much as possible.
- Developing an appropriate “land acquisition and resettlement action plan”, including “livelihood restoration program”
Mr. Rafiqul Islam, Local Leader Materbari Union expressed his concern about the construction of power plant and township in Matarbari and Dhalgata Union. He wanted to know whether any embankment would be built in the affected area. He enquired about the policy of the project authority for compensating the people losing business and houses due to the project.
Socio-economic Survey Team replied that directly affected people losing land and structure would be compensated by DC. In addition to that non-titled or illegal residents or squatters and affected businessmen, employees, lease holders would get proper compensation as per JICA guidelines for Environmental and Social Considerations.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
____________________________________________________________________________________________________________________________
3-34
Comments Response Reflection to LARAP (or EIA)
Master Mahamudullah, Teacher, Matarbari High School, expressed his concern about the acquisition of land for construction of power plant & township at Matarbari and Dhalgata Union and requested the project authority to address the following issues: i) Roads, School, Health Center should be established/developed. ii) Compensation for land should be paid at replacement value and also registration fee for purchasing land with compensation money should be given to the APs iii) All affected fisherman and salt farmers should be compensated and rehabilitated. iv) Local people should be given priority for employment in the construction work for power plant and township.
Team Leader Socio-economic Survey Team, replied that harmonization of LA Ordinance of Bangladesh and JICA's Guidelines for Environmental and Social Considerations would be done by the project and be applied to mitigate the adverse impacts of the implementation of the project. Accordingly affected land owners will get replacement value of land. Business losers and employment losers will get adequate compensation and get opportunity for rehabilitation. Access roads will be constructed, schools and health center will be established where local people will have access to these facilities. Local people will be given priority for employment in the civil works of the project.
- Enrollment in vocational training courses based on assessment of skills
[Air pollution] (EIA) - To reduce PM emissions, Electrostatic Precipitator (EP; around 99.8% efficiency) will be installed.
- Duct will be provided with CEMS (Continuous Emission Monitoring System) with the supported infrastructure as required under the gas emission standards and IFC guideline
[Protective structure]
-Coordination will be continuously made with local authorities to improve the local infrastructure. [Compensation] - Compensation under the Law (CUL) for all the private land as stipulated by the Ordinance 1982: average of last 12 months’ sales values of same kind of land X 1.5 (50% premium)
- Cash grant that covers the difference between CUL and the replacement value (RV)
- Provision of stamp duty, land registration fee, capital gains tax and value added tax incurred for replacement land
[Electrification] Electrification of surrounding area will be examined. [Education] School facilities at power plant will be shared with the local residents. [Health] Health facilities at power plant will be shared with the local residents.
Mr. Enamul Hauqe Chowdhury, Chairman, Matarbari Union Parisad told that there were both positive and negative perceptions for the construction of coal based power plant. People of Matarbari Union is very concerned about the adverse impact of the coal fired power plant. Matarbari Union is densely populated and commercially important area. Because of construction of power plant a large number of people of Matarbari Union will be directly and indirectly affected and many will lose their business, wages and income for livelihood. He suggested that as Dhalgata Union is less populated and commercially less important Union than that of Matarbari the proposed site for power plant and township can be shifted towards south namely Hasherchar, Khaserdia and Bharatagona villages along with Dhalgata Union.
Socio-economic Survey Team replied that there were several selection criteria for selection of location of power plant. Availability of land was one of the selection criterion. Availability of fuel was also another criterion in proposed power plant the primary fuel would be imported coal which would require transportation and unloading facilities. In Matarbari, coal might be imported from foreign countries by large vessels and unloading jetty facility would be created there proposed site mentioned by Mr. Enamul Haque Chowdhury would not be suitable for that consideration. Moreover, after thorough analyses from numerous aspects, not only from social aspect but from environmental, financial, technical aspect, the present location was finally prioritized and accepted.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-1
Section-4 Detailed Description of Impact and Category of Project Affected Persons (PAPs)
4.1 Power Plant
4.1.1 Pre-construction Phase and Construction Phase (1) Land Acquisition Findings: It is anticipated that 16 households currently living on the site without permission and four households who purchased the land will have to vacate their domiciles due to the land acquisition for the construction of the power plant. Apart from resettlement, land owners of the project site area will lose their land. Employers/ employees of salt farms and shrimp farms will lose their means of livelihood. Those people who run business, employers or employees at salt farms and shrimp farms in the site will lose their livelihood means. Note that the site selection was reconsidered to the present site from the previous one (2 km south), where large settlements were found on private land, in order to avoid a large-scale resettlement. 343 households and 2,031 people will be affected by the construction of the power plant and the port facility. They had complex land use patterns: some of them had lands of their own, rented additional private land and government land; some others had no land but rented private land and had domicile without permission. The following table shows the anticipated impact to the 343 households. The number of household for each category is cumulative as most of households have several kinds of statuses to the land they use.
Table 4-1: Anticipated Social Impact to 343 Households (Power Plant)
Category Impact
No. of HH
(cumulative)
No. of HH
Members
(cumulative)
Owners of private land
Own & live
Lose land ownership
Lose shelters and be physically
displaced
4 25
Own but do not live Lose land ownership 237 1,429
Users of private land
(lease) Lose tenant rights 77 460
Users of government
land with official
agreement
Lose tenant rights 10 70
Users of government
land without official
agreement
Lose occupancy of land 140 844
Squatters living on
government land
Lose occupancy of land for living
place
Lose shelters and be physically
displaced
16 86
Note: HH means household.
(Source: JICA Study Team)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-2
Mitigation Measures: Not only a compensation plan but also a livelihood restoration program for affected people shall be established.
(2) Disturbance to Poor People Findings: There are poor households among those to be resettled and/or will lose their livelihood. The household monthly income of 343 households (2,031 people) directly and indirectly affected by this project is from zero taka to 842,000 taka, and the income of nearly 60% of the households is within the range of 10,000 taka to 30,000 taka. For individual monthly incomes, 44% of the all family members fall into the range of 2,000 taka to 4,000 taka. According to the national household revenue and expenditure survey conducted in 2010, the poverty line of agricultural area of Bangladesh is 1,211.57 taka per person/ month, and Chittagong District is 1,304.64 taka per person/ month. Setting the poverty line at 1,500 taka per person/ month for the proposed power plant site at the end of 2012, less than 10% of the local population falls below the poverty line on income basis. This rate is far better than the poverty rate of rural areas for the whole of Bangladesh (35.2%), and of the Chittagong District (31.0%). Mitigation Measures: Their living conditions will not deteriorate compared to their current conditions, and they will have job opportunities at the construction site. The employment of local people should be promoted to increase employment opportunities for various subcontract work resulting from the power plant construction activity. However, approximately 70% of heads of household are illiterate or can only write their signatures, so these people can only be engaged in very simple tasks due to their lack of skills. Livelihood restoration measures shall be established, including job training for those who want it.
(3) Deterioration of Local Economy such as Losses of Employment and Livelihood Means/ Land Use and Utilization of Local Resources
Findings: It is expected that employers and employees of salt farms, shrimp farms, and fishermen will lose their means of livelihood. Fishing activities around the site will also be affected due to a rise of water temperature and restriction of fishing. The implementation of this project will change the traditional land use patterns and utilization of local resources, which may have a large impact on the existing local economy. About 70% of the heads of 343 households that will be directly or indirectly affected are working in salt or shrimp farms as laborers, mazi, businessmen or cultivators. Including laborers from outside, there are 165 permanent and 892 temporary employees involved in shrimp cultivation, salt farming, fishing activities and others. There are also twelve sharecroppers. Twenty two businessmen stated they received cash income from the salt business and three stated they received income from agriculture. There was also one boatman, six carpenters, and one tea seller. Approximately 70% of heads of household are illiterate or can only write their signatures, so they can only be engaged in very simple tasks due to their lack of skills. The sandy beach is 7km long at the west coast of Matarbari Island, according to the Maheshkhali Upazila Officer. The width of the navigation channel to be altered is 400m and the length of discharge outlet is 100m, resulting in less than 10% of the sandy beach becoming disappeared. Then fishing ground for push net will be loss. Fishermen around the project site fish offshore (3-50km from the coast), and as all dredged material will be land filled into land sites, not disposed into the ocean, therefore, there is no expected impact on fishery by the power plant construction. The catches of shrimp fly in the coastal area may be affected by the change of the sand beach due to the construction of the navigation channel and water outlet. Mitigation Measures: Although the number of salt and shrimp farms will decrease due to the construction of the power plant, employment opportunities will increase for various subcontract work of the construction. Local people will be given priority in employment. Livelihood restoration measures shall be established, including job training for those who want it. Decreased income from shrimp-fly fishing of the fishermen may be easily supplemented by increased job opportunities and job switching. Job training shall be provided for those who want it in order to assist in livelihood restoration.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-3
(4) Disturbance to Water Usage, Water Rights, etc. Findings: All water to be used for the construction work will be transported by vessels and stored in a tank. Ground water and river water will not be used. The local economy may be affected by turbid water discharged from the construction site. Outflows of street dust and oil during rainy periods may also have certain effects. The turbid water discharged from the construction site and any oil spills may affect the water quality of the marine area, rivers and ground water, and adequate mitigation measures shall be taken. Mitigation Measures: Water quality of well water, which is the main supply of drinking water, shall be monitored in order to monitor any adverse effects on ground water.
(5) Disturbance to Existing Social Infrastructure and Services Findings: As material and equipment transportation will be mainly conducted by vessels, increased marine traffic may disturb existing marine traffic including fishing boats. Additionally, vehicles transporting commuting workers may cause increased traffic and traffic jams around the project area. Mitigation Measures: In regard to vessels, water routes shall be determined after consultation with the related authorities. And in regard to vehicles, bus use will be promoted to reduce increasing the number of vehicles on the roads. The bus schedules shall be managed in consultation with related organizations.
(6) Social Institutions such as Social Infrastructure and Local Decision-making Institutions Findings: Laws of Bangladesh stipulate the need to conduct public consultations in land acquisition processes. The Deputy Commissioner’s Office of Cox’s Bazar District will officially take responsibility for initiatives to conduct local consultations concerning compensation. Mitigation Measures: A number of consultations with local residents have been conducted in preparing the draft LARAP. In consideration of changing emotions of local residents over the course of negotiations with office staff, personnel responsible for responding to complaints or suggestions from local residents will work at the power plant office in the resettlement process.
(7) Misdistribution of Benefits and Compensation - Findings: There is a possibility of unequal compensation among local residents. Mitigation Measures: Equality of compensation shall be assured in the resettlement process.
(8) Local Conflicts of Interest Findings: Local conflicts may occur between local residents who may feel that they receive unfair compensation and other local residents or conflict with staff of the Deputy Commissioner’s Office. Conflict may occur between local residents and external workers because of any changes to local customs if external workers cannot understand local customs. Mitigation Measures: A number of consultations with local residents have been conducted in preparing the draft LARAP. In the resettlement process, personnel responsible for responding to complaints or suggestions from local residents will work at the power plant office. Local people should be employed at the power plant to the maximum extent possible, and any workers from other countries should be taught to respect local customs in order to facilitate good relationships with local people. The lodgings of the project workers should be equipped with sufficient living facilities to keep workers at the project site as much as possible.
(9) Gender Findings: There are women among those to be resettled and/or lose their livelihood means. They currently have low living standards, living without proper facilities, will have better access to social services throughout the year. However, wives of those men who lose their land or jobs may suffer from adverse effects on their household economy.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-4
(10) Children's Rights Findings: Children are often forced to work and cannot attend school, and this may occur in the construction stage of the power plant as well. There will be children among those to be resettled and/or lose their livelihood means. Children from those households losing their land or jobs may suffer from adverse impact on their household economy such as drop-out of school. Mitigation Measures: Labor contracts between the construction industry and children shall be prohibited. Regular patrols to check for child workers shall be conducted.
(11) Infectious Diseases such as HIV/AIDS Findings: A temporary influx of migrant labor during the construction period may increase the risk of sexual transmitted diseases, etc. Mitigation Measures: Local people should be recruited for simple work as much as possible so to minimize the risk of infectious diseases being transmitted from external workers. Pre-employment and periodic medical check-ups should be conducted for external workers (technical workers, etc.).
(12) Work Environment (Including Work Safety) Findings: A high risk rate of accidents is predicted for the construction work. Mitigation Measures: Construction companies should establish work safety plans and submit them to CPGCBL to obtain approval. Work safety plans should stipulate mitigation measures on soft aspects (safety training, etc.) and hard aspects (provide workers with appropriate protective equipment, etc.).
(13) Accidents Findings: Land traffic and marine traffic accidents during construction work may occur. Mitigation Measures: As prevention measures for land traffic accidents, observation of traffic regulations, and training and education on safe driving will be implemented. The bus schedules shall be communicated to people in the surrounding villages. For vessel operation, marking buoys will be set around the construction area for marine safety. Vessel schedules shall be announced to fishermen, etc.
4.1.2 Operation Phase
(1) Disturbance to Poor People Findings: Resettled people may experience a deterioration of their household economies and livelihood losses due to their relocation if appropriate measures are not taken. The road around the project site is especially in a bad condition (not possible to travel in the rainy season), preventing local access to social services. Mitigation Measures: Poor people, who currently have low living standards, living without proper facilities, will have better access to social services throughout the year if roads are improved along with the construction of the power plant, especially improved access during the rainy season. An access road, a community road that will replace the existing road and a road around the power plant boundary shall be built. These roads will be built with sufficient height so that they can be used even in the rainy season. Local people should be employed to work at the power plant and related facilities to the maximum extent possible according to their skills.
(2) Deterioration of Local Economy such as Losses of Employment and Livelihood Means/ Land Use and Utilization of Local Resources
Findings: There will be permanent losses or reduction of livelihood means in salt farming, shrimp farming and fishing activities. Employment opportunities will be offered at the power plant for local people. The implementation of this project will change the traditional land use patterns and utilization of local resources, which may have a large impact on the existing local economy. Both fishermen around the project site who operate in the marine area (3-50km from the coast) outside of the adverse effects of thermal effluents and other wastewater discharge of the power plant, and fish catches, will not be affected.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-5
Mitigation Measures: Local people should be employed to work at the power plant and related facilities to the maximum extent possible according to their skills. Livelihood restoration means shall be conducted including job training for those who want it. Services (e.g., laundry, catering services, etc.) and products offered by the local community should be used by the power plant as much as possible. Efforts for area development will be promoted, including the establishment of a local development plan in cooperation with the local government.
(3) Disturbance to Water Usage, Water Rights, etc. Findings: In the operation phase, all water used for the project will be supplied not from ground water or river water, but from sea water desalinated by reverse osmosis. The local economy may be affected by discharged water from the power plant into the sea. Mitigation Measures: Wastewater generated from the power plant will be appropriately treated before discharge. Waste will also be appropriately treated and disposed of, with necessary countermeasures to prevent any seepage of oil and chemicals.
(4) Disturbance to the Existing Social Infrastructure and Service Findings: Traffic volume and traffic jams will increase in the surrounding roads during the operation phase. Mitigation Measures: Mitigation measures to decrease traffic volume shall be conducted, such as the promotion of bus use. Additionally, an access road, community road and road around the power plant boundary shall be built. These roads will be built with sufficient height so that they can be used even in the rainy season, in order to enable public access to markets and social services. In addition, a school and medical facility constructed within the power plant site shall be open to all local people for the improvement of their lives.
(5) Misdistribution of Benefits and Compensation Findings: People who live in other areas have limited access or have been prevented from accessing the school and medical facility within the power plant site and the access road, which may cause grievances. Mitigation Measures: The access road, school and medical facility constructed within the power plant site shall be open to all local people to the maximum extent possible in order to improve peoples’ lives.
(6) Local Conflicts of Interest Findings: Local conflicts of interest may occur between employers and employees of salt farms, shrimp farms and the fishing industry, and between local administration bodies and local political leaders. Conflicts among local residents may occur if such benefits were misdistributed. Mitigation Measures: Local people should be employed at the power plant to the maximum extent possible, and workers from other countries should be taught to respect local customs in order to facilitate good relationships with the local people. The lodgings of project workers should be equipped with sufficient living facilities in order to keep workers at the project site as much as possible. The access road, school and medical facility constructed within the power plant site shall be open to all local people to the maximum extent possible for the improvement of peoples’ lives.
