PRESENTATION
AFOHS DETT. MALIR
Prepared & Presented by: M. Sohail Azeem
SEQUENCE
• INTRODUCTION
• RECOMMENDATION FOR COST CURTAILMENT
• RECOMMENDATION FOR IMPROVEMENT
• CONCLUSION
SDH
• TOTAL AREA 350 SQ. YARDS
• TOTAL COVERED AREA 3000 SFT.
• RATE PER SDH Rs.12,20,000.00
I H
• TOTAL AREA 500 SQ. YARDS
• TOTAL COVERED AREA 4000 SFT.
• RATE PER I H Rs.15,50,000.00/=
COST CURTAILMENT
• 01 X RCC PIPE LINE OF 6” DIAMETER MAY BE DELETED
• TOTAL PIPE IN USE 32 METER
• RATE Rs.130.00 PER METER
• TOTAL COST Rs.4,160.00
• TOTAL SAVING Rs.2,080.00
RCC PIPE
• IF WE DELETE ONE RCC PIPELINE, 05 X MAIN HOLES AND 05 X C.I.COVER WOULD ALSO BE DELETED.
• COST OF 01XMAIN HOLE Rs.1500.00• COST OF 01XC.I.COVER Rs.500.00• TOTAL SAVING Rs.10,000.00
MAIN HOLES / C.I. COVER
• SEPTIC TANK MAY BE DELETED FROM THE DESIGN
• COST Rs.10,000
SEPTIC TANK
• STEEL RAILING OF BACK SIDE TERRACE MAY BE DELETED
• WALL OF 3’-6’’ MAY BE RAISED INSTEAD
• TOTAL RAILING IN USE 25 RFT
• RATE Rs 400/= RFT
• TOTAL COST Rs 10,000/=
• BLOCK MASONARY Rs.2000/=C.M TOTAL COST(1.5 CUM) RS.3000/=
• DIFFERENCE OF COST RS.7000/=
STEEL RAILING
• BACK SIDE WALL OF FRONT TERRACE HAS A PIPE RAILING
• MAY BE REPLACED WITH BLOCK MASONARY
• RATE OF RAILING RS.500/- RFT
• COST ( 5 RFT) RS.2500/-
• BLOCK MASONARY Rs.670/-• COST SAVING RS.1830/-
PIPE RAILING
• CLAD STONE MAY BE REPLACED WITH GRAFFIATTO
• RATE OF CLAD STONE RS.30/-SFT
• RATE OF GRAFFIATTO RS.12/- SFT
• TOTAL AREA 500 SFT• COST OF CLAD STONE RS.15000/-
• COST OF GRAFFIATTO RS.6000/-
• COST SAVING RS.9000/=
CLAD STONE
• M S SHEET/ G I OF 16 GAUGE MAY BE REPLACED WITH 18 GAUGE DOOR FRAMES
• RATE OF 16 GAUGE Rs.75/=RFT• RATE OF 18 GAUGE Rs.65/=RFT• TOTAL USAGE 300 RFT• COST OF 16 GAUGE Rs. 22500/= • COST OF 18 GAUGE Rs 19500/=• COST SAVING Rs 3000/=
M.S. SHEET / G.I.
• DEODAR WOOD IS USED FOR BIDDING/GOLAS • MAY BE REPLACED WITH PERTAL/GOLDEN
TEAK• RATE OF DEODAR WOOD RS.2500/- CFT
• RATE OF PERTAL RS.700/- CFT
• TOTAL REQUIREMENT 17 CFT
• COST OF DEODAR RS.42000/-
• COST OF PERTAL RS.12000/-
• COST SAVING RS.30,000/-
WOODEN BIDDING
. WOODEN STAIR RAILING MAY BE REPLACED WITH ALLUMINIUM RAILING
• RATE OF WOOD RS.45O/-RFT
• RATE OF ALLUMINIUM RS.250/-RFT
• TOTAL REQUIREMENT 30 RFT
• COST OF WOOD RS.13500/-
• COST OF ALLUMINIUM RS.7500/-
• COST SAVING RS.6000/-
STAIR RAILING
• 4’’ DIA UPVC PIPES MAY BE REPLACED WITH 3’’
• RATE OF 4’’ DIA PIPE RS.145/-R.M.
• RATE OF 3’’ DIA PIPE RS.100/-R.M.
• TOTAL CONSUMPTION 36 R.M.
• COST OF 4’’ DIA PIPE RS.5220/-
• COST OF 3’’ DIA PIPE RS.3600/-
• COST SAVING RS.1620/-
UPVC PIPE
• TOTAL OF 06xUPVC PIPES ARE LAID FROM THE ROOF MAY BE DELETED
• 3’’ DIA UPVC PIPES OF THE TWO BATH ROOMS ON THE FIRST FLOOR MAY BE EXTENDED UPTO ROOF AND AN ELBOW MAY BE FIXED FOR THE RAIN WATER
• COST SAVING RS.4400/-
UPVC PIPE(RAIN WATER)
• CAR PORCH ROOF OF SDH MAY BE INCREASED IN HEIGHT UPTO DRAWING ROOM SLAB
• WOODEN STAIR RAILING MAY BE REPLACED WITH ALLUMINIUM
• GRAFFIATTO OF DIFFERENT SHADES MAY BE USED FOR FRONT ELEVATION IN CASE STONE CLADDING IS DELETED
• SEPTIC TANK IN SDH MAY BE SHIFTED OUT SIDE THE BOUNDARY WALL (IF IT IS NOT DELETED)
RECOMMENDATIONS FOR IMPROVEMENT
CONCLUSION
• THE RECOMMENDATIONS MADE IF INCORPORATED WILL SAVE APPROX. Rs 85000/= PER HOUSE