CRADLE OPERATIONS
MUHAMMAD REHA N KHAN
MAINTENA NCE ENG INEER
HOISTING
AUTHORIZATION FORM
AUTHORIZATION
PRE-HOIST MEETING
BACKGROUND
Q & A
PRE-HOISTING
BACKGROUND
Requirement:• Close supervision• Thorough Inspection and testing
Responsibility:• Inspection• Mechanical Maintenance Engineers
BACKGROUND
According to the Department of Energy (U.S.), OSHA and ASME:
“The use of a crane or derrick to hoist employees on a personnel platform is PROHIBITED, except when the erection, use, and dismantling by conventional means of reaching the worksite, such as a personnel hoist, ladder, stairway, aerial lift, elevating work platform or scaffold, would be more hazardous, or is not possible because of structural design or worksite conditions.”
Requirement:• Close supervision• Thorough Inspection and testing
Responsibility:• Inspection• Mechanical Maintenance Engineers
AUTHORIZATION
Requirement:• Authorized by Department Manager• 100% Procedural Compliance
Responsibility:• Area Engineers/ Supervisors
Access through Permanent Platform
Access through Scaffolding
Access through Ladder
Access through Cradle
PRE-HOISTING
1• Ensure Crane is inspected along with load test• Check Daily inspection checklist
2• Crane for hoisting should not have free fall facility• If it has then it should be blocked & confirmed
3
• Cradle should be designed and inspected by qualified personnel
• Cradle should have its inspection tag with validity date
4• Verify the dimensions of the Cradle with the standard
given in procedure
5• Personnel should be physically & mentally fit for
hoisting
PRE-HOISTING
6• Conduct meeting with team especially Crane Operator, Lead
Rigger and Area Supervisor & review procedure with team
7
• Conduct a trial dummy lift immediately before performing actual lift
• Trial lift should be done every time when crane is positioned
8• Crane Operator and Rigger shall ensure all controls and no
hindrance in Cradle operation
9• Check level of Crane and condition of outriggers while trial lift• Lifted load should not exceed 50% of the crane rated capacity
10
• Safety harness is must to hook with Crane hook• Lead men should be responsible for overall operations and
safety
PRE-HOIST MEETING
Mandatory participants: Crane operator, riggers and personnel to be hoisted
Following points need to be discussed:
Access clearance upto job location & height. Area barrication to be decided. Riggers / Caution man deployment Dummy Run of crane Inspection of Wire slings, shackles, ropes, cradle
and harnesses Approval of Authorization form Successful communication to area owner.
HOISTING
1 •Continuous sight with verbal communication•Walkie-Talkie to be kept in Cradle•Assign additional riggers if required
2 •Crane Operator will remain at its seat throughout the Cradle Operation
3 •Cradle should not be used in winds near 15 MPH (25 KM/H)
4 •Person should keep his body parts inside cradle•Person should not stand on the rails
HOISTING
5 •No travelling of crane while Cradle in operations
6 •No other Crane should be operated in vicinity when Cradle is in operations
7 •Cradle lift is not to exceed 100 ft. height otherwise JSA should be done separately
8 •Up till a height of 30 ft. one tag rope should be used•For more height, two tag ropes should be used
HOISTING
9 •Within battery limits, person should carry Full Face Mask in Cradle
10 •Crane smooth and slow operation should be ensured while lifting•Fire extinguisher shall be carried if jobs involve fire hazard
11 •In case cradle has to be tied to a platform, care should be taken to tie the knot swiftly
12 •In case of emergency, Operations should be stopped smoothly and lower the cradle with no hurry
AUTHORIZATION FORM
I have reviewed the work site and find no alternative means of reaching it (such as scaffold and ladder etc.) Therefore Mr. ____________________ Maintenance Engineer / Supervisor is authorized to hoist personnel through Crane to carry out __________________ repair job using procedure * Daily checklist for Cranes has been filled by Crane Operator, duly verified by the Area Engineer using the crane hoisting purposes. * Capacity of cradle: _________Tons * Estimated weight of cradle: __________Tons * Crane load lifting capacity at the required boom angle: _________Tons * Number of persons in fit condition to be lifted: _____________
* Free- fall device is deactivated or not present INITIATED BY: ____________________________ REVIEWED BY:____________________________ ENGINEER SECTION HEAD APPROVED BY: ___________________________ MANAGER Authorization shall be maintained by the Engineer as record in the history sheet
Q & A