(7) Gender Mitigation Measures: Residents will have better access to social services throughout the year if roads are improved along with the construction of the power plant, especially access during the rainy season. (8) Children’s Rights Findings: There is a possibility that children may be forced to work and not attend school. Further, children’s rights to go to school may further deteriorate if the access way to their school is physically blocked by the construction site. Mitigation Measures: Labor contracts between the subcontractors and children shall be prohibited. Regular patrols to check for child workers shall be conducted. The access road,
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-6
community road and road around the power plant boundary shall be built with sufficient height so that it can be used even in the rainy season, so that access to markets and social services shall be improved, including access by children.
(9) Work Environment (Including Work Safety) Findings: Work accidents involving workers may occur at the power plant site. Mitigation Measures: CPGCBL shall establish a work safety plan. The work safety plan shall stipulate mitigation measures on soft aspects (safety training, etc.) and on hard aspects (provide workers with appropriate protective equipment, etc.).
(10) Accidents Findings: Marine traffic and land traffic accidents may occur during plant operation. Fires caused by spontaneous ignition of stored coal may also occur. Mitigation Measures: Observation of traffic regulations, installation of traffic signs, and training and education on safe driving shall be conducted for land traffic vehicles. For ocean navigation, determining water routes after consultation with related authorities, and setting course buoys around navigation channel for marine safety will be undertaken as prevention measures for accidents. Fire prevention measures shall be conducted including regular watering of the coal storage site, installation of fire protection equipment in the power plant and organization of fire-fighting team and fire-fighting training.
4.2 Port Facility
4.2.1 Pre-construction Phase and Construction Phase (1) Disturbance to Existing Social Infrastructure and Social Services Findings: Pump dredgers will be used in dredging work in the marine area, and increased marine traffic may slightly disturb the existing marine traffic including fishing boats. Mitigation measures: The construction area shall be determined after consultation with related authorities.
(2) Work Environment (Including Work Safety) Findings: A high risk rate of accidents is predicted during the construction work. Mitigation measures: Construction companies shall establish work safety plans and submit them to CPGCBL to obtain approval. Work safety plans shall stipulate mitigation measures on soft aspects (safety training, etc.) and on hard aspects (provide workers with appropriate protective equipment, etc.).
(3) Accidents Findings: Marine traffic accidents may occur during the construction work. Mitigation measures: The navigation route of vessels shall be determined after consultation with related authorities. Marking buoys will be set around the construction area for marine safety.
4.2.2 Operation phase (1) Disturbance to the Existing Social Infrastructure and Services Findings: Navigation of large coal transport vessels and tankers will cause increased marine traffic, and may disturb the existing marine traffic including fishing boats. Mitigation measures: Navigation routes shall be determined after consultation with related authorities.
(2) Work Environment (Including Work Safety) Findings: Accidents may be caused by the entry and departure of vessels and the loading-unloading of coal. Mitigation measures: Work safety plans shall be established that stipulate mitigation measures on soft aspects (safety training, etc.) and on hard aspects (provide workers with appropriate protective equipment, etc.).
(3) Accidents Findings: Marine traffic accidents may occur.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-7
Mitigation measures: Navigation routes shall be determined after consultation with related authorities. Course buoys will also be set around navigation channel for marine safety. 4.3 Transmission Line 4.3.1 Pre-construction Phase and Construction Phase
Findings: It is anticipated that 16 households currently living on the site without permission and four households who purchased the land will have to vacate their domiciles due to the land acquisition for the construction of the power plant. Apart from resettlement, land owners of the project site area will lose their land. Employers/ employees of salt farms and shrimp farms will lose their means of livelihood. Those people who run business, employers or employees at salt farms and shrimp farms in the site will lose their livelihood means. Note that the site selection was reconsidered to the present site from the previous one (2 km south), where large settlements were found on private land, in order to avoid a large-scale resettlement. 343 households and 2,031 people will be affected by the construction of the power plant and the port facility. They had complex land use patterns: some of them had lands of their own, rented additional private land and government land; some others had no land but rented private land and had domicile without permission. The following table shows the anticipated impact to the 343 households. The number of household for each category is cumulative as most of households have several kinds of statuses to the land they use.
(1) Land Acquisition and Compensation The construction of one tower base requires 2m2 x 4 = 8m2 of land. The construction of 157 transmission towers, including angle towers and suspension towers, is planned requiring a total amount of 1,256m2 of land acquisition. Voluntary offers of land do not require compensation, but it is assumed here that all land necessary for tower construction will be acquired. The table below shows the details of the assumed affected people. Land acquisition will be conducted on the basis of compensation at replacement cost. As the land to be acquired for each transmission tower is small, it is not expected that there will be any semi-permanent loss of livelihood means. However, there is a possibility of temporary impact on livelihood means during the construction period.
Table 4-2: Affected people and land owners at angle tower points
Category Impact No. of HH
No. of HH Members
Owners of private land - Temporarily affected during construction period
8 83
Users of government land with official agreement
- Temporarily affected during construction period
1 9
Total 9 92
In the case of acquisition of farm land, entry into such land will be temporarily halted during the construction period and hence farming will be impossible. Also, all trees within clearance distance from cables will be removed. All standing crops and trees lost by the land owners will be compensated with a market price.
(2) Deterioration of Local Economy such as Losses of Employment and Livelihood Means/ Land Use and Utilization of Local Resources
Farm land located at the base of the towers will be lost, although the total area will be small. Land owners and users of tower locations will be tentatively affected during construction period resulting in a loss of means of livelihood. In addition, land located under the transmission line will decline in value. Tall trees will be cut down. However local people will be employed for construction work. In the case of acquisition of farm land, entry into such land will be prohibited temporarily during the construction period and hence farming will be impossible. The construction work aims to employ as many local residents as possible, and to use the services and products of the local community as much as possible.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-8
The transmission line construction areas can be reused for farming after the completion of each transmission tower construction, except for the 2m2 x 4 = 8m2 of land used for tower bases. Therefore, adverse effects on income will be very limited.
(3) Disturbance to Water Usage, Water Rights, etc. There may be soil runoff from the exposed soil of the embankments and cut slopes, resulting in water pollution of the downstream area of the surrounding rivers and consequently alteration of water use. The transmission line route shall avoid using steep sloping land, and any slopes used shall be reinforced with concrete, plantation or other means to minimize soil runoff and turbid water generation.
(4) Social Institutions such as Social Infrastructure and Local Decision-making Institutions The Deputy Commissioner’s Office of Cox’s Bazar District will be responsible for taking the initiative to conduct local consultations concerning compensation. In consideration of the possible changing emotions of local residents over the course of negotiations with office staff, Compensation should be carried out in consultation with the local people.
(5) Cultural Heritage There is a possibility that some historical, cultural and/or archaeological property and heritage may be found in the course of the construction work. In this case, construction work will be interrupted and experts will be consulted.
(6) Infectious Diseases such as HIV/AIDS A temporary influx of migrant labor during the construction period may increase the risk of transmitted diseases. Local people will be recruited for simple work as much as possible and there is low risk of infectious diseases transmitted from external workers. Pre-employment and periodic medical check-ups shall be carried out for external workers (technical workers, etc).
(7) Work Conditions (Including Work safety) A high risk rate of accidents is predicted during the construction work. The construction company shall establish a work safety plan and submit it to PGCB to obtain approval. The work safety plan shall stipulate mitigation measures on soft aspects (safety training, etc) and on hard aspects (provide workers with appropriate protective equipment, etc).
(8) Accidents There may be land traffic accidents during the construction work. Also, other accidents may occur, including soil runoffs and tower breakages caused by cyclones, etc. As prevention measures for land traffic accidents, observation of traffic regulations, installation of traffic signs and training and education on safe driving will be implemented. In addition, the transmission line route shall avoid using steep sloping land, and any slopes used shall be reinforced with concrete, plantation or other means to minimize soil runoff and turbid water generation.
4.3.2 Operation Phase
(1) Deterioration of Local Economy such as Losses of Employment and Livelihood Means Farm land located at the base of towers will be lost, although the total area will be small. The transmission line construction area can be reused for farming after the completion of the construction, except for the 2m2 x 4 = 8m2 of land for tower bases, and any adverse effects on income will be very limited.
(2) Disturbance to Water Usage, Water Rights, etc. Soil runoff may occur from the exposed soil of the embankments and cut slopes, resulting in water pollution of the downstream area of the surrounding rivers and possible alteration of water use. The transmission line route shall avoid using steep sloping land, and any slopes used shall be reinforced with concrete, plantation or other means to minimize soil runoff and turbid water generation.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-9
(3) Work Conditions (Including Work Safety) There is a risk that accidents, such as electrification and workers falling, may occur during maintenance work. A work safety plan shall be established including mitigation measures on soft aspects (safety training, etc) and on hard aspects (provide workers with appropriate protective equipment, etc).
(4) Accidents Accidents may occur from such factors as soil runoffs and tower breakages caused by cyclones, etc. The transmission line route shall avoid using steep sloping land, and any slopes used shall be reinforced with concrete, plantation or other means to minimize soil runoff and turbid water generation.
4.4 Township Development 4.4.1 Pre-construction Phase and Construction Phase
(1) Land Acquisition Findings: It is anticipated that land owners of the project site area will lose their land. Employers/ employees of salt farms and shrimp farms will lose their means of livelihood. Those people who run business, employers or employees at salt farms and shrimp farms in the site will lose their livelihood means. 207 people belonging to 41 households will be directly affected by the construction of the
Township development. They had complex land use patterns: some of them had lands of
their own, rented additional private land and government land. The table below shows the
anticipated impact to the 41 households. The list of affected persons for loss of land is
placed at Annexure-1.
Table 4-3: Anticipated Social Impact to 41 Households (Township Site)
Category Impact
No. of HH
(cumulative)
No. of HH
Members
(cumulative)
Owners of private land
Own but do not live Lose land ownership 41 207
Note: HH means household.
Mitigation Measures: Not only a compensation plan but also a livelihood restoration program for affected people shall be established.
(2) Disturbance to Poor People Findings: There are poor households among those to be resettled and/or will lose their livelihood. The household monthly income of 41 households (207 people) directly affected by this project ranges from below 1000 taka to 70000 taka, and the income of nearly 41.46% of the households is within the range of 10,000 taka to 30,000 taka. For individual monthly incomes, 19.51% of the family members fall into the range of 2,000 taka to 3,000 taka. According to the national household revenue and expenditure survey conducted in 2010, the poverty line of agricultural area of Bangladesh is 1,211.57 taka per person/ month, and Chittagong District is 1,304.64 taka per person/ month. Setting the poverty line at 1,500 taka per person/ month for the proposed power plant site at the end of 2012, less than 10% of the local population falls below the poverty line on income basis. This rate is far better than the poverty rate of rural areas for the whole of Bangladesh (35.2%), and of the Chittagong District (31.0%).
Mitigation Measures: Their living conditions will not deteriorate compared to their current conditions, and they will have job opportunities at the construction site. The employment of local people should be promoted to increase employment opportunities for various subcontract work resulting from the construction of township activity. However,
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-10
approximately 51.22% of heads of household are illiterate or can only write their signatures, so these people can only be engaged in very simple tasks due to their lack of skills. Livelihood restoration measures shall be established, including job training for those who want it.
(3) Deterioration of Local Economy such as Losses of Employment and Livelihood Means/ Land Use and Utilization of Local Resources Findings: It is expected that employers and employees of salt farms, shrimp farms, and fishermen will lose their means of livelihood. Fishing activities around the site will also be affected because of restriction of fishing. The implementation of this project will change the traditional utilization of local resources, which may have a large impact on the existing local economy.
Apart from such land owners and users, there are also permanent and temporary laborers employed by them. Including laborers from outside, there are 12 permanent and 52 temporary employees involved in shrimp cultivation, salt farming, fishing activities and others.
Mitigation Measures: Although the number of salt and shrimp farms will decrease due to the construction of the township, employment opportunities will increase for various subcontract work of the construction. Local people will be given priority in employment. Livelihood restoration measures shall be established, including job training for those who want it. Increase of job opportunities and imparting of job training will help largely restoration of livelihood and income of the affected families.
(4) Social Institutions such as Social Infrastructure and Local Decision-making Institutions Findings: Laws of Bangladesh stipulate the need to conduct public consultations in land acquisition processes. The Deputy Commissioner’s Office of Cox’s Bazar District will officially take responsibility for initiatives to conduct local consultations concerning compensation.
Mitigation Measures: A number of consultations with local residents have been conducted in preparing the draft LARAP. In consideration of changing emotions of local residents over the course of negotiations with office staff, personnel responsible for responding to complaints or suggestions from local residents will get facility to get employment in civil work of township site and involve in other generated new service activities in the resettlement process.
(5) Misdistribution of Benefits and Compensation Findings: There is a possibility of unequal compensation among local residents.
Mitigation Measures: Equality of compensation shall be assured in the resettlement process.
(6) Local Conflicts of Interest Findings: Local conflicts may occur between local residents who may feel that they receive unfair compensation and other local residents or conflict with staff of the Deputy Commissioner’s Office. Conflict may occur between local residents and external workers because of any changes to local customs if external workers cannot understand local customs.
Mitigation Measures: A number of consultations with local residents have been conducted in preparing the draft LARAP. In the resettlement process, personnel responsible for responding to complaints or suggestions from local residents will get facility to work in the civil construction of the township site and involve in other newly generated service activities. Local people should be employed at the power plant to the maximum extent possible, and any workers from other countries should be taught to respect local customs in order to facilitate good relationships with local people. The lodgings of the project workers should be equipped with sufficient living facilities to keep workers at the project site as much as possible.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-11
(7) Gender Findings: There are women among those to be resettled and/or lose their livelihood means. They currently have low living standards, living without proper facilities, will have better access to social services throughout the year. However, wives of those men who lose their land or jobs may suffer from adverse effects on their household economy.
(8) Children's Rights Findings: Children are often forced to work and cannot attend school, and this may occur in the construction stage of the township. There will be children among those to be resettled and/or lose their livelihood means. Children from those households losing their land or jobs may suffer from adverse impact on their household economy such as drop-out of school.
Mitigation Measures: Labor contracts between the construction industry and children shall be prohibited. Regular patrols to check for child workers shall be conducted.
(9) Infectious Diseases such as HIV/AIDS Findings: A temporary influx of migrant labor during the construction period may increase the risk of sexual transmitted diseases, etc.
Mitigation Measures: Local people should be recruited for simple work as much as possible so to minimize the risk of infectious diseases being transmitted from external workers. Pre-employment and periodic medical check-ups should be conducted for external workers (technical workers, etc.).
(10) Work Environment (Including Work Safety) Findings: A risk rate of accidents is predicted for the construction work.
Mitigation Measures: Construction companies should establish work safety plans and submit them to CPGCBL to obtain approval. Work safety plans should stipulate mitigation measures on soft aspects (safety training, etc.) and hard aspects (provide workers with appropriate protective equipment, etc.).
