As of 9/4/2018
Report prepared by NHDOT - Bureau of Planning and Community Assistance
BRIDGE AID PROGRAM
STATUS REPORT
With Bridge Detail
FiscalYear: 2010 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Emergency Repair, West Bath Road over Ammonoosuc River (Village Covered Bridge), Br. #137/095 (Force Acct DOT-Br. Maint)
$0.00 $25,024.74 $6,256.19$31,280.93Bath
14439C
Complete/Final Audit
10/15/2010
Repair completed 2/2010-FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, West Road over Hoyt Brook, Br. #098/114 (Municipal Managed Project)
$0.00 $428,236.23 $107,059.06$535,295.29Bradford
14284
Complete/Final Audit
5/19/2011
Inspected 10/14/10-FV45.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Borough Road over Smith River, Br. #130/165 (Municipal Managed Project)
$724,772.99 $647,326.91 $41,036.23$1,413,136.13Bristol
14278A
Complete/Final Audit
5/17/2011
Bristol-Hill Project; Inspected 10/28/10-FV9.6 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, River Road over Mascoma River, Br. #123/126 (Municipal Managed Project)
$286,478.03 $273,008.55 $20,505.80$579,992.38Canaan
14446
Complete/Final Audit
1/30/2014
Cap=100% Const/Federal+State 60/40 [also see A project]--Inspected 8/31/10-FV25.2 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Emergency Repair, River Road over Mascoma River, Phase I, Br. #123/126 (Force Acct DOT-Br. Maint)
$0.00 $109,500.17 $30,800.57$140,300.74Canaan
14446A
Complete/Final Audit
10/4/2011
Bailey Bridge installation completed 1/16/07; Removal completed 9/23/10-FV25.2 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, High Haith Road over Squam Lake Channel, Br. #126/139 (Municipal Managed Project)
$0.00 $467,231.16 $23,309.78$490,540.94Center Harbor
15403
Complete/Final Audit
12/21/2010
100% SAB for Construction; Inspected 9/1/10-FV3.3 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Fling Road over Clay Brook, Br. #155/062 (Municipal Managed Project)
$0.00 $518,431.91 $44,295.47$562,727.38Charlestown
13534
Complete/Final Audit
3/15/2013
Construction=100% SAB+5%(Cap)- Bridge Inspection 7/14/11-FV38.6 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Columbia Covered Bridge over Connecticut River, Br. #077/140 (Force Acct DOT-Br. Maint)
$0.00 $200,349.11 $0.00$200,349.11Columbia
13815
Complete/Final Audit
2/7/2011
Columbia-Lemington,VT project; completed 6/17/20100.0 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Emergency Repair, Sewalls Falls Road over Merrimack River, Br. #070/117 (Force Acct DOT-Br. Maint)
$0.00 $169,094.74 $42,273.69$211,368.43Concord
12838
Complete/Awaiting Audit
(See also 12004)-Waiting payment from City0.0 14 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2010 Page 1
(Page 2 of 46)Report Date: 9/4/2018 8:11:54 AM
With Bridge Detail
FiscalYear: 2010 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Sandown Road over Exeter River, Br. #047/126 (Municipal Managed Project)
$0.00 $479,347.61 $18,385.75$497,733.36Danville
13535
Complete/Final Audit
10/11/2012
100% Construction w/SAB funds -Bridge Inspected 1/11/11-FV38 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Fordway Road over Beaver Brook, Br. #056/084 (Municipal Managed Project)
$611,455.66 $537,974.07 $32,584.24$1,182,013.97Derry
13650
Complete/Final Audit
4/12/2011
Inspected 11/30/10-FV72.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Area Road over Poor Farm Brook, Br. #147/138
$567,000.00 $589,709.90 $0.00$1,209,637.38Gilford $52,927.48
15626
Complete/Final Audit
10/31/2011
Gunstock Commissioners on behalf of the County; Inspected 8/19/11-FV45.7 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Other, NHRR over Drakeside Road, Br. #163/121(Closed) (Force Acct DOT-Br. Maint)
$0.00 $16,737.01 $0.00$16,737.01Hampton
15813
Complete/Final Audit
3/19/2010
Bridge Removal-FVN/A NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Pleasant Valley Road over Bunnell Brook, Arthur White Bridge, Br. #223/062 (Municipal Managed Project)
$0.00 $221,166.56 $10,074.00$231,240.56Lancaster
12796
Complete/Final Audit
11/24/2009
Inspected 9/11/09-FV18.4 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Gates Road over Robbins Brook, Br. #098/128 (Municipal Managed Project)
$0.00 $114,458.22 $28,614.55$143,072.77Marlborough
14939
