Energy Commission Review of Power Plants –
Southern California Reliability
2015 Integrated Energy Policy Report Workshopon Southern California Electricity Reliability
University of California, IrvineAugust 17, 2015
Roger JohnsonSiting, Transmission and Environmental Protection Division
Roger.Johnson@energy.ca.gov / (916) 654-5100
California Energy Commission
Southern California Power Plants
May 20, 2015 2
California Energy Commission
NRG PuenteMandalay Generating Station replacement of Units 1&2 with
262 MW GE Frame 7HA CTG
City of Oxnard
Information Hearing 8/27/2015
CEC Decision expected 6/2016
OTC compliance date 12/31/2020
PPA - Yes
California Energy Commission
AES AlamitosAlamitos Generating Station Replacement
640 MW air-cooled combined cycle
[400 MW LMS 100 simple cycle]
City of Long Beach
AFC supplement expected 2015
CEC Decision 2016
OTC compliance date 12/31/2020
PPA – Yes (640 MW)
California Energy Commission
NRG El SegundoEl Segundo Units 1&2 replaced on 8/2013
with 560 MW fast-start combined cycle.
City of El Segundo
El Segundo Units 3&4 Replacement
449 MW (1 fast-start air-cooled combined
cycle and 2 simple cycle peakers)
Final Staff Assessment 8/2015
CEC Decision expected late 2015
OTC compliance date 12/31/2015
PPA - No
California Energy Commission
AES Redondo BeachRedondo Beach Generating Station
Replacement
496 MW (3-on-1 air-cooled combined cycle)
City of Redondo Beach
PSA workshops 5/2015
CEC Decision 2016
OTC compliance date 12/31/2020
PPA - No
California Energy Commission
AES Huntington BeachHuntington Beach Generating Station Replacement
644 MW air-cooled combined cycle
[200 MW LMS 100 simple cycle]
City of Huntington Beach
Amendment to CEC Decision expected 9/2015
OTC compliance date 12/31/2020
PPA- Yes (644 MW)
California Energy Commission
NRG CarlsbadEncina Power Station Replacement
City of Carlsbad
Petition to Amend filed 4/23/2013 for 632 MW (6 LMS 100 simple cycle) and removal of Encina Generating Station
CEC Decision 7/2015
Storage tank demolition underway
Start of Construction TBD
OTC compliance date 12/31/2017
PPA – Yes (500 MW)
California Energy Commission
Pio Pico300 MW simple cycle project approved by CEC 9/12/2012
San Diego County (Otay Mesa)
Project construction started 2/2015
Operation expected 9/2016
California Energy Commission
Wellhead
Wellhead
98 MW (2 LM 6000)
City of Stanton
AFC expected in 2015 after CPUC approves PPA
PPA - Yes
California Energy Commission
Status of Southern California Power Plants
May 20, 2015 11
Project Capacity Development Status ScheduleOTC
Compliance Date
Puente 262 MW Info Hrng 8/2015 CEC Decision 2016 12/31/2020
El Segundo 1El Segundo 2
560 MW449 MW
Operational 8/2013FSA 8/2015
N/ACEC Decision 2015
N/A12/31/2015
Redondo 496 MW PSA wkshps 5/2015 CEC Decision 2016 12/31/2020
Alamitos 640 MW +400MW
AFC supplement expected 2015
Unknown 12/31/2020
Huntington Beach
644 MW +200MW
Amendment to CEC Decision expected 9/2015
Unknown 12/31/2020
Carlsbad 632 MW CEC Decision 7/2015 Const. start TBD 12/31/2017
Wellhead 98 MWAFC expected 2015 after PPA approved
Unknown N/A
Pio Pico 300 MW Const. started 2/2015 Operation 9/2016 N/A