4.5. Entitlement for Different Types of Losses.
Based on the findings and analyses in the field surveys, the entitlement matrix for the PAPs at the construction site of power plant and port facility, and transmission line route and township site has been prepared. The Entitlement Matrix lists 10 types of losses and category of entitled persons and corresponding proposed entitlements to cover all possible losses to achieve at least the same level of livelihood of the affected households. Entitlement Matrix are as in the table below:
Table 4-4: Entitlement matrix for PAPs (power plant, port facility , transmission line and Township Sites)
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
1. Loss of private land
Legal owners of land � Cash compensation under the law (CUL) for all the private land stipulated by the Ordinance 1982 is the average of last 12 months’ sales values of same kind of land X 1.5 (50% premium). Cash grant that covers the difference between CUL and the replacement value (RV)
� Provision of stamp duty, land registration fee incurred for replacement land (15%)
� value added tax � One-time assistance for lost
income (based on monthly
DC PVAT, JVT CPGCBL
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-12
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
income for three years at minimum wage rates)
Tenants and leaseholders
� Provision of another land including 50% premium
� Provision of stamp duty, land registration fee (15%) If land is purchase by the compensation money
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
2. Loss of government land including khas land
Tenants and lessee � Provision of another khas land (assuming tenants and lessee will seek private land, 50% premium is added)
� Provision of stamp duty, land registration fee (15%) If land is purchase by the compensation money
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
DC PVAT, JVT CPGCBL
Occupants without legal tenure
� Provision of another khas land (assuming tenants and lessee will seek private land, 50% premium is added)
� Provision of stamp duty, land registration fee (15%) If land is purchase by the compensation money
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
3. Permanent loss of means of livelihoods/ source of income
� Lessor (land owners who rent their land will lose income from land lease contract)
� One-time assistance for opportunity loss (based on the lease amount) (assuming the inflation rate stays 10%)
DC, DOF PVAT, JVT CPGCBL
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-13
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
� Permanent laborers
� Temporary laborers
� Sharecroppers
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
� Enrollment in vocational training courses based on assessment of skills (@300 taka / day for 120 days)
Businessmen, employers of salt farms, shrimp farms and fishing sites, self-employed people
� One-time assistance for opportunity loss (based on the lease amount) (assuming the inflation rate stays 10%)
� One-time assistance for lost income (based on monthly income for three years at minimum wage rates)
4. Loss of residential/ commercial structures
Legal title holders Owners of structures
� Cash compensation for affected portion of the structure and other fixed assets at replacement cost ( plus 50% premium)
� Option to be compensated for entire structure if remaining structure is no longer viable
� Provision of all taxes, registration costs and other fees incurred for replacement structure (15%)
� Reconstruction grant for reconstruction / repair of the remaining structure (@15 taka / sft)
� Shifting allowance based on actual costs of moving (@10 taka / sft)
� Owners to take away all salvage materials
DC PVAT, JVT, PWD CPGCBL
Legal tenants/ lease holders of the structure
� Cash compensation equivalent to replacement cost of structure (or part of structure) for the portions of the structure constructed by the tenant/ leaseholder (plus 50% premium)
� Reconstruction grant for reconstruction / repair of the remaining structure (@15 taka / sft)
� Shifting allowance based on actual cost of moving (@10 taka / sft)
� Owners to take away all salvage materials
Socially recognized owners/ unauthorized occupants
� Cash compensation equivalent to replacement cost of structure (or part of structure) erected by the displaced person (plus 50% premium)
� Reconstruction grant for reconstruction / repair of the remaining structure (@15 taka /
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
4-14
No Type of Loss Entitled Persons (Beneficiaries)
Entitlement (Compensation and Assistance Package)
Responsible Organizations
sft) � Shifting allowance based on
actual cost of moving (@10 taka / sft)
� Owners to take away all salvage materials
5. Loss of access to Residential/ Commercial Structures
Tenants of rented leased properties (but not constructed the whole part of the structure
� One time cash grant for facilitating alternative housing/ CBEs Tk. 15000/= per household
� Shifting allowance per household based on family members @ 3000/= per member minimum Tk. 9000/= maximum 12000/=
PVAT CPGCBL
6. Loss of standing crops at home gardens, shrimp, and fish
Land owners, Bargadar, Lessee and Unauthorized occupant of land
� One time assistance for opportunity loss (based on the lease amount) (assuming the inflation rate stays 10%)
DC PVAT, DOF,DAM CPGCBL
7. Loss of timber and fruit bearing trees
Legal owner of land/Socially recognised owner
� Market value of trees � Owner will be allowed to fell and
take away their trees
DC PVAT, BFD,DAM CPGCBL Non-titled user of
land
8. Temporary loss of land during construction
Owners with legal title, tenants, leaseholders
� Rental assistance for the period for which the land is temporarily requisitioned
� Temporarily requisitioned land will be returned to owners rehabilitated to original or preferably better condition
DC PVAT CPGCBL
9. Temporary loss of access to land, structure, utilities, common property resource during construction
Owners with legal title, tenants, leaseholders
� Provision of temporary access and relocation where possible
� Restoration of access to the land, structure, utilities
DC PVAT CPGCBL
10. Temporary loss of livelihood/ source of income during construction
Business owners, tenants, leaseholders, employees, vendors
� One-time assistance for lost income based on monthly income for three years from products, minimum wage rates or based on actual income, verified through incomes of comparable businesses in the area
DC, DOF, DAM CPGCBL
(Source: JICA Study Team)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
5-1
Section-5
Livelihood Restoration and Improvement Plan
5.1 The livelihood restoration and improvement plan will be implemented based on consultation with PAPs and their socio-economic profile, living environment, level of education, etc. which were identified in the socioeconomic survey. CPGCBL have agreed to incorporate the following measures into livelihood restoration program.
Table 5-1: Livelihood restoration measures
Current situation Negative impact Program
- Nearly 80 % of Household heads are illiterate or only write their names.
- Only 43 % of the affected people are literate
- Hard to find job - Access to information is limited
- Power plant offers literacy classes to local children
- Skills remain undeveloped - Women stay home
- Hard to find good jobs - Salary stays low
- PS arranges skill training classes
- Job opportunity: limited - High unemployed rates - Daily labor - Children drop out of school
- PS offers jobs at PS and associated facilities
(Source: JICA Study Team)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-1
6.1 Coal Power Generation Company of Bangladesh Ltd.
The Coal Power Generation Company of Bangladesh Ltd. (CPGCBL) under the Ministry of Power Energy and Mineral Resources (MOPEMR) is the Executing Agency (EA) responsible for implementing the LARAP. CPGCBL shall establish a Project Management Unit (PMU) for the Project, headed by a Project Director (PD) that will be responsible for the overall execution of the project including land acquisition, relocation, resettlement and other related matters. The PMU will prepare a land acquisition (LA) plan for the land required to be acquired with the assistance from consultants and shall submit to the DC, Cox’s Bazar. An experienced implementing NGO / Consultancy Firm shall be hired by CPGCBL to assist them in implementation of resettlement program. To expedite the process, the LARAP implementing NGO/Consultancy Firm will assist the DC office and EA in the process of land acquisition. CPGCBL will allocate the required budget for additional grant on top of DC’s payment for land and resettlement benefits which are to be approved by GOB.
The Executive Engineer concerned under the direct supervision of the Project Director, will undertake day-to-day activities with the appointed IA. The Executive Engineer concerned will be the convener of the Joint Verification Team (JVT) and Property Valuation Advisory Team (PVAT). There will be a Grievance Redress Committee for resolution of disputes. Grievance Redress Mechanism is detailed in Section 7. The Executive Engineer concerned will coordinate and manage resettlement and rehabilitation of the APs, disburse resettlement benefits, and ensure AP‟s access to development programs. The PMU, with assistance from the NRS of PSC & IA will carry out the following specific tasks relating to LARAP implementation:
(i) Liaise with district administration to support LARAP implementation activities i.e. appointment of JVT, PVAT, GRC and RAC members, etc;
(ii) Discharge overall responsibility of planning, management, monitoring and implementation of the resettlement and rehabilitation program;
(iii) Ensure availability of budget for all activities; (iv) Synchronize resettlement activities and handover the encumbrance free land
to the contractor within the construction schedule; (v) Develop LARAP implementation tools and form necessary committees; (vi) Monitor the effectiveness of entitlement packages and the payment modality.
The appointed LARAP Implementing Agency will carry out an information campaign and involve affected persons including women in the implementation process. The IA will collect, computerize and process data for identification of eligible persons correctly for resettlement benefits and assess their entitlements as per LARAP policy. However, the PMU will make necessary scrutiny of indents of compensation and resettlement benefits submitted by the Implementing Agency and make payments after the indents are approved by the PD. The Executive Engineer of the PMU in charge of the resettlement management will report progress to the Project Director. He will work in close coordination with the respective field-based offices and IA on the day-to-day activities of the resettlement implementation.
The PMU, LA Office and the IA will execute joint verification of the property on the ROW by JVT, valuation of the affected property by PVAT and monitor the progress of the LARAP implementation work. The PMU will ensure coordination between the relevant departments, IA, GRC, RAC, PVAT and the Project affected people. Joint Verification Team (JVT) for quantification of affected properties, and a Property Valuation Advisory Team (PVAT) will be formed by the Ministry of Power, Energy and Mineral Resources (MOPEMR) for valuation of affected property, together with a GRC for resolution or redress of disputes. A proposed
Section-6 Implementation Arrangement and Organizational Responsibilities
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-2
LARAP implementation organogram is given below in Figure 6-1 . Figure 6-1 : LARAP Implementation Organogram
Affected Communities/ Project Affected Persons
Team Leader, IA
AM, Implementing Agency
GRC RAC
ADC Revenue
MIS Specialist, IA National
Resettlement
Specialist
Land Acquisition Officer
Executive Engineer,
PMU for
Resettlement
JVT PVAT
Project Director
Sub-Divisional Engineer, PMU
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-3
Institutional responsibilities for LARAP preparation and implementation activities are summarized in Table.
Table 6-1: Institutional Roles and Responsibilities Activity Responsible Agency
A. Project Initiation Stage and Institutional Setup
Formation of PMU EA
Recruitment of DSC,PSC & IA EA
Selection & finalization of sites for projects CPGCBL
Disclosure of proposed land acquisition and project details by issuing Public Notice
PMU
Meetings at community/household level with APs PMU
Capacity Building training PMU/PSC
B. LARAP Preparation and Updating Stage
Census of APs and socioeconomic survey PMU/PSC
Survey on unit prices for computing replacement costs JVT/PAVT/IA
Screening of vulnerable APs PMU/PSC/IA
Calculation of compensation and entitlements PMU/PSC/IA
Prepare/update of project LARAPs PMU/PSC/IA
Consultations on LARAPs and entitlements with APs PMU/PSC/IA
Incorporate comments and suggestions to LARAPs PMU/PSC/IA
Finalize LARAPs and submit to JICA. All draft LARAPs must be submitted to JICA for clearance prior to award of contracts. PMU/PSC/IA
JICA website disclosure JICA
C. LARAP Implementation Stage
Issuance of ID Cards to APs PMU/IA
Detailed Schedule for compensation action plan PMU/IA
Distribution of Relocation Notices to APs PMU/IA
Award of Checks for Land Compensation PMU/IA
Award of Checks for other Compensation & Assistance/ Rehabilitation PMU/IA
Confirm with JICA in writing when payment to APs has been completed. PMU
Income Rehabilitation Assistance and Training PMU/IA
Demolishing/ Relocation of Affected Structures/Assets PMU/IA
Grievances redress PMU/IA
Internal monitoring PMU/PSC
Review of LARAP Implementation by external monitoring Agency and final outcome
External Monitoring Agency
If LARAP Implementation found satisfactory, Notice to proceed for Civil Works is issued PMU
Upon approval of the project by JICA & Government and finalization of the detailed design and the LARAP, an experienced LARAP implementing NGO/Consultancy Firm shall be engaged as a consultant by the PMU.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-4
6.2 Other Agencies Involved in the Process
6.2.1 Deputy Commissioner The DC has the power to acquire land and to assess compensation of property thus acquired. The 1982 Ordinance provides the power to the DC, who conducts the acquisition through the Land Acquisition Officer (LAO) of concerned districts. The LAO (or his officers) along with PMU, CPGCBL and IA staff will conduct joint physical verification of property on the land in accordance with the Land Acquisition Proposal (LAP) to be submitted by PMU as soon as the detailed design and alignments for the project interventions will be available.
The DC office is responsible for the entire acquisition process from “notification to affected households” to “award of compensation to owners of property and payments of compensation”. Upon fulfillment of criteria of the LA office (i.e. necessary documents to make payment) the LA officials will prepare cheque and disburse to the EPs. PMU/IA shall liaise with concerned DC offices to complete the land acquisition process in a timely fashion. However, the LAO will prepare estimates of LA and request placement of fund from the PMU. Executive Engineer, PMU will be responsible to keep all kinds of liaison with DC office on behalf of PMU related to land acquisition procedures for implementation of LARAP. The LAO will also share the award and payment data with the Executive Engineer, PMU through IA to facilitate processing of resettlement data.
6.2.2 Project Supervision Consultant EA will engage a Project Supervision Consultant (PSC) to assist PMU to carry out quite a good range of activities including monitoring the safeguard requirements of the project. PSC will be responsible for updating Land Acquisition and Resettlement Action Plan (LARAP) and Coordinate and monitor its subsequent implementation. The project supervision consultant is required to: Assist in reviewing/revising LARAP based on the information and data made available by the implementing agency. The PSC will participate in the monthly co-ordination meeting and monitor the work of the IA The PSC will submit monthly progress activities report on LARAP implementation to EA.
6.2.3 LARAP Implementing Agency CPGCBL will engage an Implementing Agency (NGO/Social Consulting Firm) through the PMU for implementation of the LARAP at the field level. The CPGCBL through PMU will contract out clearly defined tasks of the LARAP Implementing Agency in detailed Terms of Reference such as consultation /public information campaign for rapport building, issuance of ID cards, payment of eligible benefits to affected households/ individuals, institutional development, skill training/management training, community awareness and empowerment, etc. The IA will initially create ID numbers for each entitled person (EP) as identified during the Joint Verification survey by the JVT and prepare an ID card for each EP with photograph. Photograph of the EPs will be attested by the concerned UP Chairman and pasted on the ID card. The ID card will comprise information on name, father’s/husband’s name, mother’s name, age, education, identifiable marks, detailed address, details of quantity of losses etc. The ID card will be issued by CPGCBL with the joint signature of the representatives of CPGCBL and IA and distributed among the EPs by the IA.
The Implementing Agency will assist the EPs in preparing documents and opening bank accounts in their names to receive cheque from CPGCBL. They will form focus groups with the affected people based on homogeneity and/or nearness and hold meetings on a regular basis to let them know their rights and entitlements as prescribed in the LARAP. The Executing Agency will form a Ward/Union based Resettlement Advisory Committee (RAC) to involve the local communities and DPs in the implementation process.
The Implementing Agency will establish an MIS section in their central office for record keeping of the DPs, recording individual ID numbers of the entitled persons, preparing entitled person’s (EP) files based on quantity of losses and entitlement cards (EC) based on loss type and entitlement. The IA will submit monthly progress reports to the PMU mentioning progress of activities to be carried out by them.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-5
Upon fulfillment of criteria i.e. necessary documents to make payment/benefits to the EPs, the IA will prepare payment debit vouchers & other documents for payment and CPGCBL will disburse account payee cheques to the EPs in a public place or Union Parishad (UP) office in presence of the UP Chairman/member, issuing prior notice to the concerned EPs. The CPGCBL will prepare a detailed Terms of Reference for the LARAP Implementing Agency.
6.2.4 Ministry of Power, Energy and Mineral Resources (MOPEMR) The MOPEMR will constitute three committees/teams i.e. Joint Verification Team (JVT), Property Valuation Advisory Team (PVAT) and Grievance Redress Committee (GRC). A sample gazette notification is placed at Annexure-2. Among these committees/teams, JVT and PVAT will be constituted with representatives from CPGCBL, LARAP implementing NGO and Deputy Commissioner (DC). The DC office will appoint representatives as member(s) of the teams for quantifying losses and determining valuation of the affected properties. CPGCBL and IA shall liaise with DC office to complete the tasks following the notification of the Ministry.
6.2.5 Joint Verification Team The MOPEMR will form a Joint Verification Team (JVT), for the project through a gazette notification to compare and review the physical verification data collected by the Implementing Agency with the DCs' assessment of loss of physical assets and their owners. The scope and responsibility of the JVT will be clearly defined in the gazette. The Implementing Agency will process the entitlements of the project-affected persons using the JVT data as one of the determinants. The JVT will be a three-member body and be comprised as follows:
• Executive Engineer, PMU, CPGCBL - Convener • Representative of Deputy Commissioner – Member • Area Manager, LARAP Implementing Agency – Member Secretary.