Complete/Final Audit
4/6/2011
Inspection Date 9/28/10-FV71.8 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Lyndeborough Road over South Branch Piscataquog River, Br. #064/056 (Municipal Managed Project)
$0.00 $854,778.90 $136,290.35$991,069.25New Boston
14247
Complete/Final Audit
11/10/2010
Inspected 11/10/10-FV33.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Emergency Repair, Mill Pond Road over Little River, Br. #204/082(Washed out) (Force Acct DOT-Br. Maint)
$0.00 $50,704.82 $22,809.48$73,514.30Nottingham
14943
Complete/Final Audit
11/3/2009
April 2007 Flood Event; BB Installed 12/6/07; inspected 7/23/08Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Garden Road over Little River, Br. #118/053 (Municipal Managed Project)
$308,700.00 $233,021.13 $6,805.28$548,526.41Plaistow
14390
Complete/Final Audit
4/1/2015
Cap=100% Construction/Federal+State Inspected 12/1/10-FV29 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, NH 1A over Sagamore Creek, Br. #198/034 (Municipal Managed Project)
$0.00 $192,386.00 $48,096.50$240,482.50Portsmouth
14493A
Complete/Final Audit
3/9/2011
Temp Repair completed 5/24/10-FV50.5 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2010 Page 2
(Page 3 of 46)Report Date: 9/4/2018 8:11:54 AM
With Bridge Detail
FiscalYear: 2010 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Durand Road over Carlton Brook, Br. #140/067 (Municipal Managed Project)
$145,828.64 $159,914.79 $15,673.93$321,417.36Randolph
14386
Complete/Final Audit
9/4/2013
Cap=100% Construction/Federal+State (60/40); Inspected 8/12/10-FV46.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Lawrence Road over Spicket River, Br. #113/070 (Municipal Managed Project)
$774,068.87 $666,502.52 $37,614.15$1,478,185.54Salem
15593
Complete/Final Audit
12/17/2013
100% Construction/Federal+State - Inspected 3/22/11-FV57.5 13 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Mountain Road over Blackwater River, Pingree Bridge, Br. #095/135 (Municipal Managed Project)
$0.00 $1,142,578.87 $187,382.11$1,329,960.98Salisbury
14626A
Complete/Final Audit
2/28/2012
Inspected 12/8/10 >>Add 14626 to final payment-FV13.7 03F Remarks:Red List: FSR: WT: No Outlet: NoYes
Emergency Repair, Phase I: Northwood-Bow Lake Road over Brook, Br. #085/040 (Municipal Managed Project)
$0.00 $13,566.84 $3,391.72$49,562.68Strafford $32,604.12
15502
Complete/Final Audit
6/30/2009
FEMA Disaster 8/11/08; Inspected 10/15/08-FV46.2 159 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, High Street over Melvin River, Br. #141/068 (Force Acct DOT-Br. Maint)
$0.00 $176,081.17 $44,020.29$220,101.46Tuftonboro
15291
Complete/Final Audit
11/12/2009
Completed 5/1/0940.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Emergency Repair, Phase I: Connors Mill Road over Schoodac Brook, Br. #194/172 (Force Acct DOT-Br. Maint)
$0.00 $37,858.72 $11,444.68$49,303.40Warner
14519
Complete/Final Audit
11/30/2009
May 06 Rain Event - FEMA (Bailey Bridge removed 4/9/09 )27 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Phase II: Saunders Hill Road over Baker River, Br. #142/096 (Municipal Managed Project)
$226,800.00 $433,637.11 $86,372.30$746,809.41Wentworth
14517A
Complete/Final Audit
8/13/2013
Cap=100% Construction/Federal+State Inspected 11/24/10-FV29.2 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, River Road North over Aldrich Brook, Br. #107/163 (Municipal Managed Project)
$0.00 $56,023.88 $14,005.97$70,029.85Westmoreland
15590
Complete/Final Audit
7/19/2011
Inspected 10/9/08-FV39.0 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2010 Page 3
(Page 4 of 46)Report Date: 9/4/2018 8:11:54 AM
With Bridge Detail
FiscalYear: 2010 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2010 Programmed Total
FY 2009 Balance $0.00 $6,538,415.71
$11,000,000.00 $6,804,000.00
$3,645,104.19 $8,814,651.65 $1,019,102.09
FY 2010 Appropriation
FY 2010 Funds Available $11,000,000.00 $13,342,415.71
Minus FY 2010 Programmed Total $6,998,481.77 $10,161,438.07
$4,001,518.23 $3,180,977.65Sub-total
($4,001,518.23)
$0.00
$0.00 $3,180,977.65FY 2010 Balance
$13,564,389.52
State Adjustment:App includes $6.8 M Bond; Federal Adjustment: App includes $7 M ARRA-related Funds
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2010.
