Intergraph South East Asia User Conference – Sanctuary Cove 2010 Intergraph South East Asia User Conference – Sanctuary Cove 2010

SmartPlant Construction 2015 R1 Released April 2015

Jason Dubose – Executive Consultant - Construction May 2015

April 2015

Retrieve Dialog

2

Features – Dialog has been improved to allow a user to search by name, status, number

of documents and the type of document. – Dialog is not auto-populated on load. User must initiate a search. – Previous search is auto-populated when dialog is opened again.

April 2015

Partially Retrieved Document

3

Features – If a document is cancelled and is only partially retrieved, the status of the

document will be ‘Partial’. – Information column will tell the user all functionality will not be available, even

though the document can be opened in SPC.

April 2015

Print Markups in Reports

4

Features – Markups will be printed with Model/Drawing

snapshots that are part of the package summary report.

– NOTE: They will only be printed in black and white.

April 2015

Assembly details in viewers

5

Features – User will now be able to see assemblies related to a

component on the right click menu in viewers. – Selecting the assembly from the list will open a

dialog with all the components listed that are part of the assembly.

– User can then navigate to other drawings or view the properties of individual components.

April 2015

ROP Config: Specify a List for Text Properties

The capability to specify a list of properties for string lookup values was added. For example, to supply a list of values for ~SPC_ComponentItem_Thickness, the format

should be: – {Property value | Property value}

The list can only be applied to one lookup value per row. Multiple values must be separated by the pipe ( | ) character, and be contained within braces({}); these values are treated as an OR value. For example, {XS | XXS} would match all lookup values with a thickness of XS or XXS.

6

April 2015

Queuing Components for Rules of Progress by Rate Table

SmartPlant Construction can now queue all components affected by a particular rate table in the Rules of Progress spreadsheet on demand.

7

April 2015

Filter Category Search

8

Features – Users can now search for filters in categories that

might have 1000’s of filters. – Search criteria is kept between user sessions and is

independent of model/drawing in configurations. – Allows users to quickly find items they are looking for

instead of scrolling through all items.

April 2015

Schedule Import, mappings spreadsheet

Schedule Import—mappings spreadsheet determines how P6 data is imported into SmartPlant Construction (SPC). OOTB implementation—mirrors current functionality of Refresh schedule, i.e., moves WBS data from P6 into SPC

as Construction Work Packages (CWPs). Simple mapping—map P6 Entity/Attribute name to SPC Interface/property.

P6 UDF mapping—map P6 Entity/User-defined Field name to SPC Interface/property w/ special syntax.

Argument mapping—uses functions from (overridable) external service named ProjectDataMappingsService to

calculate values:

Documentation—see SPC documentation for detailed information on how to use delivered service or how to override

the functionality w/ your own

9

April 2015

Export Schedule, Partial Progress (Work Package level)

Man hours recorded in SPC (including partially progressed components) exported/imported as Labor Units in P6.

Export crew as resource checkbox must be checked. When checked :

– Planned/Completed/Actual Man Hours exported – Exported Man Hours used to calculate all Labor Units in P6:

Planned Budgeted Actual Actual Planned – Complete Remaining Actual + Remaining At Complete

– Labor Units split evenly amongst resources assigned to P6 Activity (work package) – Labor Units/Crew Size determine the duration of the P6 Activity (work package) during Schedule

10

April 2015

Import project data – Primavera Schedule

11

• Import Primavera P6 WBS items as CWPs (Construction Work Package). • Change management features let you see new/existing/updated items to select only the

items you require for processing. • Data mapping (may be customized) gives you ultimate control over how P6 data is

imported into SPC. • Future enhancements to expand the types of data that may be imported.

April 2015

Import project data – Project Configuration

12

• Replaces/updates Import Project Configuration command. • Excel spreadsheet as input maintains consistent and familiar workflow. • Change management features let you see new/existing/updated items to select only the

items you require for processing. • Intelligently manages required relationships between selected items to ensure data

remains consistent and reliable.

April 2015

Maximum Query Limit

13

SmartPlant Construction now has supports the ‘Maximum Query Limit’ property for a user in the viewers for the Quick Find and Volume Selection dialogs. User will be notified with a message that they have encountered the limit.

April 2015

Save Advanced Search Queries

14

Features – Users can now save advanced queries for different

browsers – Admins can share saved queries for all users to

utilize.

April 2015

Actual Man Hours Display on Schedule Screen

Actual Man Hours is now displayed on the Schedule Screen

15

April 2015

Actual Man Hours Editable on Component Screen

The Actual Man Hours for a work package is now displayed on the Component Screen. For tracking actual hours at the package level, this value can be edited by clicking the lock button beside the value.

16

April 2015

Material project forecast

17

Advanced queries

3 OOTB color definitions

SmartPlant Construction now has the ability to use color definitions and advanced search queries in the Material Project Forecast environment. Three color definitions are delivered out of the box.

April 2015

Forecast/ reservation based on the purpose of the FIWP

18

SmartPlant Construction now has the ability to forecast and reserve material item from SP Material based on the purpose of the work package. The Rule of progress defines which step for which purpose is consuming the material item.

April 2015

2D / 3D material filters

19

3 new filters

SmartPlant Construction now has the ability to filter material item based on their status. Three new material filters are delivered out of the box.

April 2015

Export Filters

20

Features – Export filter to an Excel based file – Available in 2D and 3D Viewers – Configure properties to export via SPF column set – Access group controlled on who can export data