Terms of Reference:
i) The Joint Verification Team (JVT) will compare and review the physical verification data conducted by the Implementing Agency (IA) with DC's assessment of loss of physical assets and quantify the lost assets corresponding to their owners and prepare the final list of affected owners and members of the team will put their signatures on the related document /records and submit to the Project Director.
ii) JVT will identify the occupants/squatters on the Government land or land khas land owned by any Government Agency on the Right of Way of the project and prepare their lists and submit to the Project Director.
iii) In pursuance of the Resettlement Implementation Schedule JVT will complete the above mentioned assignments and submit the necessary documents /reports authenticated by the members of the team to the Project Director.
6.2.6 Property Valuation Advisory Team
A Property Valuation Advisory Team (PVAT) will be formed by the MOPEMR through a gazette notification for the project. The PVAT will review the assessment of the Implementing Agency on the market price of the property affected by the project at their replacement cost. The scope and responsibility of the PVAT will clearly be defined in the gazette. The Implementing Agency will process the entitlements of the project-affected persons using the PVAT data as one of the determinants. The PVAT will be comprised as follows: Executive Engineer, PMU, CPGCBL – Convener Representative of Deputy Commissioner – Member Area Manager, LARAP Implementing Agency – Member Secretary.
Terms of Reference (TOR):
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-6
i) The Property Valuation Advisory Team (PVAT) will review the assessment of the Implementing Agency on the market price of land and other properties affected by the project and determine their replacement cost.
ii) PVAT will asses and determine the replacement cost of affected projects of the occupants /Squatters on the land owned by Government/ or any Government Agency
iii) PVAT will assist the EA in determining the replacement cost of residential /commercial and other structures, trees, crops, fish stock etc.
iv) PVAT will assist the EA in defining and determining socio-economic criteria of the Vulnerable Households affected by the project.
v) In pursuance of the Resettlement Implementation Schedule PVAT will square up the above mentioned assignments and submit necessary document/records authenticated by its members to the Project Director.
The procedure for determining replacement value is described in Figure 3 below.
Figure 6-2 : Procedure for Determining Valuation of Property.
6.2.7 Resettlement Advisory Committees (RACs)
The Implementing Agency will assist the CPGCBL to form Union based RACs at project level to involve the local communities and DPs in the implementation process. The RACs will be comprised of a CPGCBL representative (Assistant Engineer or equivalent) as the chair, the representative of Implementing Agency as member secretary, two local key informants (Male-1 and Female-1 to be selected by CPGCBL) and representatives of various stakeholders and DPs including at least one female DP in the respective area as selected by PMU in consultation with the LGI representative. The committees will seek local inputs from the affected people and communities in the implementation process and assist the Executing
Identification of Alignment and Affected Property by
CPGCBL
PVAT to Collect Information
Conduct PVS for Structure, Trees for primary data
PD for approval of Unit Rate
FD, DOF, DAM and PWD for
secondary data
PVAT members • CPGCBL Representative • IA Representative • DC Representative
Prepare Mouja wise existing
Replacement Value/Unit Rate
Implementing Agency for
Preparing Budget
Key Informants
• Trader
• Broker
• Religious Leader
• Community Leader
• Local Elites
• Potential Buyer
• Potential Seller
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
6-7
Agency in all matters related to resettlement. The RACs will ensure local participation in the implementation of the Land Acquisition and Resettlement Action Plan.
6.2.8 Women Groups in Resettlement Process
The LARAP implementation will ensure a gender sensitive approach in planning, management and operations of resettlement. Separate groups of affected women persons will be formed and operated by the Implementing Agency. Feedback from the female DPs and female headed AHs will be obtained through these female focused groups for planning relocation and resettlement. The female staff engaged by Implementing Agency will identify needs of female DPs for income restoration approaches and implementation of the income restoration component of the LARAP. Women will be consulted during social appraisal and will be further consulted during the process of LARAP implementation.
6.3 Institutional Capacity Building
There is no established resettlement unit within CPGCBL with appropriate staffing. The PMU of CPGCBL will, therefore, need technical support in preparing and implementing the LARAP. As part of the institutional development program, the CPGCBL as the Executing Agency (EA) for the project implementation will need to establish its own resettlement unit (RU) at the PMU to assist the PMU in assigning the existing staff with additional responsibility of managing resettlement. A Project Supervision Consultant (PSC) will be engaged by the EA to assist RU to carry out a range of activities including implementing and monitoring the safeguards aspects of the project. The National Resettlement Specialist (NRS) of the PSC will be responsible for arranging or carrying out the activities of updating/finalizing the LARAP for the project with IR impacts based on information from the detailed engineering design documentation prepared by the Design & Supervision Consultant (DSC). The NRS will also oversee and monitor LARAP Implementation in close liaison with the PMU and IA.
To strengthen the expertise of CPGCBL and ensuring effective execution of all resettlement related tasks, further capacity development at both the PMU and field level is needed. The training will specifically focus on the differences between the provisions of the JICA policy and the relevant country laws. The designated Training Specialist and Resettlement Specialist within the PSC will arrange such training to PMU & field officers for capacity enhancement related to the resettlement planning and implementation. Training will cover major issues such as (i) Principles and procedures of land acquisition; (ii) Public consultation and participation; (iii) Entitlements and compensation & assistance disbursement mechanisms (iv) Planning and implementing income generating schemes for livelihood restoration (v) Management of relocation of displaced persons (iv) Grievance redress; (v) Implementation of Land Acquisition and Resettlement Action Plan and (vi) Monitoring of resettlement operations and its reporting etc.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
7-1
Section-7 Grievance Redress Mechanisms
Grievance Redress Mechanisms
Other than the grievance redress mechanism stipulated by the Ordinance 1982, CPGCBL will make efforts at project level to resolve grievances through negotiations involving representatives of PAPs, village heads and Union Parishad Chairmen. The Project Director will allocate a resettlement officer at the project office, who deals with such negotiations up front. The resettlement officer will be the entry point and receive all the inquiries, concerns and complaints directly from PAPs. A notebook will also be installed at the project office entrance for anybody to write suggestions anonymously. A grievance redress committee at project site will convene meetings monthly. Non-regular meetings will also be held ad-hoc basis as necessary at such places as it is considered appropriate (such as village, union, etc.) for dealing with urgent matters. The proceedings (or minutes of meetings) will be made with the object to promptly address the concerns and complaints using an accessible and transparent process to the PAPs, and to bring an amicable settlement between the parties. All reports will be recorded in Bengali language and provided to all parties concerned. The committee at project level will include the following people:
- Resettlement Officer - Representative from local NGO/CBOs - Representatives of Displaced Persons - Representative from local government - Local intellectuals or religious figures, who would represent the residents of the project
area and be publicly known to be persons of integrity, good judgment and commands respect.
7.1 Entitlement for Different Types of Losses
In case dispute is not resolved at local level, the matter will be placed before a grievance resolution committee at the Upazila level. The Upazila Nirbahi Officer will chair the committee comprised of the project level GRC members, Project Engineers and legal advisors. In case dispute still continues, the UNO will make a decision regarding entitlement and compensation, and the decision taken during negotiations and the meetings will be formally recorded for future reference and presentation in the court, if necessary. If the matter cannot be resolved at the Upazila level, complaints will be referred to the Project Director, who will head a committee jointly with the Deputy Commissioner. Members of GRC at the Upazila level (including those at the project level) are summoned at any time for inquiry from PD and DC. Steps for grievance are shown in the diagram below for easy reference. There will be no cost required when residents appeal to the authorities at each level. Each committee is responsible to solve the issues raised by the residents within 45 days.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
7-2
Figure7-1 Flow of Grievance Redress
Grievance Redress Committee at District Level
Grievance Redress Committe at UpazilaLevel
Grievance Redress Committee at Project (Union) Level
Project Affected People
Representatives of
local NGOs/ CBOs
Representatives of
PAPs
Local intellectuals
or religious figures
Upazila Nirbahi
Officer (UNO)Project Engineer Legal Advisors
Deputy
CommissionerProject Director
If not resolved, legal settlement sought
If not resolved, grievances further stated to District level
If not resolved, grievances further stated to Upazila level
Grievances state to the project (union) level
Court
Grievance
resolved
Grievance
resolved
Grievance
resolved
Resettlement
Officer
Representatives of
local government
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
8-1
There are socially vulnerable people among those to be resettled and/or lose their livelihood means: poor households, women, children, elders. Their living conditions however will not deteriorate compared to their current ones, and poor people who currently have deteriorated living standards without proper facilities will have better access to social services throughout the year if roads are improved along with the construction of the power plant, especially access during the rainy season. Deterioration of household economies and livelihood losses may occur, on the other hand, to the resettled people due to the relocation or losses of their livelihood means. Not all adult populations at the project site are literate, which often makes them stay unskilled. Wives of those men who lose their land or jobs and their children may suffer from adverse effects on their household economy. Number of male children who drop out of school may increase because of a huge demand of unskilled workers at the construction site if there is no age restriction of unskilled workers at the power plant site. Specific measures to the vulnerable groups taken in LARAP are as follows:
(1) Employment When employing local residents at the construction site as well as power plant and associated facilities when the power plant operates, - local residents will be more prioritized according to their skills - no child will be allowed to work in order to prevent their drop-out from schooling and
child labor. Periodic and regular patrol will be made to make sure there is no child. - local women will be more prioritized if the requires skilled meet local women’s. - Enrollment in vocational training courses based on assessment of skills (2) Education School facilities at power plant will be shared with the local residents. (3) Health Health facilities at power plant will be shared with the local residents. (4) Water and sanitation Water quality of tube wells and others will be checked periodically for the safety of local residents. (5) Electrification Electrification of surrounding area will be examined.
Section-8 Specific Measures provided to Vulnerable Groups and Income Rehabilitation Assistance
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9.1 Power plant and port facility site Budget allocation will be fully committed by CPGCBL and made available to cover the costs of land acquisition (including compensation and income restoration measures) within the agreed implementation period. CPGCBL will finance the resettlement compensation as they will be impacting on the local people’s livelihoods. In addition to the compensation stipulated by the Ordinance 1982, CPGCBL will be required to finance those non-titleholders. All the compensation will be done according to the principle of the replacement cost, which will require CPGCBL to pay the gap between CUL and the replacement value (top up). Based on the entitlement matrix for the PAPs shown in Table-4.4, the compensation package for the PAPs at the construction site of power plant has been drafted as in the tables below. Values appearing in the tables, such as land, income, standing crops etc., were the figures collected from the local residents through socioeconomic survey.
(1) Loss of private land
Table 9-1: Acquisition of private land from legal owners
Note: Unit price (decimal) 10,000 taka (identified in land price survey)
Unit price (m2) 247 taka Unit price (ha) 2,471,054 taka
Remarks: (a) CUL adds 50% premium to the current market price, not the average of last 12 months' sales values of same kind of land.
(b) Replacement value covers stamp duty and land registration fees incurred for replacement of land @0.15 VAT and contingency will be added for the total project cost. (c) Lost income includes monthly household income for 3 years. (d) Although 237 households identified in the household survey had 106.78 ha in total as of Dec 2012, land acquisition costs is estimated here assuming all 455 ha is privately owned.
(Source: JICA Study Team)
Table 9-2: Acquisition of private land from tenants and lessee
Note: Unit price (decimal) 10,000 taka (identified in land price survey)
Unit price (m2) 247 taka Unit price (ha) 2,471,054 taka
Remarks: (a) Amount for provision of another land includes 50% premium, stamp duty and land registration fees @0.15
(b) Lost income includes monthly household income for 3 years. (Source: JICA Study Team)
No of HHs Area (ha) Land value (taka)
(a) cash
compensation under
law (taka)
(b) Replacement
value of land
exccept VAT and
contingency (taka)
(c) One time assistance
for lost income (d) Total (a+b+c)
237 455.00 1,124,329,603 1,686,494,405 252,974,160.68 259,147,152 2,198,615,717
Entitled Persons
Legal owners of land
(a) Amount for
provision of
another land
(b) One time
assistance for lost
income
(c) Total (a+b)
77 155.86 385,150,000 664,383,750.00 83,300,400 747,684,150 Tenants and lessee (private land)
Compensation package (taka)
Entitled Persons No of HHs Area (ha) Land value (taka)
Section-9 Estimated Land Acquisition and Resettlement Cost
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-2
(2) Loss of government land
Table 9-3: Acquisition of government land from legal tenants and lessee
Note: Unit price (decimal) 10,000 taka (identified in land price survey)
Unit price (m2) 247 taka Unit price (ha) 2,471,054 taka
Remarks: (a) Amount for provision of another land includes 50% premium, stamp duty and land registration fees @0.15
(b) Lost income includes monthly household income for 3 years. It is assumed that tenants and lessee will seek private land.
(Source: JICA Study Team)
Table 9-4: Acquisition of government land from occupants without legal tenure
Note1: Compensation amount is based on the land value stated by the interviewees for the sake of estimation. Note2: Unit price (decimal) 10,000 taka (identified in land price survey)
Unit price (m2) 247 taka Unit price (ha) 2,471,054 taka
Remarks: (a) Amount for provision of another land includes 50% premium, stamp duty and land registration fees @0.15
(b) Lost income includes monthly household income for 3 years. Number of households include both occupants for cultivation (140 HHs) and occupants for domicile (16 HHs).
(Source: JICA Study Team)
(3) Permanent loss of means of livelihood / sources of income
Table 9-5: Assistance for transition in recovering loss of income source of land owners
Note: Compensation amount is based on the land value stated by the interviewees for the
sake of estimation. Remarks: It was not possible to identify the number of lessor who lends land to the tenants
and lessee identified in the household survey. (Source: JICA Study Team)
Table 9-6:Assistance for transition in recovering loss of income from livelihood activities
(a) Amount for
provision of
another land
(b) One time
assistance for lost
income
(c) Total (a+b)
10 1.15 2,840,000 4,899,000.00 12,155,976 17,054,976 Tenants and lessee (gov land)
Entitled Persons No of HHs Area (ha) Land value (taka)
Compensation package (taka)
(a) Amount for
provision of
another land
(b) One time
assistance for lost
income
(c) Total (a+b)
156.00 19.41 47,973,161 82,753,703.00 129,902,400 212,656,103
Entitled Persons No of HHs Area (ha) Land value (taka)
Compensation package (taka)
Occupants without legal tenure
Area (ha) Annual value (taka)Rate for
opportunity loss
Compensation package
(taka)
155.86 8,748,665 10 87,486,650.00
Entitled Persons
lessor (land owners who rent their land)
Type of loss
Income from land lease contract
Permanent 44 5,211,000 15,633,000 36,000 15,669,000
Temporary 597 1,428,800 4,286,400 36,000 4,322,400
Permanent 117 6,943,000 20,829,000 36,000 20,865,000
Temporary 256 2,844,550 8,533,650 36,000 8,569,650
Permanent 4 0 0 36,000 36,000
Temporary 22 2,400,000 7,200,000 36,000 7,236,000
Permanent 0 0 0 36,000 36,000
Temporary 17 30,800 92,400 36,000 128,400
Sharecroppers income from crop Sharecroppers 12 2,478,961 7,436,884 36,000 7,472,884
Type of laborTotal annual wage
(taka)
(a) One time
assistance for lost
income
(b) Enrollment in
vocational training
courses
Compensation package
(c) Total (a+b)
No of employed
personsEntitled Persons
Laborers
income from shrimp
cultivation
income from salt
farming
income from fishing
activities
Type of Loss
income from other
activities
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-3
Note: Compensation amount is based on the actual wages stated by the interviewees for the sake of estimation.
Remarks: (a) Lost income includes monthly household income for 3 years. (b) Vocational training is estimated @Tk.300/day for 120 days (6 months).
(Source: JICA Study Team)
Table 9-7: Assistance for transition in recovering loss of income from own business or self-employment
Note: Compensation amount is based on the actual wages stated by the interviewees for the
sake of estimation. Remarks: (a) Opportunity loss is fixed based on recent annual inflation rates in Bangladesh.
