Karnataka Industrial Areas Development BoardNo.49,4* & 5* Floors, Khanija Bhavan, Race Course Road, Bangalore - 560 001
No.IADB/ JD(T&P) / 608 / 2016-77Dt. 12-4-2416
CIRCULAR
Sub: Fixation of time limit for allotment of land,building construction permit and providing
water supply connection to the plots allotted in
KIADB Industrial Areas.
-oOo-
The Government of India has implemented Business Reforms Action
Plan 2016 under Ease of Doing Business in order to perform public works
within the stipulated time limit.
The Karnataka Industrial Areas Development Board (KIADB) is
acquiring lands throughout the State for development of industrial areas
and allotting land to the entrepreneurs after providing all the
infrastru cture faciiitie s.
KIADB is approving Development plan / Building plan submitted by
the Entrepreneurs for construction of building in tJle aLlotted plots. KIADB
is issuing Commencement Certificate & Occupancy Certificate and also
arranging water supply to the unit.
The above activities will have to be completed within the stipulated
time from the date of receiving applications till issue of approval letters/
Certificates to the allottees/ entrepreneurs.
: : 2 : :
The time limit stipulated for each activity is as detailed below:
sl.No
Details Time limit
1 . Allotment of Plot
a. Initial Deposit along with theapplication (3Oo/o / 2Qo/' / LA% ofthe Land Cost)
30 days from the dateof communication.
b . 7Oo ,80% & 9Oo/o of land cost Within 90/ 1s0/ 180days from the date ofallotment letter.
c . Obtaining Possession Certificate One month from thedate of issue ofconfirmatory letter ofallotment
d Execution of Lease cum saleagreement /Lease deed
One month from thedate of PossessionCertificate.
e . Approval for Development PlanlBuilding Plan.
Six months from thedate of execution ofLease cnm saleagreement /Leasedeed .
f. Completion of construction ofbuilding, installation ofmachinery and commencementof production
36160 months fromthe date of PossessionCertificate
: : 3 : :
2 . Construction of Building
From the date of friing application
{*ith al1 relevant documents/NoObiection Certificates)a. Approval of Development planl
Building plan.45 days
b , Issue of Commencementcertificate
30 days
Issue of Occupancy certificate 3O days
? Water Supply conneetion
From the date of application (with a-11relevant documents/No ObjectionCertificates)
45 days
All the Development Officers are directed to strictiy adhere to the
stipulated time limit for the above activities. Any lapses in performing t}-e
above duties will be viewed seriously and disciplinary action will be
initiated against erred officers.
sd/-Chief Executive Officerand Executive Member
To1. Chief Development Officer & Chief Engineer, KiADB, Bengaluru.
2. Joint Director (T. & C. P), KIADB, Bengaluru.
3. All Development Officers and Executive Engineers, KIADB Zonal
Offices.4. Technical Assistant-l & II, KIADB, Bangalore
5. All Deputy Development Officers & Assistant Executive Engineers,
KIADB, ZonaT offices.
6. All Assistant Secretaries, KIADB, Head office and Zonal. offices.
: : 4 : :Copy to:
1. The Additional Chief Secretary to Govt., Commerce and IndustriesDepartment, Vikasa Soudha, Bengaluru : for kind information.
2. Trle Commissioner for iD, Industries and Commerce Dept., KhanijaBhavan, Bengaluru : for kind information.
Time Line / Schedule for Approval of Development plan/ Building plan:
Events Time Scheduled A. Submission of the Application by the
Applicant in the Zonal Office, KIADB.
I. The proposal with an extent of plot.
For Development plan approval: <5acres (Non Residential/Industrial),
<3acres (Residential)
Building Plan approval: Height of building<G+3 or 15m.
i. Scrutiny of Documents & NOC’s by the
Assistant Engineer.
ii. Inspection Letter to Applicant for
Inspection of site.
iii. Site Inspection by the DO along with
DDO & AE.
iv. Uploading of Site Inspection report.
v. Verification of drawing/plans by AE
and forwarding with opinion to DDO.
vi. Verification by DDO and forwarding
with recommendation for Approval to
DO.
vii. Approval by DO.
5 Working Days
2 Working Days
7 Working Days
2 Working Days 5 Working Days 5 Working Days
3-4 Working Days
II. The proposal with an extent of plot.
For Development plan approval: >5acres (Non Residential/Industrial), >3acres (Residential)
For Building Plan approval: Height of building> G+3 or 15m.
i. Scrutiny of Documents & NOC’s by the
Assistant Engineer.
ii. Inspection Letter to Applicant for
Inspection of site.
iii. Site Inspection by the DO along with DDO & AE.
iv. Uploading of Site Inspection report.
v. Verification of drawing/plans by AE and
forwarding with opinion to DDO.
vi. Verification by DDO and forwarding with
opinion to DO.
vii. Verification by DO and sends to Head
Office (CDO&CE) with recommendation along with site inspection report,
Documents/NOC’s for approval.
viii. Scrutiny by Caseworker and sends with
opinion to JD(T&P)
ix. JD(T&P) Verifies and sends with
recommendation for approval to CDO&CE
x. CDO&CE Accords in principle approval and sends back for further process to DO
section.
xi. Accords approval by DO.
3 Working Days 7 Working Days
2 Working Days 2 Working Days 4 Working Days 4 Working Days 5 Working Days 3 Working Days 4 Working Days
7 Working Days 4 Working Days
Note:
Sl No.
Details
Total Time Limit for approval
Building Plan/Development Plan
1. The proposal with an extent of plot.
For Development plan: <5acres (Non-Residential/Industrial),
<3acres (Residential)
For Building Plan approval: Height of building <G+3 or 15m.
30 Days
2. The proposal with an extent of plot.
For Development plan: >5acres (Non-Residential/Industrial),
>3acres (Residential)
For Building Plan approval: Height of building >G+3 or 15m.
45 Days