Bybanen Utbygging (BU)
Market DayBergen Light Rail - phase 40900-1115: Part 1 in norwegianLunch 1115-12301230-1500: Part 2 in english
Date: 2017-09-06
Roger SkoglieProject DirectorBybanen Utbygging
Today …
… is not a tender conference
… not an adult education about the Bergen Light Raileither
• Our aim for today is to give the market an overall presentation of the Bergen Light Railconstruction phase 4
Bybanen Utbygging – who are we?:
• A public builder on behalf of Hordaland County Council and the parties in the «Urban Growth Agreement for Bergen»
• We’re given the authorizations to prepare and follow up strategies for procurement and construction works.
• We‘re responsible for the detail design, procurement, construction works and handover to the owner company.
Bybanen Utbygging and the suppliers
The suppliers are important, thus -
• They’re performing the actual building
• Their understanding of the task is crucial
• Their competence and abilities to perform is essential
• BU depends on skilled contractor and suppliers!
Bybanen Utbygging – we see ourselves as …
… a professional and demanding client- only skilled suppliers are working for us
… a client who is concerned about competition and havingthe abilities to create competition in the market. Our objectives are:
– To engage respectabable suppliers– To reduce the market uncertainty– To achieve the "right price"
Receive theorder Procurement Build HandoverDetail
design
Existing Line 1City Center –Airport(apprx. 20 km)
New Line 2City Center –Fyllingsdalen(apprx. 10,8 km)
BU subsections
Hotel Ørnen
Agenda09:00-09:15 Registration and coffee
09:15-09:30 Opening part 1 and welcome by Project Director
09:30-10:45 Presentation of Bergen Light Rail, phase 4 – civil works
10:45-11:15 Procurement plan11:15-12:15 Lunch & mingling
12:30-12:45 Opening part 2 – by Project Director12:45-14:00 Presentation of technical works
construction stage 4
14:00-14:45 Status progress and procurement
14:45-15:30 Individual questions
Ole Wilhelm Mortensen
Today’schairperson
• Contractors with green solutions will have an advantage in future.
• Some green solutions will be chosen in the engineering phase• Some green solutions will be a requirement in the contracts• Bybanen Utbygging looks forward to constructive dialogue with green companies.
Haukeland Station Project manager Mona Løvås
• D34, Haukeland Station, technical• D35, Haukeland Station, elevators• D36, Haukeland Station, escalators• D23, Sheds
Haukeland Station Project manager Mona Løvås
• D34, Haukeland Station, technical• D35, Haukeland Station, elevators• D36, Haukeland Station, escalators
Haukeland, floors:
The construction at the stop will consist of a 9‐storey concrete building, with a total floor area of approximately 4500 m2
Contracts Haukeland
• D12, groundwork and tunnel• D13, concrete work• D34, Ventilation, plumbing, heating, building services and electrical works, fire and security
• D35, Elevators (also Møllendal og Kristianborg)• D36, escaltors
Haukeland, D35
• D35:Elevatorscontract consists of delivery and installation, testing and commissioning
• 6 elevators at Haukeland• 2‐4 elevator at Fløen and Kristianborg
Haukeland D36
• D36, escalatorsContract consists of delivery, assembly, testing and commissioning
• Haukeland: 3 x 3 escalators at S1, 3 x 2 escalators at N3
Power supplyDirector of procurement and turn‐key contracts,
Ole Wilhelm Mortensen
• D43, Catenary System• D44, substations
Changes from previous construction stages
Separate contract for catenary system• D43, Catenary System
Separate contract for the rectifier system• D44, substations
D43 – Catenary system• Catenary system>Mast>Cantilever, GRP>Fixations>Contact wire>Carrying wire>Over voltage protection in
the mast>Section isolators>To be constructed in
accordance to Bybanen design program
D43 – Catenary system• The delivery of complete catenary system for the light rail operation. • Main line:• Approx. 20 000m overhead line on single track• A complete overhead line system• In the tunnel system specifically
designed for this• Contact line for 8 track switches and one track crossing• Switches etc.• Installation in existing line in operationDepot:• Ca. 1000 m OHL on single track• In general simple contact wire• Switches etc.• Close coordination with civil works contracts
and technical contracts.