It is assumed as 10% here. (b) Lost income includes monthly household income for 3 years.
(Source: JICA Study Team)
(4) Loss of residential / commercial structure
Table 9-8:Assistance for transition in recovering loss of income from residential / commercial structure
Note1: Compensation amount is based on the house size stated by the interviewees for the
sake of estimation. Note2: 1m2 is approximately equivalent to 10.7639 sft. Remarks: (a) Amount for provision of another land includes 50% premium, stamp duty and
land registration fees @0.15 (b) Reconstruction grant will be provided to the affected households at the rate of 15 taka per square feet. (c’) Shifting allowance will be provided at the rate of 10 taka per square feet.
(Source: JICA Study Team)
(5) Loss of standing crops at home gardens, shrimp and fish
Table 9-9: Assistance for transition in recovering loss of income from livelihood means
Note: Compensation amount is based on the actual wages stated by the interviewees for the
sake of estimation. Remarks: Opportunity loss is fixed based on recent annual inflation rates in Bangladesh. It is
assumed as 10% here.
No of people
involved
Amount of capital
(taka)
Rate for
opportunity loss
Compensation for
opportunity loss
22 1,455,000 10 14,550,000
3 0 10 -
1 200,000 10 2,000,000
1 30,000 10 300,000
6 105,000 10 1,050,000
1 250,000 10 2,500,000
Unknown 2,240,000 10 22,400,000
Entitled Persons
Businessmen
Boat men
Teacher
Carpenter
Tea staller
Others (unknown)
Income from salt business
Agriculture
Boat
Teaching
Construction
Shop
Unknown
Type of Loss
Replacement of
structure value with
50 % premium
(taka)
Stamp duty and
registration fees
(taka)
Reconstruction
grant (taka)shifting allowance (taka) (c) Total (a+b)
1,130 sft
105 m2
-
-
4,712 sft
438 m2
Entitled Persons
1,058,288
House size
Compensation package (taka)
Legal title holders / owners of sttructure
Socially recognized owners /
unauthorized occupants
Legal tenants / lease holders of the
structure- - -
4 420,000 42,000 11,300 16,950
No of HHs
490,250
16 855,000 85,500 70,673 47,115
Entitled Persons No of HHs Production amount
Annual income
from productive
activities (taka)
Rate for
opportunity loss
Compensation package
(taka)
65 - 4,553,831 10 45,538,310
139 - 4,907,881 10 49,078,810
23 - 50,010 10 500,100
8 - 52,000 10 520,000
109 - 3,398,303 10 33,983,030
155 6,669,715 kg 30,506,536 10 305,065,364
income from shrimp cultivation
income from salt bed
income from fishing
Source of income from activities
income from pischiculture
income from crop
Land owners,
bargadar, lesse and
unauthorized
occupants
income from other activities
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-4
(Source: JICA Study Team)
(6) Loss of timber and fruit bearing trees
Table 9-10: Assistance for transition in recovering loss of trees
Remarks: to be recalculated.
(Source: JICA Study Team)
(7) Temporary loss of land during construction Not applicable.
(8) Temporary loss of access to land, structure, utilities, common property resource during construction
Not applicable.
(9) Temporary loss of livelihood/source of income during construction Not applicable.
Total amount required for land acquisition, resettlement, and assistance for transition in restoring livelihood means and income sources are 3.86 billion taka.
Table 9-11: Compensation for PAPs at power plant site Compensation Item Amount (taka) Remarks
1 Permanent loss of private land caused by land acquisition
2,946,299,867 Table 9-1, Table 9-2
2 Permanent loss of government land caused by land acquisition
229,711,079 Table 9-3, Table 9-4
3 Permanent loss of means of livelihood 194,621,984
Table 9-5, Table 9-6, Table 9-7
4 Permanent loss of residential / commercial structure caused by resettlement
1,548,538 Table 9-8
5 Loss of standing crops at home gardens, shrimp and fish
434,685,614 Table 9-9
6 Loss of timber and fruit bearing trees 57,178,000 Table 9-10
7 Temporary loss of land during construction
0 -
8 Temporary loss of access to land, structure, utilities, common property resource during construction
0 -
9 Temporary loss of livelihood/source of income during construction
0 -
Total 3,864,045,082 (Source: JICA Study Team)
9.2 Transmission line route It is PGCB who will allocate budget to cover the costs of temporary land acquisition and compensation for standing crops within the agreed implementation period. All the compensation will be done according to the principle of the replacement cost, and PGCB will pay the gap between CUL and the replacement value (top up). Based on the entitlement matrix for the PAPs shown in Table 4.4, the compensation package for the PAPs has been drafted as in the tables below. Values appearing in the tables, such as land, income, standing crops etc., were the figures collected from the local residents through socioeconomic survey.
Entitled Persons No of HHs No of trees in totalMarket value of
tree (taka)
Compensation
package (taka)
Owner of trees 274 28,589 2,000 57,178,000
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-5
(1) Permanent loss of private land There will be 157 towers for both angle towers and suspension towers from Anowara Upazila to Maheshkhali Upazila, which will require 1,256 m2 of land for the installation of tower bases. When PGCB acquire land involuntarily from the land owners at the tower locations, PCGB will pay for the land. It is estimated as shown in the following table:
Table 9-12: Anticipated Land Acquisition and Assistance
Entitled Persons
No of HHs
Total area for towers (m
2)
Land value* (taka)
Cash compensation under law (taka)
Replacement value of land except VAT and contingency**
Total
land owners
157 1,256
(8 m2
X 157)
932,279 1,398,419 0 1,398,419
Remarks: (a) Land value was estimated based on the current market prices of land varied from 247 m2 to 1,236 m2 from Maheshkhali Upazila to Anowara Upazila.
(b) Replacement value is estimated as zero as the landowners will not have to be shifted.
(Source: JICA Study Team)
(2) Permanent loss of government land Not applicable.
(3) Permanent loss of means of livelihood / sources of income Not applicable.
(4) Permanent loss of residential / commercial structure
(5) Permanent loss of standing crops at home gardens, shrimp and fish Not applicable.
(6) Permanent loss of timber and fruit bearing trees Not applicable.
(7) Temporary loss of land during construction The anticipated impact on the land owners will not last permanently or be critical, as the land area for tower bases are relatively small, and land owners’ livelihood activities will be hindered only during the construction period. Landowners with legal title, tenants and lease holders will receive rental assistance for the construction period for which the land is temporarily requisitioned. Temporarily requisitioned land will be returned to owners rehabilitated to original or preferably better condition.
(8) Temporary loss of access to land, structure, utilities, common property resource during construction
Landowners with legal title, tenants and leaseholders will be provided temporary access and relocation where possible. Restoration of access to the land, structure and utilities will be confirmed.
(9) Temporary loss of livelihood/source of income during construction One-time assistance for lost income based on monthly income for three years from products, minimum wage rates or based on actual income, verified through incomes of comparable businesses in the area.
Table 9-13: Compensation for PAPs at power plant site
Entitled Persons No of HHs One-time assistance for lost income*
Total
land owners 157 1,720,800 1,720,800
Remarks: Lost income includes monthly household income for 3 years. It was based on the annual crop price as of Dec 2012 (30 taka / m2).
(Source: JICA Study Team)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-6
Total amount required for land acquisition, resettlement, and assistance for transition in restoring livelihood means and income sources are 3.86 billion taka.
Table 9-14: Compensation for PAPs at power plant site
Compensation Item Amount (taka)
Remarks
1 Permanent loss of private land caused by land acquisition 1,398,4190
Table 9-12 2 Permanent loss of government land caused by land acquisition 0
3 Permanent loss of means of livelihood 0
4 Permanent loss of residential / commercial structure caused by resettlement 0
5 Loss of standing crops at home gardens, shrimp and fish 0
6 Loss of timber and fruit bearing trees 0
7 Temporary loss of land during construction 0 -
8 Temporary loss of access to land, structure, utilities, common property resource during construction
0 -
9 Temporary loss of livelihood/source of income during construction 1,720,800
Table 9-13
Total 3,119,219
(Source: JICA Study Team)
9.3 Township Area
Compensation Cost and budget for affected privately owned land (total 20 hector) has been estimated basing on unit price(ha) (Tk. 2,471,054 determined by JICA Study Team. In conformity with entitlement matrix cost of compensation and resettlement benefits for the following types of losses and resettlement benefits have been estimated i) Loss of land by legal owners ii) Income from shrimp cultivation iii) Income for salt farming iv) Loss of wages v) Loss of crop vi) Permanent loss of means of livelihood and vii) Vocational Training Cost
Table 9-15 Acquisition of private land from legal owners
Entitled Person
No of HHs
Area (ha)
Land Value (Taka)
(a) Cash Compensation Under Law (Taka)
(b) Replacement Value of Land except VAT and Contingency (Taka)
© One time assistance for lost income
(d) Total (a+b+c)
Legal Owners of land
41 20 9,421,080 74,131,620 7,413,162 36,360,000 117,904,782
Note: Unit price (decimal) 10,000 taka (identified in land price survey) Unit price (m2) 247 taka Unit price (ha) 2,471,054 taka
Remarks: (a) CUL adds 50% premium to the current market price, not the average of last 12 months' sales values of same kind of land.
(b) Replacement value covers stamp duty and land registration fees incurred for replacement of land @15% VAT and contingency will be added for the total project cost. (c) Lost income includes monthly household income for 3 years.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-7
9-16 Assistance for restoration in recovering loss of income from livelihood activities
Entitled Person
Type of loss Type of Labour
(a)No of
Employed
Persons
Total Annual Wage (Taka)
Compensation Package
(b) One time assistance for lost income
(c) Enrollment in Vocational Training Courses
(d) Total (aXc+b)
Labours Income from shrimp cultivation
Permanent 5 360000
1,080,000 36000
1,260,000
Temporary 31 1116000
3,348,000 36000
4,464,000
Income from salt farming
Permanent 7 504000
1,512,000 36000
1,764,000
Temporary 21 756000
2,268,000 36000
3,024,000
Total 10,512,000
Note: Compensation amount is based on the actual wages stated by the interviewees for estimation.
Remarks: (a) Lost income includes monthly household income for 3 years. For permanent labour full 3 years @ monthly household income Tk.6000. For temporary labour six months per year is calculated, for 3 years it comes to 18 months.
(b) Vocational training is estimated @Tk.300/day for 120 days (4 months). (Source: JICA Study Team)
(10) Loss of standing crops at home gardens, shrimp and fish
Table 9-17: Assistance for transition in recovering loss of income from livelihood means Entitled Persons
Sources of Income from activities
No of HHs Production Amount
Annual Income From Productive activities (Taka)
10% inflation (Taka)
Compensation Package (Taka)
Land owners
Income from shrimp cultivation
8 200,168 20,017 220,185
Income from salt cultivation
6 215,713 21,571 237,284
Income from crop
5 293174 Kg 1,340,945 134,095 1,475,040
Total 1,932,509
Note: Compensation amount is based on the actual wages stated by the interviewees for the sake of estimation.
Remarks: Opportunity loss is fixed based on recent annual inflation rates in Bangladesh. It is assumed as 10% here.
(Source: JICA Study Team)
(10) Permanent loss of government land Not applicable.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-8
(11) Permanent loss of residential / commercial structure (12) Not applicable.
(13) Permanent loss of timber and fruit bearing trees Not applicable.
(14) Temporary loss of land during construction Not applicable.
(15) Temporary loss of access to land, structure, utilities, common property resource during construction
Not applicable
(16) Temporary loss of livelihood/source of income during construction Not applicable
Table 9-18: Compensation for PAPs at Township Site Compensation Item Amount (taka) Remarks
1 Permanent loss of private land caused by land acquisition
117,904,782 Table 9-15
2 Permanent loss of government land caused by land acquisition
3 Permanent loss of means of livelihood 10,512,000 Table 9-16
4 Permanent loss of residential / commercial structure caused by resettlement
5 Loss of standing crops at home gardens, shrimp and fish
1,932,509 Table 9-17
6 Loss of timber and fruit bearing trees -
7 Temporary loss of land during construction
0 -
8 Temporary loss of access to land, structure, utilities, common property resource during construction
0 -
9 Temporary loss of livelihood/source of income during construction
0 -
Total 130,349,291
(Source: JICA Study Team)
9.4 Compensation and Resettlement Budget
9.4.1 Finalization and Approval of the Compensation and Resettlement Budget
Land acquisition and resettlement budget contained in the LARAP will be revised as per findings Census for inventory and assessment of losses and market survey for replacement price of land and property conducted by the Implementing Agency. The revised budget will need to be approved by the Ministry of Power, Energy and Mineral Resources along with revised LARAP. Upon approval of land acquisition by Ministry of Land, the DC will prepare estimates for compensation including service charge and produce that to CPGCBL for placement of fund within 60 days.
The LARAP implementing agency will assist PMU, CPGCBL to prepare resettlement budget. Covering all eligible loss and entitlements confirmed through joint verification and determination of replacement price of land and property by PVAT. PMU will get this budget approved by the Ministry of Power, Energy and Mineral Resources through CPGCBL will make placement of fund with resettlement account of the PMU for disbursement.
9.4.2 Management of Budget
The CPGCBL does not have any set codified rules for payment of compensation to APs for resettlement of affected persons. Under the circumstances, a detailed administrative guideline (payment modality) will be required to implement the LARAP at the field level as well as for PMU and EA. Administrative guideline (payment modality) for payment of
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
9-9
compensation and resettlement benefits. PMU, CPGCBL and Implementing Agency and other stakeholders will follow administrative guideline after its approval from the appropriate authority. A draft Administrative guideline (payment modality) is placed at Annexure-3.
The PMU, with requisition from IA for payments of compensation and resettlement assistance in all other forms will authorize Executive Engineer concerned to prepare cheques for disbursement of individual APs based on approved indent. The IA will assist the PMU for disbursement of cheques to EP following the administrative guideline (payment modality).
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
10-1
10.1 Project Stakeholders
The primary stakeholders of the project include the agriculture farmers, salt cultivators, shrimp cultivators, fisher man, and service holder, laboures, mazi, boat businessman, share croppers, carpenters local business community , squatters the AHs as well as beneficiaries of the project and host population. Other stakeholders include CPGCBL, Ministry of Power, Energy and Mineral Resources JICA as donor, policy makers, elected officials and other government agencies.
10.2 Disclosure and Public Consultation
Goals and objectives of the project is being disclosed with the affected people and other stakeholders through focus group discussion and public consultation meetings. 1. Information gathering:
a. Review of JICA guidelines on disclosure and public consultations b. Review of other Donors’ guidelines on disclosure and public consultations c. Review of available literature on disclosure and consultation method followed in
other donor funded infrastructure projects and good practice
2. Information Disclosure:
a. Dialogue with local people through public meetings b. Information and consultation meetings (ICM) in the locality c. Disclosure of the project components and other related issues among stakeholders
of all levels through conducting public meeting organized by prior notice d. Focus group discussion with local stakeholders with primary focus with the project affected people (directly or indirectly affected people irrespective of gender and social status) e. Disclosure of the Land Acquisition and Resettlement Issues among the potential affected persons 3. Consultation:
a. Consultation of resettlement and rehabilitation issues with all level stakeholders and gather feedback on potential risks and probable mitigation measures b. Encourage all level stakeholders to participate in the consultation by receiving views from representatives from different groups including directly and indirectly affected households, structure owners, agriculture land losers, owners and employees of CBEs, salt cultivators, farmers, fishermen, local traders, women and vulnerable groups etc.