$85,531.60
Number of Projects for FY 2010 By Funding Source
Funding or Managed By Tally
Federal/State 1
Federal/State/Municipal 4
Federal/State/Municipal/Other 1
Federal/State/Other 1
State 1
State/Municipal 18
State/Municipal/Other 1
27Total Number of projects
Managed By Tally
Number of Projects for FY 2010 By Managing Lead
Force Acct DOT-Br. Maint 6
Municipality 20
Other 1
27Total Number of projects
FY 2010 Page 4
(Page 5 of 46)Report Date: 9/4/2018 8:11:54 AM
With Bridge Detail
FiscalYear: 2011 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Places Mill Road over Sunset Lake Outlet, Br. #098/178 (Municipal Managed Project)
$0.00 $430,830.73 $75,478.16$506,308.89Alton
14239
Complete/Final Audit
12/13/2012
Br. Insp. 9/14/11-FV32.1 03P Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, River Street over Squam River, Br. #101/073 (Municipal Managed Project)
$0.00 $385,920.80 $96,480.20$482,401.00Ashland
14262
Complete/Final Audit
1/3/2012
Br. Inspection 12/8/11-FV40.9 105 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Fremont Road over Towle Brook, Br. #147/100 (Municipal Managed Project)
$0.00 $314,430.55 $78,607.64$393,038.19Chester
13696
Complete/Final Audit
11/1/2012
Br. Inspection 12/14/11-FV21.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Tasker Hill Road over Pequawket Pond, Br. #182/066 (Municipal Managed Project)
$0.00 $368,885.70 $57,052.70$425,938.40Conway
15300
Complete/Final Audit
3/31/2011
Bridge Inspected 9/29/10-FV40.6 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, South Avenue over Shield Brook, Br. #066/092 (Municipal Managed Project)
$0.00 $314,273.60 $78,568.40$392,842.00Derry
13651
Complete/Final Audit
11/29/2011
Bridge Inspection 9/19/11-FV58.3 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Wiswall Road over Lamprey River, Br. #070/072, 069/072 (Municipal Managed Project)
$466,413.78 $454,749.40 $65,952.20$1,721,157.29Durham $734,041.91
14453
Complete/Final Audit
6/22/2011
May 2006 Rain Event - FEMA&OEM; Inspected 12/2/10-FV20.9 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bay Road over Cocheco River, Br. #060/144 (Municipal Managed Project)
$0.00 $314,806.59 $53,026.15$367,832.74Farmington
15677
Complete/Final Audit
9/30/2010
Bridge Inspection 9/30/10-FV40.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Phase II: Mill Brook Road over Mill Brook, Br. #162/139 (Municipal Managed Project)
$0.00 $332,601.47 $78,355.35$410,956.82Grafton
13373A
Complete/Final Audit
2/27/2012
FY10>11-Bridge Inspection 10/20/11-FV19.4 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, High Street over North River, Br. #063/045 (Municipal Managed Project)
$0.00 $1,117,113.36 $166,934.34$1,284,047.70Lee
14842
Complete/Final Audit
10/17/2012
Bridge Inspected 2/21/12-FV55.9 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Old Mill Road over Oyster River, Br. #116/130 (Force Acct DOT-Br. Maint)
$0.00 $94,542.71 $23,635.68$118,178.39Lee
14843
Complete/Final Audit
4/22/2011
BM Completion Date 11/9/10-FV99.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2011 Page 1
(Page 6 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2011 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Stearns Brook Road over Stearns Brooks, Br. #254/038 (Force Acct DOT-Br. Maint)
$0.00 $25,838.09 $6,459.52$32,297.61Milan
20814
Complete/Final Audit
5/6/2014
DOT to install Bailey Br purchased by Town. BM completed 7/5/11-Pay Rec'd 8/11/14-FV21.9 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Village Road over Andrew Brook, Br. #120/078 (Municipal Managed Project)
$0.00 $601,826.34 $93,065.33$694,891.67Newbury
14916
Complete/Final Audit
3/2/2012
Br. Inspected 12/20/11-FV31.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Sutton Road over Ring Brook, Br. #138/072 (Municipal Managed Project)
$0.00 $699,673.87 $114,816.12$814,489.99Newbury
14917
Complete/Final Audit
2/11/2013
Br. Inspected 12/20/11-FV49.3 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Reed's Farm Road over Brook, Br. #167/148 (Municipal Managed Project)
$0.00 $97,060.27 $24,265.07$121,325.34Newport
15597
Complete/Final Audit
6/2/2011
Town Force Acct Used; Inspected 8/10/10-FV79.9 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Phase II: Northwood-Bow Lake Road over Brook, Br. #085/040 (Municipal Managed Project)
$0.00 $341,497.44 $55,537.66$397,035.10Strafford
15502A
Complete/Final Audit
4/12/2011
Inspected 12/20/10-FV46.2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Other, Main Street, Thompson Covered Bridge, Br. #093/124 (Municipal Managed Project)
$514,940.65 $169,805.79 $62,170.40$746,916.84Swanzey
14195
Complete/Final Audit
1/30/2014
Fed Historic Br; Fire protection system & center pier rehab; Completed 10/22/10-FV13.6 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Water Street over Johns River, Br. #106/106 (Municipal Managed Project)
$0.00 $22,944.72 $5,736.18$28,680.90Whitefield
15732
Complete/Final Audit
10/2/2013
Only Paying PE-FV37.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2011 Page 2
(Page 7 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2011 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2011 Programmed Total
FY 2010 Balance $0.00 $3,180,977.65
$8,000,000.00 $6,804,000.00
$981,354.43 $6,086,801.43 $1,136,141.10
FY 2011 Appropriation
FY 2011 Funds Available $8,000,000.00 $9,984,977.65
Minus FY 2011 Programmed Total $4,000,000.00 $7,012,227.21
$4,000,000.00 $2,972,750.44Sub-total
($4,000,000.00)
$0.00
$0.00 $2,972,750.44FY 2011 Balance
$8,938,338.87
State Adjustment:App includes $6.8 M Bond; Federal Adjustment: App includes $4 M ARRA-related Funds
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2011.