Time schedule
• Prequalification: Dec. 2019
• Contract: May 2020
D44 – substations• Rectifiers:
• 750V 12 pulse diode rectifiers, transformers and one axillaries transformers, 11kV circuit breakers, 750V circuit breakers, internal and external low voltage switchboard
• Supply and installation of 4 rectifier stations on the line
• Modify one existing rectifier station
• Supply and installation of one rectifier station at workshop / depot
D44 – substations• Rectifiers:
> Overspenningsvern> VLD> TVP safety> Intertripping> Local power scada> Interlocking, elektric and mechanical
D44 – substations• The substation building
delivered by the civil work contract. Including doors and paint.
• BKK, the local power grid provider, is delivering and installing own 11 kV circuit breakers
• D44 are delivering false floor and all other technical installations in the building
Time schedule
• Prequalification: Sept. 2019
• Contract: February 2020
D45 – Low voltageThe delivery includes general low voltage supplyalong the track
• Tunnel installation (3 pcs): Emergency lighting,
ventilation, technical rooms, various assembly works
• Public lighting: Street lights, park area lighting
• Platform installation (10 pcs): LV Switchboards,
heating cables, lighting, other LV works
• Traffic signals (5 pcs)
• Earthing line wide
• Tetra network in tunnel (Løvstakken, «nødnett» for
emergency services).
D45 – Low voltageRequires Norwegian certificationas installer / electrical worker
Time schedule
• Prequalification: Dec. 2018
• Contract: May 2019
D51 – Track worksMainline
• Approx 10 km double track (incl. 5 km tunnel)
• Mainly ballasted track but also embedded
tracks for urban areas
(asphalt/grass/concrete)
• Installation and delivery including rails,
sleepers, ballast mats, ballast, level crossings
• Installation of approx 16-20 switches,
delivered by client
• Cross bonding works for tracks
Close cooperation with side contractors for civil
works and technical works
D51 – Track worksDepot Spelhaugen• Approx 2-3 km single track
• Mainly ballast track, some with asphalt
• Installation and delivery, including rails, sleepers, ballast, damping mats
• Installation of approx 8-12 switches, delivered by client
Close cooperation with side contractors for civil works and technical works
Time schedule• Prequalification: June 2019
• Contract: Dec. 2019
D52 – Track switchesMain line:
• Delivery of approx.16-20 switches
• Grooved (Ri60) and vignol rails (49E1)
• Radius 25 to 100 m
Depot:
• Delivery of approx 8-12 track switches
• Mainly grooved (Ri60)
• Radius 25-50 m
Delivery includes wheel rail study, fabric design, fabrication of rails, sleepers
D52 – Track switchesDelivery of the track switches by the D52 contractor to Bergen.
The D51 Track works contractor is participating at fabric inspection.
The D51 Track works contractor will install the switches.
Bybanen Utbygging (BU)Deliverables and requirements 3D‐modell based construction
Dato: 2017‐09‐06
Bjørn Gisle HodnelandBIM ManagerBybanen Utbygging
3D/BIM goals
Bybanen Utbygging (BU) wants to promote the use ofinformation‐ og communcation technology, trying to streamlinethe design and construction.
This means extended use of 3D models through all phases of theproject and using the model as a platform for exchange ofinformation between, designers, engineers, constructors, ownerand others
3D/BIM goals
• Ensure quality in designed solutions
• Ensure efficient communication in the project
• Ensure constructability
• Increased safety
• Reduced cost
The road to 3D/BIM
• Useful 3D experience from stage 3
• Comprehensive 3D and model requirements for the engineeringand design team.(BIM execution plan)
• Use 3D models in zoning and design phase.
• Extended requirements for 3D og model deliveries and usage in construction phase.