10.3 Stakeholder’s Participation Process
53. Consultation and communication with APs and other stakeholders during design stage of the project is considered an integral part of the process of gathering additional data. During the preparation of LARAP, PAPs and their communities have been informed, consulted and three stakeholders meetings were held and views of primary and secondary stakeholders were documented. At time of the implementation of LARAP the PAPs and their communities will also be consulted about the project, the rights and options available to them, and the proposed mitigation measures for adverse effects, and to all extents possible they will be involved in the decision-making process concerning their resettlement. The PAPs will receive prior notification of the compensation, relocation and other assistance available to them. CPGCBL will be responsible to hold and conduct a number of consultations with primary and secondary stakeholders and information dissemination on the following issues:
Section-10 Local Consultation, Participation and Disclosure
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
___________________________________________________________________________________________________________________
10-2
- The relevant details of the project - The RP and various degrees of project impact - Details of entitlements under the RP and what is required of PAPs in order to claim their
entitlements - Compensation process and compensation rates - Relocation and resettlement site development operation in order to obtain agreement
and support of affected people in participating in these operations - Implementation schedule and timetable for the delivery of entitlements
Local participation should be spontaneously encouraged and information be made available during the preparation and implementations of the LARAP and at the minimum include community meetings and focus groups discussions. Information dissemination can be done not only for the project affected people but non-affected people out of the project site for sharing proper knowledge on the project with broader channels. Where a host community is affected by the development of resettlement sites in that community, the host community shall be involved in any resettlement planning and decision-making. All attempts shall be made to minimize adverse impacts of resettlement upon host communities. As planned 3rd public Consultation meeting was held on 1st October, 2013 in Materbari, Union Parishad Hall Room. Details are described in Section 3.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
11-1
Section-11 Implementation Schedule
LARAP Implementation Schedule
A time bound implementation schedule for the LARAP is prepared synchronized with project construction schedule. The overall schedule of implementation is based on the principle that resettlement benefits are paid to AHs before they are displaced. The implementation of each LARAP will include –
I. Identification of cut -off date and notification, II. Verification of losses and extent of impacts,
III. Finalization of entitlements and distribution of ID cards, IV. Consultations with PAPs on their needs and priorities and, V. Resettlement, provision of compensation and assistance and income
restoration of PAPs.
The LARAP will be finalized after submission of land acquisition plan and approval of budgets by EA. The IA will be appointed during detailed design phase for updating and implementation of LARAP. This will shorten time for tendering and other processing of award of IA. Implementation of LARAP will commence before starting of the construction works and will continue up to four years time. A tentative RP implementation schedule is placed below:
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
11-2
Note: EP implies eligible person. (Source: JICA Study Team)
Figure 11-1 Tentative Schedule for Land Acquisition and Resettlement
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Project Appraisal 3 wks in Dec2013
Conclusion of Loan Agreement Mar end 2014
Consultant Selection Consultant selection
Basic Design Basic Design
Pre-qualification of EPC Contractor PQ of EPC Contractor
Selection of EPC contractor (Civil Works) Selection of EPC Contractor (Lot 1&2)
Construction (Access Roads)
Construction (Port Facilities and Power Plant)
Finalization of EIA
Submission of draft EIA by JICA Team
Preparation of an application and submission of EIA to DOE
Approval of EIA from DOE
Finalization of land acquisition and resettlement action plan
Submission of draft Land Acquisition and Resettlement Action Plan (LARAP) by JICA Team
Preparation/Submission of application for land acquisition to MOPEMR and make a request to DC of Cox's Bazar
Appraisal by DC Appraisal by DC within 90 days
Approval of land acquisition by the GOB Appraisal by GOB within 90 days
Preparation/Submission of Resettlement Action Plan (RAP) to MOPEMR
Budget application for Additional Grant (AG) on top of DC's payment for land, and Resettlement Benefits (RBs)
Budget approval for AG and RB by the GOB
Data collection and EP identification
Deployment of officers in charge of land acquisition & resettlement
Survey design (in line with DC)
Conduct socioeconomic survey and collect data (in line with DC)
Data analysis and report processing
Preparation of ID card, EP file, and Entitlement Cards
Collection of award data, assigning ID numbers, phorographing of EPs, issuance/distribution of ID cards
Local consultation and information management
Preparation of information brochure
Distribute information brochure
Local consultations (ex. public consultation meetings, focus group discussion, etc.)
Finalizagtion of budget
Formation of Property Valuation Advisory Committee (PVAC)
Valuation of assets value
Finalization of resettlement budget
Implementation of land acquisition and resettlement
Cash Compensation under Law (CCL) for the affected lands, structures crops and trees to the EPs (by DC)
Payment of AG on top of DC's payment for the lands and other RBs to the EPs by CPGCBL
Assist EPs in replacement land purchase/relocation
Assist EPs with implementation of the livelihood rehabilitation / improvement program
Handing over the acquired land by CPGCBL to Contractor
Formation of Grievance Redress Committee (GRC)
Receiving grievance from stakeholders
Monitoring
Internal Monitoring
External Monitoring
20162013 2014 2015Procedure
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-1
Section-12 Monitoring and Evaluation
12.1 Monitoring and Evaluation Monitoring and follow up provides periodic checks to ascertain whether resettlement activities are working as planned. The project management will need this feedback to be able to ensure the planned activities to be on the right track. Monitoring provides both working system for the project management and channel for the resettlers to make aware of their needs and reaction to the way the resettlement being carried out. Evaluation on the other hand, is an exercise usually undertaken towards the end of the projects to assess whether the plan achieved its goals and objectives.
The EA, through the PMU, will establish a monitoring system involving the Project Supervision Consultant (PSC) and the LARAP Implementing Agency for collection, analysis, reporting and use of information about the progress of resettlement, based on the LARAP. These stakeholders will be made responsible to monitor the progress of all aspects of land acquisition/ resettlement and income generation. The EA will report to the JICA on land acquisition, resettlement and income generation by APs in the quarterly reports, including identification of significant issues. Besides, an annual report stipulating all efforts and outcome will be sought by the JICA from the CPGCBL.
12.2 Internal Monitoring Internal monitoring will be undertaken by the PMU through Executive Engineer concerned with assistance from the IA. The IA will gather information on LARAP implementation covering relevant activities as per schedule. All activities listed will be illustrated in Gantt Charts showing the target dates for completing resettlement activities. Internal monitoring reports on LARAP implementation will be included in the quarterly Project Progress Report (PPR). It will be then submitted to JICA. The report of PMU will contain: (i) accomplishment to-date, (ii) objectives attained and not attained during the period, (iii) challenges encountered, and (iv) targets for the next quarter. The EA will make bi-annual reporting to JICA on monitoring. However, the NRS will monitor the activities of IA and report to PD on a monthly basis. Table11-1 below shows the potential monitoring indicators that will be followed for reporting.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-2
Table 12-1: Potential Monitoring Indicators Monitoring Issues Monitoring Indicators
1. Budget and Timeframe
• Have all resettlement staff been appointed and mobilized for field and office work on schedule?
• Have capacity building and training activities been completed on schedule?
• Are resettlement implementation activities being done as per agreed implementation plan?
• Are funds for resettlement being allocated to resettlement agencies on time?
• Have resettlement offices received the allocated funds?
• Have funds been disbursed according to Entitlement Matrix of LARAP.
• Has all the land made encumbrance free and handed over to the contractor in time for project implementation?
2. Delivery of DP Entitlements
• Have all DPs received entitlements according to quantity and categories of loss set out in the entitlement matrix?
• How many affected households have land titles?
• How many affected households are relocated and built their new structures at new location?
• Are income and livelihood restoration program activities being implemented as planned?
• Have affected businesses received entitled benefits?
• Have the APs losing their eroded land received proper compensation?
• Have the squatters, encroachers been displaced due to the project, been compensated?
• Have the community structures been compensated and rebuilt at new site?
3. Consultation, Grievances and Special Issues
• Have resettlement information brochures/leaflets been prepared and distributed?
• Have consultations taken place as scheduled including meetings, groups, community activities?
• Have any DP used the grievance redress procedures?
• What grievances were raised
• What were the outcomes?
• Have grievances and resolutions been documented?
• Have any cases been taken to court?
• Have conflicts been resolved?
4. Benefit Monitoring • What changes have occurred in patterns of occupation compared to the pre-project situation?
• What changes have occurred in income and expenditure patterns compared to pre-project situation?
• Have APs income kept pace with these changes?
• What changes have occurred for vulnerable groups?
12.3 Implementation Mechanism of Land Acquisition and Resettlement For overall Implementation Management and Monitoring of land acquisition and resettlement and civil work etc. the diagram is appended below: (figure )
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-3
Figure 12-1 Implementation Mechanism of Land Acquisition and Resettlement
12.4 External Monitoring & Evaluation Appropriate reporting (including auditing and redress functions), monitoring and evaluation mechanisms, will be identified and set in place as part of the resettlement management system. The EA will recruit an Independent External Monitor (IEM) acceptable to JICA for monitoring the performance of LARAP implementation and evaluation of resettlement process and final outcome. A sample TOR for Independent External Monitor is placed at Annexure-4. Besides that IEM will also monitor and evaluate environmental impacts as per environmental plan.
An Environmental Monitoring Plan will be prepared to provide guidelines for the construction activities of the power plant. The environmental components to be monitored are those that will be positively or negatively affected, or expected to be affected, by the construction activities. The purposes of creating an Environmental Monitoring Plan for the construction of the power plant are to: - Confirm that mitigation measures shall reduce any negative impacts on the environment
to allowable levels during the construction and operation phases. - Set up an organization that is responsible for the implementation of monitoring the plan. - Perform appropriate monitoring during the construction and operation phases.
Budget
allocation for
top-up
Contractors
Cox's Bazar District
Project Office at Site
Project Affected People
Project Director
Deputy
Commissioner
Upazila Nirbahi
Officer (UNO)
Project Engineer
Ministry of Power,
Energy and Mineral
Resources
Internal monitors
Request for
budget allocation
Coordination
and meeting Hand over the acquired land
Monitoring
Government of
Bangladesh
CPGCBL
Resettlement
Officer
External monitors
Request for
budget allocation
Budget
allocation for
top-up
Budget allocation for CUL
Consultation
Payment of CUL
Payment of top-up
Provide assistance Submit grievances
Project Office at Site
Project Director
Project Engineer
Internal monitors
Monitoring
PGCB
External monitors
Chittagong District
Deputy
Commissioner
Upazila Nirbahi
Officer (UNO)
Coordination and meeting
Request for budget allocation
Budget allocation
Consultation
Payment of CUL
Pa
ym
en
t o
f to
p-u
pP
rov
ide
ass
ista
nce S
ub
mit
gri
ev
an
ces
Contractors
Hand over the acquired
land
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-4
Table 12-2: Contents of environmental management plan and monitoring plan
Item Impact Targeted Range Contents of Environmental Management Plan
Contents of Monitoring Plan
Resettlement - Land Acquisition and Resettlement
- Around the power plant site
-Preparation of LARAP (livelihood restoration plan)
- Monitoring the progress of land acquisition and resettlement - Monitoring the conditions of local residents’ employment - Grievances from residents
Disturbance to Poor People
- Land Acquisition and Resettlement
- Around the power plant site
- Preparation of LARAP (livelihood restoration plan)
- Monitoring the livelihood conditions of the targeted households - Grievances from residents
Deterioration of Local Economy such as Losses of Employment and Means of Livelihood
- Loss or damage to the salt/shrimp cultivation ponds by land acquisition
- Around the power plant site
- Preparation of LARAP (livelihood restoration plan)
- Monitoring the livelihood conditions of the households engaged in salt cultivation/ shrimp aquaculture - Grievances from residents
Land Use and Utilization of Local Resources
- Change of land use - Around the power plant site
- Employment of local residents - Procurement of materials from the local area
- Grievances from residents
Disturbance to Existing Social Infrastructure and Services
- Change of land use - Around the power plant site
- Construction of roads that can be used by local residents - Permit usage of certain facilities in the power plant to local residents
- Grievance from residents
- Increase of traffic during construction phase
- Around the power plant site
- Reschedule construction schedule
- Grievances from residents
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-5
Item Impact Targeted Range Contents of Environmental Management Plan
Contents of Monitoring Plan
Misdistribution of Benefits and Damages
- Loss or damages to the salt/shrimp cultivation ponds by land acquisition
- Around the power plant site
- Preparation of livelihood restoration plan to the targeted households, in case the households engaged in salt/shrimp cultivation are included in the relocated households
- Monitoring the livelihood conditions of the targeted households - Grievances from residents
Local Conflicts of Interest - Loss or damages to the salt/shrimp cultivation ponds by land acquisition
- Around the power plant site
- Preparation of livelihood restoration plan to the targeted households, in case the households engaged in salt/shrimp cultivation are included in the relocated households
- Monitoring the livelihood conditions of the targeted households - Grievances from residents
Gender
- Change of land use - Around the power plant site
- Construction of roads that can be used by local residents - Permit usage of certain facilities in the power plant to local residents
- Grievances from residents
Children’s Rights
- Change of land use - Around the power plant site
- Construction of roads that can be used by local residents - Permit usage of certain facilities in the power plant to local residents
- Grievances from residents
(Source: JICA Study Team)
The following tables shows the performance monitoring form for land acquisition, resettlement and assistance for transition of the project affected people, impact monitoring during implementation and post-project stage.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-6
Table 12-3:Monitoring Form 1(for Performance Monitoring of Resettlement Action Plan)
Procedure Indicator (specific step/action)
Unit
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr
4th qtr
1st qtr
2nd qtr
3rd qtr
4th qtr
Staffing and Management
Recruitment, training and deployment of staff / expert in charge
1. Deployment of (an) officer(s) / expert(s) in charge of land acquisition
Man-months
2. Deployment of resettlement officer(s) / expert(s)
Man-months
3. Training and mobilization of officers-in-charge (if required)
No. of trained personnel
Supervision and Management
1. Supply of manpower and logistics
No. of persons
2. Liaison with other agencies (ex. DC Office, Upazila Nirbahi Office, Union Parishads etc.)
No. of meetings
3. Administrative management
Month
Finalization of land acquisition and resettlement action plan
Finalization of land acquisition
1. Preparation of an application for land acquisition
%
2. Submission of application to MOPEMR and make a request to the Deputy Commissioner of Cox’s Bazar
Date of submission
3. Approval of land acquisition by the GOB
Date of approval
Adoption of the Resettlement Action Plan
1. Review of the draft Resettlement Action Plan (RAP)
%
2. Submission of application to MOPEMR and make a request to the Deputy Commissioner of Cox’s
Date of submission
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-7
Procedure Indicator (specific step/action)
Unit
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr
4th qtr
1st qtr
2nd qtr
3rd qtr
4th qtr
Bazar District for implementation of RAP in line with land acquisition
3. Approval of RAP Date of approval
Identification of eligible persons
Socioeconomic Survey (in liaison with DC office)
1. Survey design Time
2. Field Survey and collection of data
%
3. Computerization of field data
%
4. Data analysis and report processing
%
5. Preparation of ID card, EP file, and Entitlement Cards
%
Identification of Eligible Persons (in liaison with DC office)
1. Collection of award data No. of EPs
2. Assigning ID numbers No. of EPs
3. Photographing of EPs No. of EPs
4. Issuance of ID cards No. of EPs
5. Distribution of ID cards No. of EPs
Local consultation and information management
Information Management (in liaison with DC office)