$734,041.91
Number of Projects for FY 2011 By Funding Source
Funding or Managed By Tally
Federal/State/Municipal 1
State/Municipal 17
State/Municipal/Other 1
19Total Number of projects
Managed By Tally
Number of Projects for FY 2011 By Managing Lead
Force Acct DOT-Br. Maint 2
Municipality 17
19Total Number of projects
FY 2011 Page 3
(Page 8 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2012 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Reed Road over West Alton Brook, Br. #078/275 (Municipal Managed Project)
$0.00 $400,968.30 $100,242.08$501,210.38Alton
20403
Complete/Final Audit
7/27/2012
Bid Stage for Contract #2-Br. Inspected 12/20/11 Contract #3-FV56.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Old North Branch Road over North Branch River, Br. #130/149 (Municipal Managed Project)
$488,380.13 $519,423.17 $48,459.09$1,056,262.39Antrim
14944
Complete/Final Audit
12/30/2014
Cap=100% Construction/Federal+State (+5%) Br. Inspected 1/11/12-FV38.0 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Water Street over Great Brook, Br. #178/069 (Municipal Managed Project)
$0.00 $303,557.87 $75,889.47$379,447.34Antrim
15350
Complete/Final Audit
2/15/2012
Bridge Inspected 10/07/10-FV40.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Phase II: West Bath Road over Ammonoosuc River (Village Covered Bridge), Br. #137/095 (Municipal Managed Project)
$0.00 $832,563.62 $208,141.85$3,360,705.47Bath $2,320,000.00
14439
Complete/Final Audit
5/4/2018
Inspected 9/8/14-FV0.0 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Prospect Street over Ammonoosuc River, Br. #071/137 (Municipal Managed Project)
$0.00 $701,048.07 $193,512.02$894,560.09Bethlehem
14228
Complete/Final Audit
1/22/2013
Br. Insp. 12/15/11-FV27 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Blair Road over Pemigewasset River; Blair Covered Bridge, Br. #117/076 (Municipal Managed Project)
$0.00 $864,197.22 $151,288.24$2,738,992.98Campton $1,723,507.52
12407
Complete/Final Audit
3/2/2015
Nat'l Historic Cov Br Preservation Program Br. Inspected 7/30/14-FV16.3 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Washburn Road over Mohawk River, Br. #188/063 (Municipal Managed Project)
$0.00 $49,200.00 $12,300.00$61,500.00Colebrook
21385
Complete/Final Audit
7/10/2012
Br. Inspection 12/13/11-FV16.6 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Davis Road over Smith River, Br. #123/104 (Municipal Managed Project)
$0.00 $352,968.54 $53,346.24$406,314.78Grafton
14627
Complete/Final Audit
3/12/2012
Bridge Inspected 12/16/11 For Estimate this project in ProMIS is under14621-FV30.3 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Church Street over Beaver Brook, Br. #140/075 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Keene
15345
Complete/Final Audit
5/12/2014
Project is being reprogram to Keene 2934047.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2012 Page 1
(Page 9 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2012 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Rehabilitation, Mount Orne Road over Connecticut River; Mount Orne Covered Bridge, Br. #039/105 (Force Acct DOT-Br. Maint)
$0.00 $124,577.12 $31,144.28$155,721.40Lancaster
15924
Complete/Final Audit
7/22/2013
FV2.0 Y Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Millbrook Road over Mill Brook, Br. #084/147 (Force Acct DOT-Br. Maint)
$0.00 $63,281.52 $15,820.38$79,101.90Landaff
20251
Complete/Final Audit
1/11/2012
BM completed 10/13/11-FV41 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Emergency Repair, Phase I: Loon Mountain Road over East Br Pemigewasset River, Br. #212/151 (Force Acct DOT-Br. Maint)
$0.00 $165,090.50 $60,340.04$844,519.90Lincoln $619,089.36
16400
Complete/Final Audit
11/13/2013
FEMA funds for 2 temporary bridges (Phase II=#22292)2.0 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Historic Preservation, River Road over Clay Brook; Edgell Covered Bridge, Br. #069/190 (Force Acct DOT-Br. Maint)
$0.00 $104,693.52 $26,173.38$130,866.90Lyme
14235
Complete/Final Audit
5/31/2013
21.1 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Other, Perkins Road over B&M Railroad, Br. #119/074(Closed) (Force Acct DOT-Br. Maint)
$0.00 $60,000.00 $0.00$60,000.00Madbury
15773
Under Design
Bridge Removal 12/0932.0 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Kelley Street over B&MRR/Piscataquog River, Br. #119/045 (Municipal Managed Project)
$4,103,048.47 $494,400.70 $54,352.26$5,249,079.65Manchester $597,278.22
15390
Complete/Final Audit
12/30/2014
Federal+SAB; Br. Inspected 10/01/12-FV87.4 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Morse Loop Road over Brook, Br. #170/024 (Municipal Managed Project)
$0.00 $41,748.80 $10,437.20$52,186.00Sutton
15346
Complete/Final Audit
6/17/2011
Town closed road & discontinued project-FV53.5 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Old Westport Road over Wheelock Brook, Br. #133/163 (Municipal Managed Project)
$0.00 $339,894.26 $55,718.07$395,612.33Winchester
15317
Complete/Final Audit
2/29/2012
Br. Insp. 7/18/11-FV49.8 106 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2012 Page 2
(Page 10 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2012 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2012 Programmed Total
FY 2011 Balance $0.00 $2,972,750.44
$4,000,000.00 $6,804,000.00
$4,591,428.60 $5,417,613.22 $1,097,164.60
FY 2012 Appropriation
FY 2012 Funds Available $4,000,000.00 $9,776,750.44
Minus FY 2012 Programmed Total $0.00 $7,791,607.19
$4,000,000.00 $1,985,143.24Sub-total
($4,000,000.00)
$0.00
$0.00 $1,985,143.24FY 2012 Balance
$16,366,081.51
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2012.
