Crabtree, Rohrbaugh & Associates, Architects
Montoursville Area School District
High School Project UpdateFebruary 10, 2015
AGENDA
• ACE Grant
• Exterior Elevation Concepts
• Weight Room / Board Room Options
• District Administration Options
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Department of Community and Economic Developmentand
Department of Environmental Protection
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Benefits:
• ACE Grant
$2,000,000
• Additional PDE Reimbursement $ 373,000
• Lower Energy Costs annual
$2,373,000
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Required:
• LEED Gold - High Performance Bldg.
Alternative and Clean Energy Program (ACE)
CRA obtained $2 million grant for each:
Lewisburg School District
State College School District
South Middleton School District
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Cost: for LEED Gold
• Energy Efficient Components $ 750,000• Enhanced Commissioning $ 50,000• General Construction $ 50,000• Design / Application Fees $ 132,000
$ 982,000
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Net Benefit:
• Total Benefits $ 2,373,000
• Cost for LEED Gold less $ 982,000• Scope beyond budget (1%) less $ 384,000 Includes Basic EPDM roofing
$ 1,007,000
Montoursville Area School District
MEPReplace all Roof-top units
ArchitecturalMoveable CaseworkUnforseen floor conditions in Aux Gym / Weight Room area
CivilD zone surfacing of trackAdditional Paving Scoreboard electrical Stadium EntranceFencing
Scope beyond original Budget includes :
1 2Montoursville Montoursville
TREMCO TREMCORoofing Single Ply Built-Up
Add to Base Cost 349,623$ 733,558$
Montoursville Area School District
2Net Benefit : $ 1,007,000Tremco TPO Single Ply $ 350,000
$ 657,000
3Net Benefit : $ 1,007,000Tremco Built-Up Roof $ 734,000
$ 273,000
Current DesignWeight Room and No DAO Board Room
Alternate 1 Add $200,000DAO Board Room with Weight Room Addition
Alternate 2 No Cost ChangeSmaller Weight Room and Smaller DAO Board Room
1st Floor Plan
1st Floor Plan
1st Floor PlanExist. Maintenance, Tech. Ed. Bldg, & Field house
Main Entrance
Classroom Wing
District Administration Entrance 1
Bird’s eye District Administration 1
District Administration Entrance 2
Bird’s eye District Administration 2
District Administration Entrance 3
Bird’s eye District Administration 3