1. Preparation of information brochure
%
2. Distribute information brochure
No. distributed
3. Personal contacts No. contacted
4. Local consultations (ex. public consultation meetings, focus group discussions (FGD) s, etc.)
No of consultations
Budgeting
Valuation of affected property (in liaison with DC office)
1. Formation of Property Valuation Advisory Committee (PVAC)
%
2. Planning for valuation %
3. Communication and collection of data
%
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-8
Procedure Indicator (specific step/action)
Unit
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr
4th qtr
1st qtr
2nd qtr
3rd qtr
4th qtr
4. Valuation %
5. Finalization of resettlement budget
%
Implementation of land acquisition and resettlement
Payment of compensation for land acquisition (in liaison with DC office)
1 Motivate Eligible Persons (EP)
No. of EPs
2 Assist EPs to collect Cash Compensation under Law (CCL)
No. of EPs
3 Organize top-up payment to fill the gap between CUL and RV
No. of EPs
Relocation of Project Affected Persons (in liaison with DC office)
1. Motivate Eligible Persons (EP)
No. of EPs
2. Payment of Transfer Grant
No. of EPs
3 Assist EPs in replacement land purchase/Relocation
No. of cases
Resettlement of Project Affected Persons (in liaison with DC office)
1. Assist EPs to collect Cash Compensation under Law (CCL)
No. of EPs
2. Organize top-up payment to fill the gap between CUL and RV
No. of EPs
3. Assist vulnerable EPs in resettlement
No. of EPs
Assistance in transition (in liaison with DC office)
1. Motivate EPs to join the livelihood rehabilitation / improvement program
No of EPs
2. Literacy class No of class
No of attendance
3. Skill trainings No o trainings offered
No of trained personnel
4. Job opportunities at power No of posts
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-9
Procedure Indicator (specific step/action)
Unit
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr
4th qtr
1st qtr
2nd qtr
3rd qtr
4th qtr
station and associated facilities
offered to EPs
No of employed EPs
Grievance Redress (in liaison with DC office)
1. Formation of Grievance Redress Committee (GRC)
No. of members
2. Publicizing/notifying of GRC
%
3. Receiving grievance from stakeholders
No. of cases
4. Resolving grievances No. of cases (%)
5. Other claim/criticism No. of cases
Report processing
Performance Reporting
1. Inception report Date of submission
2. Monthly progress report Date of submission
3. Draft final report Date of submission
4. Final report Date of submission
Table 12-4: Monitoring Form 2 (for Impact Monitoring during Project Implementation)
Indicator Unit (Standard value)
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr 4th qtr 1st qtr 2nd qtr
3rd qtr 4th qtr
Grievance redress mechanism
Grievance submitted by the stakeholders
Number of cases
Grievance resolved No. of cases (%)
Conflict with host community No. of cases
Other claim/criticism No. of cases
Land acquisition and compensation
Households losing their own No of HHs
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-10
Indicator Unit (Standard value)
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr 4th qtr 1st qtr 2nd qtr
3rd qtr 4th qtr
land (%)
Households losing their domicile on their own land
No of HHs (%)
Households losing their renting land (private land)
No of HHs (%)
Households losing their renting land (government land)
No of HHs (%)
Households losing their occupancy on khas land
No of HHs (%)
Households losing their illegal domicile on government land
No of HHs (%)
Households losing income from own land
No of HHs (%)
Households losing income from own livelihood activities
No of HHs (%)
Households losing income from own business
No of HHs (%)
Households losing income from standing crops
No of HHs (%)
Compensation completed No. of cases (%)
Relocation and compensation
Relocated households No of HHs (%)
Relocated households owning land
No of HHs (%)
Relocated households owning domicile
No of HHs (%)
Relocated households renting land
No of HHs (%)
Relocated households renting domicile
No of HHs (%)
Compensation completed No. of cases (%)
Household economy
Project affected household that lacks the source of income
No of HHs (%)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-11
Indicator Unit (Standard value)
Year 1 Year 2
Comments 1st qtr
2nd qtr
3rd qtr 4th qtr 1st qtr 2nd qtr
3rd qtr 4th qtr
Project affected household with reduced monthly income
No of HHs (%)
Livelihood restoration
Literacy class Number (%)
Job training conducted No. of courses
PAPs (age over 16) that received job training
Number (%)
Compensated/relocated structure for business (e.g. shop, garage, etc)
Number (%)
Allocation of substitute farmland Area (%)
Substitute farmland being utilized
Area (%)
Employment of project affected people (age over 16) by the project
No. of PAPs (%)
Employment of female PAPs (age over 16) by the project
No. of PAPs (%)
Child labour No. of children
Provision of personal protective equipment (PPE)
PAPs provided with PPE (100%)
Labour accident No. of cases
Area infrastructure development
Water and sanitation facility Number (%)
Electricity distribution Number of HHs (%)
Clinics or health facilities Number (%)
Primary schools Number (%)
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-12
Table 12-5: Monitoring Form 3 (for Impact Monitoring at Post-project Stage)
Category Source of information
Baseline data (at the commencement of Year 1)
Actual
Comments Month 24
Month 48
Month 72
Month 96
Month XX
End-line data
Social
Registers crimes/disputes (per 1,000 pop.) Statistics obtained at local police
Crimes/disputes involving women (per 1,000 pop.) do
Crimes/disputes involving vulnerable group (per 1,000 pop.)
do
Primary school attendance (male)
Statistics obtained at local education department
Primary school attendance (female) do
Number of community-based organizations Upazila Office
Household Economy
Average land holding per household (hectares) Household survey
Percentage households owning land do
Percentage households owning domicile do
Percentage households renting land do
Percentage households renting domicile do
Agricultural production: Rice do
Fish catch (ton per household/per annum) do
Shrimp catch (ton per household/per annum) do
Salt cultivation (ton per household/per annum) do
Employment: Number of male wage earners do
Employment: Number of female wage earners do
Average household income (Taka per annum) do
Average household expenditure (Taka per annum) do
Energy Consumption: Fuel wood (tons per annum) do
Energy Consumption: Kerosene (tons per annum) do
Energy Consumption: Electricity (kWh per annum) do
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-13
Health
Water source Household survey
Incidence of diarrhea do
Incidence of upper respiratory infection do
HIV infection do
Other epidemics do
Others
Traffic accidents in resettlement site do
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12-14
12.5 Post Evaluation by JICA Review Missions, JICA will undertake a comprehensive mid-term review of the LARAP
implementation. A post-evaluation of LARAP activities will be carried out by JICA to assess
the resettlement impact in terms of adequacy and deficiency in planning and R&R
operations.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
1
Annexure-1
List of anticipated affected Land owning households based on Socio-economic Survey of Designated Township Area
SES No.
Name of Household
Father's Name
Village Union Age Sex Religion Educational Qualification
Occupation Total Family Member
Monthly Income (BDT)
Affected Land (Decimal)
Monthly Expenditure (BDT)
Category of Loss
1 Nurul Abshar L/. Nur Mohammad
South Mohirgona
Dhalghata 45 Male Muslim Degree Business 1 70000 61.5 50000 Land owner
2 Dosta Mohammad
L/. Shale Ahmed
South Mohirgona
Dhalghata 70 Male Muslim SSC Business 2 60000 61.5 50000 Land owner
3 Abu Syed L/. Kajol Mia North Mohirgona
Dhalghata 53 Male Muslim Illiterate Salt Cultivator
6 12000 18 10000 Land owner
4 Upazilla,Un0 South Mohirgona
Dhalghata 45 Male Muslim Master Degree
Service 1 0 300 0 Land owner
5 Abdul Kalam Tajlok Mia North Mohirgona
Dhalghata 46 Male Muslim Illiterate Agriculture 8 30000 18 30000 Land owner
6 Kabir Hossain L/. Kajol Mia North Mohirgona
Dhalghata 55 Male Muslim Illiterate Salt Busin 7 25000 18 20000 Land owner
7 Jaker Hossain
L/. Kajol Mia North Mohirgona
Dhalghata 42 Male Muslim Illiterate Salt Cultivator
5 15000 18 15000 Land owner
8 Ali Hossain L/. Kajol Mia South Mohirgona
Dhalghata 32 Male Muslim SSC Service 1 50000 18 20000 Land owner
9 Md. Osman L/. Kajol Mia South Mohirgona
Dhalghata 46 Male Muslim Master Degree
Salt Busin 5 18000 18 18000 Land owner
10 Amir Hossain L/. Kajol Mia North Mohirgona
Dhalghata 40 Male Muslim Illiterate Salt Cultivator
5 10000 19 8000 Land owner
11 Jafor Alam L/. Ejlas Mia North Mohirgona
Dhalghata 45 Male Muslim Illiterate Business 5 20000 9 20000 Land owner
12 Jahir Alam L/. Ejlas Mia North Mohirgona
Dhalghata 37 Male Muslim SSC Service 6 12000 9 12000 Land owner
13 Saber Alam L/. Ejlas Mia North Mohirgona
Dhalghata 40 Male Muslim Illiterate Agriculture 3 8000 9 8000 Land owner
14 Abdul Mannan
L/. Ejlas Mia North Mohirgona
Dhalghata 30 Male Muslim Signature Salt Cultivator
4 10000 9 9000 Land owner
15 Md. Hossain L/. Ejlas Mia North Mohirgona
Dhalghata 65 Male Muslim Illiterate Household 11 20000 9 10000 Land owner
16 Safiul Alam Hazi Abul Hossain
North Mohirgona
Dhalghata 55 Male Muslim Illiterate Cultivator 13 60000 50 50000 Land owner
17 Hazi Nur Kader
L/. Ali Mia Nasir Moha. Dail
Dhalghata 60 Male Muslim Illiterate Salt Business
6 40000 80 30000 Land owner
18 Syed Ahamad L/. Hazi Abdul Mia
North Mohirgona
Dhalghata 65 Male Muslim HSC Salt Business
3 30000 8 27000 Land owner
19 Mir Kashem L/. Mokhlesur Rahman
Nasir Moha. Dail
Dhalghata 42 Male Muslim Signature Salt Business
6 30000 80 30000 Land owner
20 Jamal Uddin L/. Hazi Abdul Mia
North Mohirgona
Dhalghata 76 Male Muslim Illiterate Salt Business
5 33000 20 25000 Land owner
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
2
SES No.
Name of Household
Father's Name
Village Union Age Sex Religion Educational Qualification
Occupation Total Family Member
Monthly Income (BDT)
Affected Land (Decimal)
Monthly Expenditure (BDT)
Category of Loss
21 Badsha Alam L/. Kala Mia North Mohirgona
Dhalghata 55 Male Muslim Illiterate Business 7 35000 20 35000 Land owner
22 Barkot Ullah L/. Kajal Mia North Mohirgona
Dhalghata 57 Male Muslim Signature Agriculture 3 10000 20 8000 Land owner
23 Kabir Ahmed L/. Elaha Dad
Nasir Moha. Dail
Dhalghata 55 Male Muslim Illiterate Salt Cultivator
4 15000 15 15000 Land owner
24 Emdad Mia Gong
L/ Abdul Ali Matarbari Matabari 45 Male Muslim SSC Cultivator 8 22000 77 20000 Land owner
25 Yakub Ali Gong
Abdul Motlab
Matarbari Matabari 40 Male Muslim Illiterate Salt Cultivator
7 25000 647 20000 Land owner
26 Mohammad Ibrahim Gong
Hari Mia Matarbari Matabari 36 Male Muslim Degree Service 5 45000 386 30000 Land owner
27 Ismail Gong Parman Ali Matarbari Matabari 47 Male Muslim HSC Salt Business
5 20000 247 18000 Land owner
28 Abul Kalam Gong
Dhola Mia Matarbari Matabari 48 Male Muslim SSC Salt Cultivator
4 12000 339 10000 Land owner
29 Sadar Ali Abdul Hakim
Matarbari Matabari 49 Male Muslim Five Cultivator 5 25000 9 20000 Land owner
30 Sayful Khabir Abdur Rahsid
Matarbari Matabari 50 Male Muslim Nine Salt Business
6 13000 220 12000 Land owner
31 Omar Ali Alhaj Bashrat Ali
Matarbari Matabari 37 Male Muslim Illiterate Agriculture 3 10000 43 8000 Land owner
32 Akbar Ahmed Safi Ullah Matarbari Matabari 39 Male Muslim Five Salt Cultivator
4 12000 15 10000 Land owner
33 Asad Ali Ear Mohammad
Shaplapur Matabari 65 Male Muslim Nine Shrimp Cultivator
4 45000 600 35000 Land owner
34 Haji Mofij Ullah
Haji Naju Miah
Matarbari Matabari 60 Male Muslim Illiterate Cultivator 6 35000 89 30000 Land owner
35 Karim Baksu Ayin Uddin Matarbari Matabari 56 Male Muslim SSC Cultivator 6 30000 158 25000 Land owner
36 Ekram Ullah L/. Kala Mia Matarbari Matabari 48 Male Muslim SSC Business 6 15000 40 12000 Land owner
37 Badiuzzaman Haji Hakim Ali
Matarbari Matabari 47 Male Muslim Illiterate Agriculture 4 15000 300 15000 Land owner
38 Yousuf Hossain
Najir Mia Matarbari Matabari 52 Male Muslim Five Business 6 35000 130 30000 Land owner
39 Rahela Khatun
L/. Ejlas Mia Matarbari Dhalghata 45 Femal Muslim Illiterate Household 3 10000 9 10000 Land owner
40 Sanabor Khatun
H/. Mofjal Mia
Matarbari Matabari 55 Femal Muslim Five Household 4 15000 18 12000 Land owner
41 Jainat Khatun H/. Kasim Ali
Matarbari Matabari 50 Femal Muslim Nine Household 4 13000 9 12000 Land owner
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
6
Annexure-3
Coal Power Generation Company of Bangladesh Ltd. (CPGCBL) Administrative Guidelines For Payments Of Compensation & Resettlement Benefits
(AGPCRB)
1. Identification of Eligible Persons For Compensation & Resettlement Benefits.
A. Through the operation of LA ordinance, 1982 and its subsequent amendments D.C.
makes acquisition of land for public purposes as required by the Requiring Body (RB) for
implementation of the project. Under the law, the Legal owners of land affected by the
acquisition will be identified by D.C and will be eligible to compensation for (i) land
permanently acquired (including standing crops, trees, houses) and (ii) any other impact and
damages caused by such acquisition. DC, under section 7 of the L.A. ordinance makes an
award to the person entitled to compensation who is indentified as an awardee.
B. The joint verification survey (JVS) of affected land, trees, and other properties conducted
by joint verification Team in consultation with Census & SES data of APs will identify entitled
persons without legal title and assess the quantity of losses for both titled and non-titled
affected persons. The implementing Agency will prepare an ID Card for each EP with
photograph as identified during the joint verification survey. ID Cards to all EPs will be issued
with due verification from Union Parisad Chairman/Member.
2. Assessment of the replacement Cost of affected properties
A Property Valuation Advisory Team (PVAT) formed by the Ministry of Power, Energy and
Mineral Resource by a gazette notification will review the assessment of the market prices of
the affected carried out by Implementing Agency and determine the replacement cost of
those properties affected by the project.
3. Entitled person's (EP) files and Entitled card (EC)
The implementing Agency will establish menu-driven MIS at its central office for record
keeping of APs and ID numbers of the entitled persons. IA will collect and computerize data
on individual losses and compensation thereof as determined by DC and JVT of the title
holders and socially recognized non-titled EPs. The IA will prepare Entitled persons (EP)
files based on quantity of losses assessed by JVT and Entitlement Cards (EC) for each EP
based on loss type using replacement value determined by PVAT. The EC will contain
quantity of losses by type and replacement value of loss of properties and other resettlement
benefits as per Entitlement Matrix.
4. Preparation of Compensation and Resettlement Benefits by IA.
The IA based on both JVT & PVAT data regarding quantity of losses, replacement value of
loss of properties and other resettlement benefits prescribed by entitlement policy and
estimation of deferential between Compensation Under Law (CUL) and replacement value of
affected land, properties, structures, trees will prepare budget for payment of compensation
and resettlement benefits and add 2.5% contingency to the estimated budget to meet up
statistical uncertainties, valuation and GRC cases. Then the IA will place the estimated
budget to the PMU for verification and scrutiny. After the estimated budget is verified and
scrutinized will be placed to the EA for onward transmission to the Administrative Ministry for
approval within 30 days from the date of submission of budget by IA.
5. Approval of Resettlement Budget
On receipt of the resettlement budget from the EA, the administrative Ministry (Ministry of
Power, Energy and Mineral Resource) will give approval to the budget within 15 working
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
7
days. If there is any queries or need for clarification the ministry will send it back to the EA
with specific observation or note for clarification within 7 days. In that case EA will send back
the estimated budget with explanation and clarification to meet the queries to the Ministry.
And the ministry will accord their approval to the estimated budget within 7 working days.
6. Payment by project authority
6A. Placement of budgetary fund for resettlement
Upon approval of resettlement budget Administrative Ministry will forthwith place budgetary
fund to CPGCBL for disbursement to the PMU as per their budgetary allocation of fund.