$5,259,875.10
Number of Projects for FY 2012 By Funding Source
Funding or Managed By Tally
State 1
State/Municipal 16
State/Municipal/Other 3
20Total Number of projects
Managed By Tally
Number of Projects for FY 2012 By Managing Lead
Force Acct DOT-Br. Maint 5
Municipality 15
20Total Number of projects
FY 2012 Page 3
(Page 11 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2013 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Depot Street over Relief, Br. #181/071 (Municipal Managed Project)
$0.00 $249,767.46 $62,441.87$312,209.33Antrim
14940
Complete/Final Audit
8/4/2017
FV94.7 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Depot Street over Contoocook River Overflow, Br. #183/071 (Municipal Managed Project)
$0.00 $428,748.70 $107,187.18$535,935.88Antrim
14941
Complete/Final Audit
6/4/2015
Br. Inspected 11/5/13-FV63.5 8 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Depot Street over Relief, Br. #181/071 (Municipal Managed Project)
$0.00 $249,767.46 $69,738.40$319,505.86Antrim
15349A
Complete/Final Audit
6/4/2015
Br. Inspected 11/5/13--FV47.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Phase II: Depot Street over Contoocook River, Br. #184/071 (Municipal Managed Project)
$0.00 $916,609.62 $233,771.64$1,150,381.26Antrim
15349A
Complete/Final Audit
4/2/2015
Antrim-Bennington Project; PO #400343836 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Chester Turnpike over Murray Brook, Br. #120/149 (Municipal Managed Project)
$0.00 $243,868.66 $60,967.17$363,729.58Auburn $58,893.75
15512
Complete/Final Audit
7/10/2012
April 2007 Flood; Town Force Account - Inspected 11/30/1064.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Cross Road over Gunnison Brook, Br. #105/129 (Municipal Managed Project)
$0.00 $344,910.86 $86,227.72$431,138.58Goshen
16112
Complete/Final Audit
8/26/2013
Br. Inspected 8/1/2013-FV40.9 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, South Merrimack Road over Witch Brook, Br. #122/164 (Municipal Managed Project)
$0.00 $249,199.98 $62,300.00$311,499.98Hollis
14897
Complete/Final Audit
7/10/2012
Inspected 12/6/07-FV37.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Spring Street over Beaver Brook, Br. #140/078 (Municipal Managed Project)
$0.00 $85,114.71 $21,278.67$106,393.38Keene
14441
Complete/Final Audit
1/16/2014
Only paying PE and ROW. City withdrew construction-FV48.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Wire Road over Baboosic Brook, Br. #098/174 (Municipal Managed Project)
$0.00 $828,074.16 $207,018.55$1,035,092.71Merrimack
15839
Complete/Final Audit
9/16/2013
Inspected 6/27/13-FV86.3 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Emerson Way over Widow Harris Brook, Br. #114/108 (Municipal Managed Project)
$0.00 $406,066.26 $101,516.56$507,582.82Salem
14881
Complete/Final Audit
1/2/2013
Br. Insp. 3/23/11-FV23.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2013 Page 1
(Page 12 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2013 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Providence Hill Road over Providence Hill Brook, Br. #120/155 (Municipal Managed Project)
$0.00 $94,206.84 $23,551.71$117,758.55Salem
20225
Complete/Final Audit
5/30/2013
Only paying PE--Br. Inspection 10/15/13-FV52.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Cobble Hill Road over California Brook, Br. #082/115 (Municipal Managed Project)
$0.00 $1,180,838.16 $295,209.54$1,476,047.70Swanzey
14918
Complete/Final Audit
2/28/2014
PO #4002971; Inspected 12/3/13-FV46.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Warmac Road over Perry Brook, Br. #135/068 (Municipal Managed Project)
$0.00 $451,088.82 $112,772.20$563,861.02Swanzey
15348
Complete/Final Audit
2/28/2014
PO 4002970 Br. Inspected 12/3/13-FV39.8 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Putnam Road over Brook & Brook Overflow, Br. #116/139, 117/138 (Municipal Managed Project)
$0.00 $26,400.00 $6,600.00$33,000.00Temple
14937
Complete/Final Audit
10/18/2012
Engr Study only. Town closed project and substituted another-FV32.2 6 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Stage Road over Little Sugar River; Phase I&II, Br. #035/074 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Unity
14248
Complete/Final Audit
4/13/2012
October 2005 Rain Event-Project completed without DOT funding-FV39.3 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Evans Road over South Branch Baker River, Br. #136/053 (Municipal Managed Project)
$0.00 $487,227.95 $121,806.99$609,034.94Wentworth
14516
Complete/Final Audit
1/27/2014
Br. Inspected 9/17/13-FV46.5 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2013 Page 2
(Page 13 of 46)Report Date: 9/4/2018 8:11:55 AM
With Bridge Detail
FiscalYear: 2013 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2013 Programmed Total
FY 2012 Balance $0.00 $1,985,143.24
$4,000,000.00 $6,804,000.00
$0.00 $6,241,889.64 $1,572,388.20
FY 2013 Appropriation
FY 2013 Funds Available $4,000,000.00 $8,789,143.24
Minus FY 2013 Programmed Total $1,595,421.60 $11,978,199.41
$2,404,578.40 ($3,189,056.17)Sub-total
($2,404,578.40)
$0.00
$0.00 ($3,189,056.17)FY 2013 Balance
$7,873,171.59
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2013.
