Capital Improvement Projects 2014 A Snapshot of Current Construction Activity in the City of Irvine. Replacement of deteriorated asphalt roadway, sidewalk, curbs, median landscape and irrigation Replacement of 140 mature Camphor trees Target Completion Date – April 2014. - PowerPoint PPT Presentation

Transcript of Capital Improvement Projects 2014 A Snapshot of Current Construction Activity in the

Capital Improvement Projects 2014

A Snapshot of Current Construction Activity in the

City of Irvine

Rehabilitation of Campus Drive

• Replacement of deteriorated asphalt roadway, sidewalk, curbs, median landscape and irrigation

• Replacement of 140 mature Camphor trees• Target Completion Date – April 2014

I405 Landscaping and Monument Signs at Jamboree Road

• Installation of gateway signage and new landscaping along both directions of I405 at Jamboree

• Target Completion Date – September 2014

Widening of Barranca Parkway at Jamboree Road

• Add additional lane on northbound Jamboree south of Barranca

• Target Completion Date – July 2017

Barranca Parkway at The District

• Add additional travel lane on westbound Barranca adjacent to The District Shopping Center

• Target Completion Date – April 2014

John Wayne Airport Jet Fuel Line

• Install a fuel pipeline connecting John Wayne Airport to existing Kinder Morgan pipeline in the City of Tustin

• Target Completion Date – To Be Determined

Southern California Gas Company Advance Meter Project

• Installation of infrastructure to transmit usage data directly from the meter to the SCGC

• Target Completion Date – May 2015

Sand Canyon Grade Separation Project

• Lowering Sand Canyon under the railroad to provide a grade separated crossing

• Realignment and widening of the roadway from four to six lanes

• Target Completion Date – November 2014

Sand Canyon/I5 Widening Project

• Add additional travel lane in each direction between Burt Road and northbound freeway on/off-ramps

• Additional lanes to southbound freeway off-ramp and northbound freeway on/off-ramps

• Target Completion Date – July 2014

Jeffrey Open Space Trail

• Construction of three pedestrian overcrossings at Irvine Blvd, Trabuco, and Roosevelt.

• Provides continuous path along the Jeffrey Open Space Trail for bicyclists and pedestrians

• Target Completion Date - August 2014

Orange County Great Park – 688 Acres

• 5-year proposal to build 688 acres of amenities– Sports Park– Bosque Area– Upper Bee Canyon Improvements– Wildlife Corridor– Golf Course– Agricultural Area– Trail Improvements