Post on 05-Jan-2016
WCCUSD Bond Program
Construction UpdateHarding Elementary School
Exterior Repairs & Select Roofing Replacement11/18/2014
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement Site Plan
General Contractor Best Contracting Services, Inc.
Architect of Record Grossman Design Group
Construction Manager Willie Robinson
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement
Project Team
Contract Amount $918,600
Notice of Award 06/17/14
Notice to Proceed 07/21/14
Completion 01/05/15
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement
Fabricating & installing Surround Window flashings is 95%
complete. Re-setting of Windows at Building A is 90% compete. Stucco (scratch & brown coats) at Building A-1 upper
parapet walls & west wall of Theatre is complete. Installation of waterproof membrane and lathing at Building
A-1 is 75% complete. Clean-up, repair and environmental testing of water
intrusion areas.
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement
Project Status
Building A-1: South wall at storefront.
Building A-1: Theatre West Wall – Stucco brown coasting.
Building A: 1st floor windows re-installed.
Building A-1: Stucco brown coat at upper parapet wall.
Library Past Water Intrusion Damage _2 10/28/14.
Computer Lab Hygienist Clean –Up 10/04/14
Library Water Intrusion Repairs_3 11/06/14
Building A-1: Theatre West Wall, stucco brown coat.