$58,893.75
Number of Projects for FY 2013 By Funding Source
Funding or Managed By Tally
Federal/State/Municipal 1
State/Municipal 19
State/Municipal/Other 1
21Total Number of projects
Managed By Tally
Number of Projects for FY 2013 By Managing Lead
Municipality 21
21Total Number of projects
FY 2013 Page 3
(Page 14 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2014 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Crawley Falls Road over Exeter River, Br. #073/065 (Municipal Managed Project)
$0.00 $916,457.49 $229,114.38$1,145,571.87Brentwood
15277
Complete/Final Audit
7/25/2016
FY2010>12>13-Br. Inspected 10/29/14-FV32.4 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, New Boston Road over Powwow River, Br. #116/113 (Municipal Managed Project)
$0.00 $331,802.14 $82,950.53$414,752.67Kingston
14973
Complete/Final Audit
7/31/2013
Inspected 5/7/09-FV62.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Manchester Street over Pennichuck Reservoir, Br. #120/026 (Municipal Managed Project)
$0.00 $1,875,047.03 $666,005.34$2,541,052.37Nashua
13964
Complete/Final Audit
2/6/2017
Merrimack-Nashua project (Nashua is managing)-Br. Inspect 9/10/15-FV27.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Willow Street over Beaver Brook, Br. #105/069 (Municipal Managed Project)
$0.00 $1,524,504.80 $381,126.20$1,982,752.00Pelham $77,121.00
26762
Under Construction
56 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Fay Martin Road over Tully Brook, Br. #160/071 (Municipal Managed Project)
$0.00 $452,335.20 $93,093.62$545,428.82Richmond
21190
Complete/Final Audit
11/5/2013
Br. Inspected 7/24/13-FV43.1 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Teague Drive over Spicket River, Br. #095/175 (Municipal Managed Project)
$0.00 $87,092.20 $21,773.05$108,865.25Salem
27202
Complete/Final Audit
3/3/2015
ROW+CON is non-participating-FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Plummer Road over Hermit Brook, Br. #148/156 (Municipal Managed Project)
$0.00 $228,204.35 $57,051.09$285,255.44Sanbornton
16081
Complete/Final Audit
12/10/2013
Town replaced without Bridge Aid. SAB paid for Engr Study only-FV14.6 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Cross Road over Town Line Brook, Br. #071/099 (Municipal Managed Project)
$0.00 $380,293.42 $95,073.36$475,366.78Sharon
15513
Complete/Final Audit
11/28/2014
Br. Inspection 10/1/2014-FV66.5 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Dufour Road over South Branch Baker River, Br. #162/072 (Municipal Managed Project)
$0.00 $317,040.00 $79,260.00$396,300.00Wentworth
14518
Complete/Awaiting Audit
Br. Inspection 8/27/1441.0 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Broad Brook Road over Broad Brook, Br. #070/106 (Municipal Managed Project)
$0.00 $330,921.51 $66,141.58$397,063.09Winchester
15316
Complete/Final Audit
1/5/2015
Br. Inspected 11/18/14-FV25.4 10 Remarks:Red List: FSR: WT: No Outlet: YesYes
FY 2014 Page 1
(Page 15 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2014 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2014 Programmed Total
FY 2013 Balance $0.00 ($3,189,056.17)
$4,000,000.00 $6,804,000.00
$0.00 $6,443,698.14 $1,771,589.15
FY 2014 Appropriation
FY 2014 Funds Available $4,000,000.00 $3,614,943.83
Minus FY 2014 Programmed Total $0.00 $6,803,340.57
$4,000,000.00 ($3,188,396.74)Sub-total
($4,000,000.00)
$0.00
$0.00 ($3,188,396.74)FY 2014 Balance
$8,292,408.29
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2014.
