Community ConsultationJuly 18, 2018

2

At Waterfront Toronto, we work with our partners at the City of Toronto, Province of Ontario and Government of Canada.

Chris GlaisekSVP Planning & Design, Waterfront Toronto

Julius GombosVP Project Delivery, Waterfront Toronto

3

4

Insert map from Port Lands 101 context board

5

6

Keating Channel

7

8

The Port Lands Flood Protection Project

9

10

Keating Channel

Port Lands Flood Protection Project Boundary

11

What are we building?

12

Earthworks/Flood Protection

Bridges and Structures

14

Roads and Municipal Services

15

Parks

Where are we now?

16

A decade of planning

2006Don Mouth

Naturalization and Port Lands Flood Protection Project Environmental

Assessment (DMNP EA) began

2007International design

competition

2011Port Lands

Acceleration Initiative

2015DMNP EA and Lower

Don Lands EA approved

2016Due Diligence report for Port Lands Flood Protection completed

2017$1.25 billion funding for

Port Lands Flood Protection

Port Lands Framework Plan and Villiers Island Precinct Plan approved

2012Port Lands

Framework Plan and Villiers Island

Precinct Plan began

Where are we now?

Feb 2018Port Lands Flood Protection (PLFP)

Community consultation #1

May 2018Design river, parks,

roads & bridges is 30% complete

July 2018PLFP community consultation #2

Fall 2018River excavation begins

Design for parks & river is 50% complete

Design complete on Cherry Street & Cherry

Street Bridge North

Spring 2019Design for parks & river

is 60% complete

we are here

Fall 2019Design for

Commissioners Street is complete

19

Construction Progress

20

21

22

23

Construction Schedule

24

Construction Schedule: July 2018 – September 2018

25

Construction Schedule: September 2018 – December 2018

26

Construction Schedule: January 2019 – April 2019

27

Construction Schedule: May 2019 – July 2019

28

Construction Schedule: August 2019 – October 2019

29

Construction Schedule: November 2019 – December 2019

Matthew Urbanski, Principal, MVVA

Herb Sweeney, Associate Principal, MVVA

James Roche, Partner, DTAH

Michael Meschino, Principal, Entuitive