Construction Manager / General Contractor CM/GC ... Manager / General Contractor CM/GC Procurement...

Post on 12-Mar-2018

237 views 2 download

Transcript of Construction Manager / General Contractor CM/GC ... Manager / General Contractor CM/GC Procurement...

1

Construction Manager / General ContractorCM/GC Procurement Case Study

February 2016

Federal Transit AdministrationWendy A. Lee, Regional Counsel, Cambridge, MA

WORLD TRADE CENTER PATH TERMINAL PROJECT

MBTA GREEN LINE EXTENSION PROJECT

2

Observations and Lesson Learned

The use of non-traditional contracting methods for major FTA-funded construction projects is on the rise.

• The CM/GC approach is the most innovative but difficult to manage

• Selection of the right Joint Venture, Design, and other consulting teams is critical

• Early involvement of in-house legal counsel

• Requires experienced owner to manage competing interests; significant and continuous involvement of owner

• Need to be willing to terminate agreement if Guaranteed Maximum Price (GMP) not established within the contractual time frame and execute contingency plan

Green Line Extension (GLX)Light Rail Project

• MBTA

• Extend existing light rail service 4.3 miles

• Executed Full Funding Grant Agreement in January 2015

Project Budget - $2.297B

Required Completion Date –June 29, 2022

• Utilized CM/GC procurement strategy

Engaged White Skanska Kiewit, J.V. in August 2014

3

Project Background

World Trade Center (WTC) PATH Terminal Project

• Port Authority of NY & NJ

• Rebuild former WTC PATH Terminal

• Executed Construction Agreement in May 2006

Project Budget - $2.501B

Required Completion Date -April 30, 2012

• Utilized CM/GC procurement strategy

Engage Phoenix Constructors J.V. in January 2006 (Fluor, Skanska, Bovis, Granite)

4

WTC PATH Terminal ProjectJustification for CM / GC Approach

A single CM/GC approach would:

• Fast-track project delivery that could save between 10-31 months

• Yield cost of between $95-$243 million

• Produce higher quality work

• Provide a single point of responsibility and control of construction activities

• Establish a guaranteed maximum price (GMP) prior to completion of final design

5

WTC PATH Terminal ProjectKnown Challenges and Risks

Highly challenging conditions include:• Aggressive Schedule

• Complex Construction Coordination with 16-acres site

• Scope and Quality of Construction

VSC

1 LineSubway

6

WTA PATH Terminal ProjectWTC Site

Tower 4

Tower 3Tower 2

FreedomTower

Memorial

Route 9A

Chiller Plant

DeutscheBank

PAC Dey StConnector

Oculus

WTC PATH Terminal ProjectStakeholders

7

In September 2008, the PA and CM/GC mutually agreed to terminate the contract

• Design process was delayed due to several factors:

Complexity of the site

Interdependence of each redevelopment project on others

Conflicting and changing demands of multiple stakeholders

Conscious effort by PA to re-examine certain aspects of design to reign in costs and accelerate schedule

• Failure to negotiate a realistic GMP

• Failure to establish comprehensive schedule to meet program milestones

• Market conditions improved thereby softening the construction market

WTC PATH Terminal ProjectProcurement Shift

8

WTC PATH Terminal ProjectCost and Schedule Update

Construction Agreement April 25, 2006

Project Budget $2.201B Federal; $2.501B Total 

Required Completion Date April 30, 2012

Revised and Restated Construction Agreement September 18, 2012

Project Budget $2.872B Federal; $3.995B Total

Required Completion Date December 17, 2015

Hurricane Sandy October 26‐29, 2012

Current Completion Date December 31, 20169

WTC PATH Terminal Project

10

WTC PATH Terminal Project

11

12

WTC PATH Terminal ProjectExcavation for the Transit Hub

October 2009

13

WTC PATH Terminal ProjectSteel Erection Below Grade

May 2012

14

WTC PATH Terminal ProjectOculus East Arch Retail Area

August 2012

15

WTC PATH Terminal ProjectTransit Hall

August 2012

16

WTC PATH Terminal ProjectEast/West Connector

August 2012

17

WTC PATH Terminal ProjectTower Cranes in Position to Erect Oculus Steel

May 2013

18

WTC PATH Terminal ProjectErection of Oculus Portal Steel

April 2014

19

WTC PATH Terminal ProjectOculus Rafter Installation

November 2014

20

WTC PATH Terminal ProjectInside the Oculus

August 2015

21

WTC PATH Terminal ProjectEnclosure is Almost Complete

December 2015

22

WTC PATH Terminal ProjectAerial View

January 2016

23

MBTA Green Line Extension ProjectProject Area

24

MBTA Green Line Extension ProjectJustification for CM / GC Approach

A single CM/GC approach would:

• Allow owner to maintain ownership of the design

• Integrate contractor into design process to improve constructability, reduce changes and minimize schedule risk

• Reduce construction contingency since pricing not established by contractor until risk items are assigned

25

MBTA Green Line Extension ProjectJustification for CM / GC Approach

26

MBTA Green Line Extension ProjectProject Delivery Method Advantage/Disadvantage Summary

DBB CM‐GC DBProject‐Level Issues Rating1.  Project Size2.  Cost3.  Schedule4.  Schedule Flexibility5.  Risk Management6.  Risk Allocation7.  Sustainability/LEED CertificationAgency‐Level Issues Rating8.  Agency Experience9.  Staffing Required10. Staff Capability11. Agency Goals and Objectives12. Agency Control of Project13. Third‐Party Agreement(s)Public Policy/Regulatory  Issues Rating14. Competition15. DBE Impacts16. Labor Unions17. Federal/State/Local Laws18. FTA/EPA Regulations19. Stakeholder/Community InputLifecylel Issues Rating20. Lifecycle Costs21. MaintainabilityOther Issues Rating22. Construction Claims23. Adversarial Relationships

Most Appropriate Appropriate Least Appropriate

27

MBTA Green Line Extension ProjectKnown Challenges and Risks

Massachusetts laws limited use of Construction Management delivery methods to vertical construction

• In 2012, Mass legislature authorized use of CM / GC for the Green Line Extension Project as a pilot project

• Further authorization was provided by the MBTA Board and Massachusetts Office of Inspector General Align

• MBTA had virtually no experience with use of CM /GC for large, complex, horizontal construction project

• Heavy reliance on outside consultants by MBTA project team

• CM/GC required to perform no less than 50% of overall contract value

• No incentive for sharing savings; savings benefited MBTA exclusively

28

MBTA Green Line Extension ProjectProject Phasing

Phase 3

Phase 1

Phase 1 Phase 4

Phase 2A

Phase 1

Union Sq

Washington St

Phase 2

Phase 1 – Harvard Street Rail Bridge; Medford Street Rail Bridge; & 21 Water Street Demolition

Phase 2 – Lechmere to Washington Street

Phase 2A – Union Square Branch

Phase 3 – Vehicle Maintenance Facility

Phase 4 – Washington Street to College Avenue

29

MBTA Green Line Extension ProjectBaseline vs. Actual/Projected Cost

$0

$500,000,000

$1,000,000,000

$1,500,000,000

$2,000,000,000

$2,500,000,000

$3,000,000,000

Dec-11 May-13 Sep-14 Jan-16 Jun-17 Oct-18 Mar-20 Jul-21 Dec-22

Baseline

Projected 

CM/GC Cancelled

IGMP’s 1‐3, 4a

FFGA Executed

IGMP 4

30

MBTA Green Line Extension ProjectProject Redirect

In December 2015, the MBTA terminated its contractual relationship with the CM/GC

• Not financially feasible to proceed with GMP #4 FFGA (60% Design) - $487,306,862 CM/GC - $889,081,221

Established conditions for moving forward with GLX

• Undertaking value engineering and redesign to reduce costs while maintaining functionality

• Developing a re-procurement strategy• Putting in place new project management team• Focusing on other non-federal funding sources

31

MBTA Green Line Extension ProjectConceptual Design

32

MBTA Green Line Extension ProjectConceptual Design

33

MBTA Green Line Extension ProjectConceptual Design

34

MBTA Green Line Extension Project

35

MBTA Green Line Extension Project

36

MBTA Green Line Extension Project

37

MBTA Green Line Extension Project

38

MBTA Green Line Extension Project

39

MBTA Green Line Extension Project

40

MBTA Green Line Extension Project

41

MBTA Green Line Extension Project

42

MBTA Green Line Extension Project