6B. Preparation of Documents and Process of Payment
Based on EP file & EC IA will prepare indents by installments for payment of compensation
and resettlement benefits to the EPs and submit the indents to the PMU along with EP files
& EC authenticated by Team Leader & MIS specialist. Accordingly PMU will approve the
indent after thorough scrutiny and authorize the Executive Engineer concerned of PMU to
prepare cheques for individual EPs based on indent/ demand note of PMU.
The IA will prepare payment debit vouchers in quadruplicate, one for XEN concerned, one
for PMU records, one for IA and one for the CPGCBL.
The Sub-divisional Engineer authorized by PD will make payment by disbursing account
payee cheques to the EPs in a public place or Union Parisad office in presence of UP
Chairman/Member with prior notice to the EPs concerned. The debit vouchers will be signed
by Sub-divisional Engineer designated by PD.
While receiving the cheque EPs will show their ID Card to the CPGCBL officials and UP
Chairman/Member who will identify the individual EP. Sub-divisional Engineer will submit
monthly report on progress of disbursement of compensation and resettlement benefits to
the PMU.
7. Payment by Deputy Commissioner
7A. Placement of Fund to DC for Payment of Compensation Under Law (CUL)
Following the process of acquisition, DC will make an award to the person interested for
payment of compensation and send the estimate of the award of compensation to the
Requiring Body (RB) under section 7 of the Acquisition and Requisition of Immoveable
Property Ordinance 1982 and its amendments. As stipulated in this section 7 of the
Ordinance the Executing Agency herein referred as a Requiring Body will place fund against
estimated budget for compensation to the Deputy Commissioner directly within 60 days from
the date of sending the request for placement of fund to EA by DC.
7B. Payment of Compensation Under Law By DC
The compensation payment under Law (L.A Ordinance) will be paid to entitled persons by
the office of the Deputy Commissioner following the existing government rules and
procedures.
8. Audit and Verification of Financial Documents
Bill/Vouchers and documents relating to payment of compensation & resettlement benefits
shall be subject to half yearly audit and verification by the auditor of EA. And Audit report
should be submitted to the C.E.O of the EA with a copy to P.D.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
8
Annexure-4 TOR for Independent External Monitor
Chittagong Area Coal Fired Power Plant Development Project Land Acquisition and Resettlement Action Plan Independent Monitoring of Resettlement Activities
Terms of Reference
1. Project Description
1. The proposed Chittagong Area Coal Fired Power Plant Development Project is an initiative to cope with a rapid increase in power demand in Bangladesh and supply power in a stable manner through the construction of a coal-fired power plant (2 x 600MW) in Chittagong Division in the southeast of Bangladesh.
2. To achieve the above objectives, the project components will be as follows: - construction of a coal-fired power plant (2 x 600MW) with ultra super critical technology
(Cox’s Bazar District) - construction of an excavated port including a fuel berth and a fuel transportation facility
to the power plant (Cox’s Bazar District) - construction of an access road (Cox’s Bazar District) - extension of a 400kV transmission line between Matarbari and Anowara (Cox’s Bazar
District and Chittagong District) - Construction of Township at Matarbari and Dhalghata union of Maheshkhali Upazila in
Cox's Bazar District.
3. Power plant and Port facility The proposed coal-fired power plant (CPCG Matarbari Coal-Fired Power Plant, 2 x 600MW) is located in Matarbari Union and Dhalghata Union in Maheshkhali Upazila in Cox’s Bazar District, Chittagong Division .
4. Transmission line The power plant will be connected to the substation facility in Anowara power plant, which will be constructed in the south of Chittagong, with a 400kV transmission line of approximately 60km. The transmission line will take a route along the local road . As land for construction of the transmission towers are subject to compensation, the final route will be determined so as to avoid any residential areas, taking into account the firmness of the land foundation.
5. Access Road The location and route of access road is in the area from the national highway running between Chittagong and Cox’s Bazar to the power plant site. Basically, existing road facilities will be utilized wherever possible. It is envisioned that the route segments to join the national highway in the north and the route from Maheshkhali Island to the power plant site will involve new road and bridge construction.
6. Township The proposed Township for building residential quarters and other facilities for staff is located at Matarbari and Dhalghata Union in Maheskhali Upazila, Cox's Bazar District, Chittagong Division.
B. Objective
7. The Land Actuation and Resettlement Action Plan (LARAP) is prepared for large scale land acquisition and to address involuntary resettlement impacts with a time bound action plan and appropriate budget provisions that would be incorporated as an integral part of project design. The LARAP is based on the principle of the JICA Guidelines for Environmental and Social
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
9
Considerations that development projects must serve the needs of the society and ensure that PAPs are not made worse off by the proposed intervention. It aims to clarifying resettlement principles, organizational arrangements, and design criteria to be applied to the Project. It also addresses and fills the gap between the existing legislations of Bangladesh and the JICA Guidelines. In response to the above principle, involuntary resettlement should be an important consideration in project identification. Three important elements of involuntary resettlement are: 1) compensation for loss of assets, loss of income sources and livelihood means; 2) assistance for relocation including provision of relocation sites with appropriate facilities and services, and; 3) assistance for rehabilitation to achieve at least the same level of well-being. As warranted by policy requirement of JICA for involuntary resettlement the extent of losses has been identified and depending on estimation of losses LARAP is prepared. The LARAP will be translated into Bengali Language and disclosed for the reference of PAPs as well as other interested groups. 8. The Coal Power Generation Company of Bangladesh Ltd (CPGCBL) will implement the LARAP of Chittagong Area Coal Fired Power Plant Development Project engaging an experienced non-governmental implementing agency (IA) for the Project. The LARAP implementation will be over period of 4 years. The IA will implement the LARAP as per the resettlement policy, ensure stakeholders participation as per the Project need, and provide technical assistance for compensating the APs as per LARAP policy and packages.
9. The project supervision consultant through its national resettlement specialists will supervise and monitor the resettlement activities for the Project. CPGCBL is intending to engage an independent external monitor to ensure complete and objective information on monitoring and evaluation of the resettlement interventions.
II. Objectives of Independent Monitoring and Evaluation
10. In order to implement the LARAP properly, independent monitoring by third party of the executing agency, the supervision consultant and the implementing agency, preferably by an external monitoring consultant has been considered effective. Through independent monitoring, the executing agency can help ensure LARAP implementation activity efficient. It will be possible to identify bottlenecks and amend/improve the LARAP implementation procedure or payment modality through executive order, if found necessary. The major objectives of engaging the independent monitor are to:
• Assess the overall approach of resettlement activities along the alignment of the project
• Verify results of internal monitoring;
• Assess whether resettlement objectives have been met; specifically, whether livelihoods and living standards have been restored or enhanced;
• Assess resettlement efficiency, effectiveness, impact and sustainability drawing lessons as a guide to future resettlement policy making and planning; and
• Ascertain whether the resettlement entitlements were appropriate in meeting the objectives, and whether the objectives were suited to AP conditions.
III. Scope of Work - Specific Tasks
11. The independent monitoring consultant will set up a set of baseline indicators reviewing available data and or collecting primary data for monitoring and evaluation, building upon the Projects' own record keeping system. It may also include maps, charts, photographs of affected property, copies of contracts and land titles, payments, and valuation documents relating to resettlement. Specific tasks of the monitor are to
• Establish system of internal monitoring to assess progress in meeting key targets in the Resettlement Plan: budget and time frame, delivery of AP entitlements, consultation, grievance and special issues and benefits.
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
10
• Conduct regular reviews, based on internal monitoring and evaluation reports, involving key stakeholders including AP representatives. Reach consensus on actions required to improve resettlement performance and implement them.
• Establish a system for external monitoring and evaluation to assess achievement and suitability of resettlement objectives.
• Establish monitoring and evaluation reporting methods and reporting requirements.
• Involve APs, hosts, IA and community in Project monitoring and evaluation using appropriate methods.
• Include an ex-post evaluation of resettlement to be conducted by the independent monitor after completion of the Project.
• Review lessons learned for resettlement policy making and planning.
12. In specific to the Project the independent monitor should perform the following activities
• Monitor the authenticity of the data and the approach for generation of those.
• Review justification for changes in LARAP policy and budget.
• Verify progress and achievement of implementing agency and devise formats for estimating various indicators responsible for achievement of progress.
IV. Monitoring indicators and Information Needed
13. The information needed for independent monitoring are as follows:
A. Basic information on AP households
• Location
• Composition and structure, ages, educational and skill levels
• Gender of household head
• Access to health, education, utilities and other social services
• Housing type
• Land and other resource owning and using patterns
• Occupations and employment patterns
• Income sources and levels
• Agricultural production data
• Participation in neighbourhood or community groups
• Value of all assets forming entitlements and resettlement entitlements
B. Restoration of living standards
• Cost of compensation and entitlements
• Adoption of housing options developed
• Restoration of perceptions of "community"
• Replacement of key social and cultural elements C. Restoration of livelihoods
• Cost of compensation and entitlements
• Degree of sufficiency of the compensation and entitlements
• Availability of replacement land
• Degree of sufficiency of transfer and relocation grants to cover the costs incurred
• Degree of sufficiency of income substitution allowances
• Degree of sufficiency of assistance for re-establishment of business enterprises
• Degree of sufficiency of assistance for re-establishment of CPRs
• Income earning opportunities provided to the vulnerable APs and their adequacy
• Degree of sufficiency of the jobs provided to the APs to restore pre-Project income level
D. Levels of AP satisfaction
• Level of the knowledge about resettlement procedures and the entitlements
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
11
• Knowledge base on fulfillment of these provisions
• AP assessment on restoration of living standards and livelihoods
• Knowledge on GRC mechanism and conflict resolution procedure
E. Effectiveness of Resettlement Planning
• Assistance provided to land speculators
• Sufficiency of time and budget to meet objectives of the LARAP
• Degree of generosity of the entitlements
• Identification of vulnerable groups
• Dealing with unforeseen problems by LARAP implementers
Other Impacts
Unintended environmental impacts Unintended impacts on employment or incomes
V. Approach and Methodology
(i) General Approach
14. Appropriate methods will be followed to collect field level information in order to review and compare the socioeconomic condition of APs "before" and "after" resettlement program. Collected information on the key indicators of resettlement progress, efficiency, effectiveness, impact and sustainability will be analyzed. The monitoring and evaluation consultant will also conduct at least one ex-post evaluation Surveys to assess the achievement of resettlement objectives, the changes in living standards and livelihoods and the restoration of the economic and social base of the APs. (ii) Detailed Methodology
15. The independent monitor will use existing baseline census and Survey data with their periodic updates. In specific the independent monitor perform its activity in the following methods:
• Review pre-Project baseline data on income and expenditure, occupational and livelihood patterns, leadership, community organizations and cultural parameters.
• Identify an appropriate set of indicators for gathering and analyzing information on resettlement/rehabilitation impacts; the indicators shall include but not limited to issues like relocation of affected people, delivery of entitlement, and level of satisfaction by the beneficiaries of the programs.
• Review result of internal monitoring and verify claims through random checking at the field level to assess whether resettlement/ rehabilitation objectives have been generally met. Involve the APs and community groups in assessing the impact of resettlement programs for monitoring and evaluation purposes.
• Conduct both individuals and community level impact analysis through the use of formal and informal Surveys, key informant interviewers, focus group discussions, community public meetings, and in-depth case studies of APs/women from the various social classes to assess the impact of LARAP implementation.
(iii) Methodology for Participatory Rapid Appraisal
16. The affected and host people should be involved in the monitoring and evaluation process to solve day-to-day problems arising during resettlement operations. APs, local CBOs, and/or local NGOs should be involved in the process. The key players should be involved in the evaluation design and implementation. Participatory Rapid Appraisal (PRA) techniques should be undertaken to foster the involvement of APs and other key stakeholders in resettlement monitoring and implementation. The methodology of the PRA should be as follows:
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
12
• Key informant interviews: select local leaders, community workers or persons with special knowledge or experience about resettlement activities and implementation.
• Focus group discussion: specific topics (e.g. land compensation payments, services at resettlement sites, income restoration, and gender issues)
• Field observations on status of resettlement implementation, plus individual or groups interviews for cross-checking purposes.
• Informal Surveys/interviews: informal Surveys of APs, hosts, community workers, resettlement staff, and implementing agency personnel using non-sampled methods.
VI. Required Resources 17. The tasks require a consultant experienced in the field of resettlement planning, implementation and monitoring. The consultant should have sufficient technical and professional skill in dealing with involuntary resettlement as per JICA guidelines. Criteria for selection of Consultant
18. The Consultant must be able to present appropriate evidence to verify his/her satisfactory performance in resettlement planning, implementation, monitoring and evaluation and preparation of analytical/evaluation reports meeting the standards of the external financiers.
VII. Staffing for the Tasks 19. The consultant must be able to present evidence of his/her skill and sufficiently qualified, experienced and trained manpower to mobilize to the field to collect data according to the requirements. In order to carry out the tasks stipulated in this Terms of Reference, the field level input should be limited as shown in Table 1 below. The consultant should show the duration of their services and limit as per requirement in consultation with the civil works contact. However, the mobilization is based on field requirement only.
Table 1: Staffing for Independent Monitoring
Position Nos. Unit Estimated no. of man months
Resettlement Monitor 1 16
Data Collector/Data Processor 4 60
Total 5 76
X. Stakeholders and their Responsibility
a. Responsibility of Executing Agency
20. Responsibility of the Executing agency will be as follows- i. CPGCBL through its Project Management Unit (PMU) and the Resettlement Unit (RU) will ensure timely supply of background references, data to the independent monitor. It will ensure uninterrupted access to work sites, relevant offices of the GOB and CPGCBL in particular. The independent monitor will sit in quarterly coordination meetings with the CPGCBL in presence of the PSC and CPGCBL should organize that at PMU or RU level as appropriate. ii. Recommendation based on the result of the monitoring should be offered to CPGCBL to cover up the deficiencies identified by the independent monitor. The CPGCBL will accept the recommendations of the independent monitor if it is within the scope of work and there is nothing incorrect in the report.
b. Responsibility of Project Supervision Consultant 21. The project supervision consultant (PSC) will provide appropriate protocol at site or at its Project Office for the mission of the independent monitor. It will, on behalf of the EA, ensure free access to work sites, impact areas and the database on resettlement and civil
Matarbari 2x600 MW Coal Fired Power Plant Project Matarbari, Cox's Bazar
13
works. The PSC will ensure timely intimation of its civil works planning as and when made or updated during the construction period and Keep the Independent Monitor informed.
c. Responsibility of LARAP Implementing Agency (IA) 22. The LARAP Implementing Agency will assist and cooperate with the independent monitor through providing free access to its database and the automated management information system (MIS). It will provide copies of the progress reports and other reports as requested by the independent monitor. The IA may have to carry out surveys as well for fulfillment of the requirements of the independent monitoring.
d. Japan International Cooperation Agency (JICA) 23. The Japan International Cooperation Agency (JICA) will review the activities of the independent monitor in light of the social safeguard strategy and the involuntary resettlement guideline of JICA. JICA will ensure timely response from the EA on queries and recommendations from the independent monitor.
XI. Time Frame 24. The independent monitor will be employed from starting of the project and runs down to the end of project intermittent inputs of total 16 months over the project period.
XII. Reporting Requirement 25. Half yearly monitoring report should be submitted to the CPGCBL and simultaneously to the JBIC. An evaluation report at the end of the Project should be submitted to the CPGCBL and concerned parties with critical analysis of the achievement of the program and performance of the EA and IA. The independent monitor will report to CPGCBL and JICA based on some agreed upon formats developed in consultation with the CPGCBL.
XIII. Budget and Logistics
26. The budget will includes all expenses such as staff salary, training, computer/software, transport, field expenses and other logistics necessary for resettlement monitoring. The budget contains a workshop to be conducted together with the project supervision consultant to disseminate and discuss the Project experience of implementation of resettlement action plan of the project. Additional expense claims whatsoever outside the proposed and negotiated budget will not be entertained. VAT, Income Tax and other charges admissible will be deducted at source as per GOB rule.