$77,121.00
Number of Projects for FY 2014 By Funding Source
Funding or Managed By Tally
State/Municipal 15
State/Municipal/Other 2
17Total Number of projects
Managed By Tally
Number of Projects for FY 2014 By Managing Lead
Municipality 17
17Total Number of projects
FY 2014 Page 2
(Page 16 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2015 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Manchester Road over Beaver Brook, Br. #134/100 (Municipal Managed Project)
$0.00 $1,010,489.66 $252,622.42$1,329,826.08Amherst $66,714.00
20242
Complete/Final Audit
2/13/2017
Br. Inspected 4/1/16-FV40.5 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Old Candia Road over Maple Falls Brook, Br. #088/159 (Municipal Managed Project)
$0.00 $267,867.58 $66,966.90$334,834.48Auburn
15657
Complete/Final Audit
9/20/2014
Br. Inspection 12/09/12-FV35.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, River Street over Saco River, Br. #109/113 (Municipal Managed Project)
$0.00 $143,931.19 $35,982.80$719,655.97Bartlett $539,741.98
22893
Complete/Final Audit
3/3/2017
Br Inspected 8-4-16-FV87.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Other, West Street (Old 3-B) over Merrimack River, Br. #132/085 (Municipal Managed Project)
$0.00 $240,058.98 $60,014.74$300,073.72Boscawen
15281
Complete/Final Audit
3/27/2015
Boscawen-Canterbury Bridge Removal Project-FVN/A BRC Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Breezy Hill Road over Warner River, Br. #161/145 (Municipal Managed Project)
$0.00 $1,153,884.19 $288,471.06$1,442,355.25Bradford
15857
Complete/Final Audit
5/8/2017
FY2016>2018; SB367>2015 offered-Br. Inspected 8/30/16-FV32.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Goose Pond Road over Goose Pond Brook, Br. #087/092 (Municipal Managed Project)
$0.00 $498,647.12 $124,661.78$623,308.90Canaan
14952
Complete/Final Audit
4/14/2016
Br. Inspected 12/12/14-FV39.8 6 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Meriden Hill Road over Lyman Brook, Br. #054/032 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Columbia
29388
Complete/Final Audit
1/5/2015
Project is canceled33.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Juniper Hill Road over Brennan Brook, Br. #093/087 (Municipal Managed Project)
$0.00 $400,201.38 $100,050.35$500,251.73Francestown
15762
Complete/Final Audit
2/8/2016
Br. Inspected 10/20/15-FV48.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Woodward Hill Road over Brennan Brook, Br. #121/077 (Municipal Managed Project)
$0.00 $506,913.68 $126,728.42$633,642.10Francestown
15764
Complete/Final Audit
2/8/2016
Br. Inspected 10/20/15-FV41.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Second NH Turnpike over So. Br. Piscataquog River, Br. #125/077 (Municipal Managed Project)
$0.00 $682,308.82 $170,577.21$852,886.03Francestown
22892
Complete/Final Audit
1/3/2014
Br. Inspected 10/10/14-FV40.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2015 Page 1
(Page 17 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2015 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Pelham Road over Second Brook, Br. #129/092(Tentative) (Municipal Managed Project)
$0.00 $622,821.70 $155,705.44$778,527.14Hudson
16175
Complete/Final Audit
Br. Inspected 1/4/16 - PO 4005738-1-Awaiting FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Phase II: Loon Mountain Road over East Br Pemigewasset River, Br. #212/151 (Municipal Managed Project)
$0.00 $1,679,436.10 $419,859.02$8,105,194.14Lincoln $6,005,899.02
22292
Under Construction
FEMA funds. PO #4003795, L2 (See also #16400) - TempBr Rental=$1600/month2 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Jennison Road over Hartshorn Brook, Br. #099/150 (Municipal Managed Project)
$0.00 $470,080.88 $117,520.22$599,246.87Milford $11,645.77
22372
Complete/Final Audit
12/29/2016
[Steel beam rental monthly@$270.83/month] Br. Inspected 11/19/1539.4 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Jones Crossing over Souhegan River, Br. #062/138(Closed) (Municipal Managed Project)
$0.00 $122,689.54 $30,672.39$153,361.93Milford
29509
Complete/Final Audit
11/28/2016
Bridge Removal - No A&B phases-FVN/A BRC Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Riverdale Road over Mid Branch Piscataquog River, Br. #131/147 (Municipal Managed Project)
$0.00 $739,208.76 $184,802.19$924,010.95New Boston
22352
Complete/Final Audit
8/21/2017
Br. Inspected 11/23/15 -FV100.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Paradise Road over Sugar River, Br. #177/117(Closed) (Municipal Managed Project)
$0.00 $39,016.77 $9,754.19$48,770.96Newport
14969
Complete/Final Audit
9/29/2014
Bridge Closed; Town canceled project 9/25/14-FV16.4 BRC Remarks:Red List: FSR: WT: No Outlet: YesYes
Bridge Replacement, Indian Pond Road over Bean Brook, Br. #108/075(New) (Municipal Managed Project)
$0.00 $69,919.69 $17,479.92$301,161.53Piermont $213,761.92
27450
Complete/Awaiting Audit
