Commissioning of Lighting Systems

Post on 23-Feb-2016

35 views 0 download

Tags:

description

Commissioning of Lighting Systems. Michael Chow, P.E., CxA, LEED AP BD+C Owner/Founder of Metro CD Engineering, LLC. Course Objectives. - PowerPoint PPT Presentation

Transcript of Commissioning of Lighting Systems

Commissioning of Lighting SystemsMichael Chow, P.E., CxA, LEED AP BD+COwner/Founder of Metro CD Engineering, LLC

Course Objectives1. The participant will be able to evaluate how to effectively use both the IES

DG-29-11, The Commissioning Process Applied to Lighting and Control Systems, and the ASHRAE Guideline 0-2005 The Commissioning Process as tools to develop an effective lighting commissioning plan

2. The participant will be able to determine the technical requirements for commissioning lighting and control systems to achieve owner performance criteria.

3. The participant will explore the requirements for verification and acceptance activities during each phase of the Commissioning Process.

Commissioning Resources ACG COMMISSIONING GUIDELINE

Commissioning Resources ASHRAE Guideline 0-2005 The Commissioning Process

Commissioning ResourcesUSGBC:LEED Reference Guides

Commissioning Resources IES DG-29-11, The Commissioning Process Applied to Lighting and Control Systems

Commissioning Defined “A quality-focused process for enhancing the delivery of a project. The

process focuses upon verifying and documenting that the facility and

all of its systems and assemblies are planned, designed, installed,

tested, operated, and maintained to meet the owner’s project

requirements (OPR).”

- ASHRAE Guideline 0-2005 The Commissioning Process

Commissioning of Lighting Systems Defined

“A systematic process that ensures that all elements of

the lighting control system perform interactively and

continuously according to documented design intent

and the needs of the building owner.”

- IES Lighting Handbook, 9th Edition

IES DG-29-111. Pre-Design Phase

2. Design Phase

3. Construction Phase

4. Occupancy and Operations Phase

Pre-Design Phase1. Form Commissioning Team

2. The Commissioning Plan

3. Owner’s Project Requirements (OPR)

4. Other Pre-Design Activities

Design Phase1. Basis Of Design (BOD)

2. Project Phasing◦ Schematic design◦ Design Development◦ Construction Documentation◦ Construction Administration◦ Final punch list

Design PhaseUniversity of ToledoLarimer Athletic ComplexRemodel

Courtesy: Metro CD Engineering

Construction Phase1. Construction Administration and Occupancy

2. Performance Testing

3. Issues Log

4. Systems Manual

Occupancy and Operations Phase1. Ongoing commissioning

A. Ongoing training

B. Periodic system testing

C. Maintaining the Systems Manual

Commissioning of Lighting Systems1. Daylight Harvesting

2. Occupancy Sensors

3. Low-voltage Relay Control System

Daylight Harvesting1. BOD (Specify Open, Closed, Dual-

Loop System)

2. Photosensor Location, Orientation and Sensitivity

3. Testing

Occupancy Sensors1. BOD

A. Which types in which areas (e.g., dual technology, Passive IR only, etc.)

B. Time-delay (LED light sources can have shorter delay)

2. MountingA. > 6-8 ft. from HVAC diffusers, etc.B. Placed close to task area.

Occupancy Sensors Courtesy: Wattstopper

Low-voltage Relay Control System

1. BOD A. Control zones (conference

rooms, etc.)

2. Shop Drawing Review3. Testing Coordination with

Operations Team, Contractors, CxA, Design Team

Questions?