How does this impact stage 4
• Models must be used for construction
• Individual models per contract
• Reduced number of drawings
• Models prioritized over drawings
• Drawings delivered only as digital pdf format
• Focus on collaboration
Technical presentation of3D/BIM plans for stage 4
When: 09.00 am, thursday 07.09.2017Location: 1. floor. Meeting room: Vestland, Fylkeshuset, Agnes
Mowinckels gate 5
• 3D/BIM plans for stage 4• What Bybanen Utbygging delivers as construction data• How Bybanen Utbygging delivers constrution data• Model in tender and construction• Model setup and coding
Contract strategy
Bybanen Utbygging has chosen to:1. Divide the civil works in to several contracts to enable several construction sites
2. Have different sizes for the contracts to enable the possibilities for different contractors
3. Technical contracts mainly covering all the line from city center to the depot
4. Technical contracts dedicated to specific craft
Procurement plan
1. Contract strategy and progress2. Regulations3. Procedures4. Electronic implementation
Contract strategy and progressName Area Type Annonuncement Construction
startD06 – Filling Store Lungegårdsvann
Store Lungegårdsvann from AdO arena to Fløen
Initial entreprise Ongoing
D07 – Crossingrailroad track Fløen
By existing railroadtrack
Initial entreprise Nov 2017 March 2018
D08 – PreparingKronstad
By existing railroadtunnel
Initial entreprise Ongoing March 2018
D09 – CrossingFjøsangerveien
Crossing Fjøsanger by Kristianborg
Initial entreprise Oct 2017 April 2018
D10 – EntranceLøvstakken tunnel west
Fyllingsdalen by northernLydhovden/Dag Hammarskjölds vei
Initial entreprise Ongoing February 2018
Contract strategy and progressName Area Type Annonuncement Construction
startD11 – City centre From Gulating to Store
Lungegårdsvann southby AdO arena
Entreprise groundworks
February 2019 October 2019
D12 - Fløen -Kronstad
From AdO arena to Kanaleveien via Haukeland and Kronstad
Entreprise groundworks
April 2018 December2018
D13 - Haukeland Haukeland withentrance/exit betweenHaukeland hospitaland Haraldsplass
Civil entreprise November 2018 June 2019
D14 - Mindemyren From roundaboutKanalveien north to Kristianborg
Entreprise ground works
September 2018 April 2019
D15 – Løvstakk tunnel
From Kristianborg to Fyllingsdalen
Entreprise ground works
February 2018 October 2018
D16 – Fyllingsdalen From Lydhovden northto Ørnahaugen
Entreprise groundworks
May 2018 January 2019
D17 – Spelhaugen From Ørnahaugen to Spelhaugen
Entreprise ground works
May 2018 January 2019
D18 – Bicycle roadKronstad tunnel
From Møllendal to Kronstad
Entreprise groundworks
April 2019 December2019
Contract strategy and progressName Area Type Annonuncement Construction
startD23 - Sheds Along the entire area November 2018 May 2019
D24 – Noisereduction buildings
Along the entire area September 2019 February 2020
D25 – Mass storage Along the entire area Ongoing November 2017
D26 – Unusablemasses
Along the entire area October 2017 February 2018
Contract strategy and progressName Area Type Annonuncement Construction
startD31 - Tram shed By the end station at
SpelhaugenNovember 2018 June 2019
D34 – Technical installationHaukeland
Underground stationbetween Haukeland hostpital and Haraldsplass
Technical entreprise
November 2018 June 2019
D35 – Elavator Møllendal, Haukeland and Kristianborg
Technical entreprise
November 2018 June 2019
D36 – Escalator Haukeland Technical entreprise
November 2018 June 2019
Contract strategy and progressName Area Type Annonuncement Construction
startD41 - EPCI Railsignaling
Along the entire area Technical total entreprise
Ongoing
D42 - EPCI Signaling Telecom
Along the entire area Technical total entreprise
Ongoing
D43 – OCS poles and catenaryequipment
Along the entire area Technical entreprise
December 2019 May 2020
D44 - Substation Along the entire area Technical entreprise
September 2019 February 2020
D45 – Low voltageinstallations
Along the entire area Technical entreprise
December 2018 May 2019
D51 - Track Along the entire area Technical entreprise
June 2019 December2019
D52 – Trackswitches
Along the entire area Delivery Ongoring
Key dates• Start procurement main entreprises feb 2018• Start building main entreprises sept 2018• Start technical entreprises autumn 2019
Procurement
Bybanen Utbygging want to:• Establish a good dialog with the suppliers• Reduce the risk in the project• High quality on production and final product• That every worker are safe home and protect the suroundings• To reduce our carbon emission• Preform on cost and time
Procurement
Bybanen Utbygging want to support this goals in the procurement by:• Including performance description in the evaluation• Negotiations with the suppliers to understand and challenge
Laws and regulations
• Public procurement laws
• Regulations about procurement within Utilities sector(forsyningsforskriften)
• Above EEA‐threshold: Anounecement of the entreprises througout th EU/EEA
Procedure
• Negotiated procedure:
1. Prequalification o Supplier acceptable: Economics/financial position, relevant experience
etc.o European single procurement document (ESPD)
2. Bid phaseo Prequalified suppliers invited to bido Evaluation and negotiations
Electronic implementation
• Supplier portalo Downloading competition‐/contractual documentso Questions/answerso Supplying letter of qualification and bid
• Start sending/uploading in due time! o Deadline for letter of prequalification is absoluteo Deadline for bid is absolute