FEMA-State paying Construction ONLYRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Cluffs Crossing over Policy Brook, Br. #094/060 (Municipal Managed Project)
$0.00 $666,235.31 $166,558.83$832,794.14Salem
15592
Complete/Final Audit
8/11/2014
Bridge Inspection Approved 9/29/10-FV65.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Pelham Road over Porcupine Brook, Br. #058/074(New) (Municipal Managed Project)
$0.00 $287,702.59 $71,925.65$359,628.24Salem
15596
Complete/Final Audit
9/4/2014
Br. Insp. 3/22/11-FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, North Main Street over Widow Harris Brook, Br. #115/115 (Municipal Managed Project)
$0.00 $553,394.25 $138,348.57$691,742.82Salem
15772
Complete/Final Audit
8/11/2014
Inspected 3/23/11-FV52.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2015 Page 2
(Page 18 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2015 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Town Farm Road over Spicket River, Br. #118/116 (Municipal Managed Project)
$0.00 $1,078,943.48 $269,735.88$1,384,623.21Salem $35,943.85
15988
Complete/Final Audit
4/10/2017
PO 4003611-Br. Inspected 6/28/16-FV27.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Other, Lawrence Road over Spicket River (Municipal Managed Project)
$0.00 $25,038.90 $6,259.72$31,298.62Salem
25121
Complete/Final Audit
3/4/2015
FEMA LOMR Prep for Project #15593 [PE, ROW, & Const were done in #15593]-FVRemarks:Red List: FSR: WT: No Outlet:
Bridge Replacement, First Crown Point Road over Big River, Br. #069/164 (Municipal Managed Project)
$0.00 $497,630.05 $76,851.71$574,481.76Strafford
24213
Complete/Final Audit
12/2/2015
Br. Inspected 6/29/15-FV52.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Lower Main Street over Sugar River, Br. #094/100 (Municipal Managed Project)
$0.00 $391,175.65 $97,793.91$488,969.56Sunapee
15836
Complete/Final Audit
9/26/2016
FY17>15 PO 4005745-1-Br. Inspected 3/31/16-FV24 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Other, Sawyers Crossing Covered Bridge, Br. #136/143 (Municipal Managed Project)
$0.00 $127,616.33 $18,944.08$146,560.41Swanzey
14196
Complete/Final Audit
1/23/2015
PO#400247-Line 1 for all phases-FV21.8 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Converse Road over Whiting Brook, Br. #110/141 (Municipal Managed Project)
$0.00 $449,830.84 $71,669.21$521,500.05Temple
24178
Complete/Final Audit
12/1/2015
Br. Inspected 7/29/15-FV47.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Old Cheshire County Rd over Spring Brook, Br. #205/098 (Municipal Managed Project)
$0.00 $375,368.57 $93,876.16$469,244.73Unity
22977
Complete/Final Audit
12/17/2014
Br. Inspected 8/8/14-FV41.0 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bartlett Loop Road over Willow Brook, Br. #177/127 (Municipal Managed Project)
$0.00 $275,908.73 $68,977.19$344,885.92Warner
27650
Complete/Final Audit
7/25/2016
Br. Inspected 12/4/15-FV40.9 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Peaslee Road over Piscataquog River, Br. #125/141 (Municipal Managed Project)
$0.00 $993,215.76 $155,856.94$1,149,072.70Weare
14339
Complete/Final Audit
3/16/2015
Br. Inspected 10/29/15-FV29.6 104 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2015 Page 3
(Page 19 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2015 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2015 Programmed Total
FY 2014 Balance $0.00 ($3,188,396.74)
$4,000,000.00 $14,800,000.00
$0.00 $14,369,536.50 $3,398,666.90
FY 2015 Appropriation
FY 2015 Funds Available $4,000,000.00 $11,611,603.26
Minus FY 2015 Programmed Total $2,665,646.00 $9,703,972.29
$1,334,354.00 $1,907,630.97Sub-total
($1,334,354.00)
$0.00
$0.00 $1,907,630.97FY 2015 Balance
$24,641,909.94
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2015.
$6,873,706.54
Number of Projects for FY 2015 By Funding Source
Funding or Managed By Tally
Federal/State/Municipal 1
State/Municipal 17
State/Municipal/Other 3
21Total Number of projects
Managed By Tally
Number of Projects for FY 2015 By Managing Lead
Force Acct DOT-Br. Maint 1
Municipality 20
21Total Number of projects
FY 2015 Page 4
(Page 20 of 46)Report Date: 9/4/2018 8:11:56 AM
With Bridge Detail
FiscalYear: 2016 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Rehabilitation, Shaker Road over Pumping Station Brook, Br. #098/062 (Force Acct DOT-Br. Maint)
$0.00 $63,944.83 $15,986.21$79,931.04Belmont
14285
Complete/Final Audit
12/21/2015
73.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, 12th Street over Androscoggin River, Br. #256/087 (Municipal Managed Project)
$0.00 $493,976.58 $123,494.15$617,470.73Berlin
15793
Complete/Awaiting Audit
Br. Inspected 8/7/14-Awaiting FV94.7 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Charcoal Road over Charcoal Brook, Br. #085/103 (Municipal Managed Project)
$0.00 $855,004.56 $213,751.15$1,123,509.21Dublin $54,753.50
15684
Complete/Final Audit
2/21/2017
Ln 1-Br. Inspected 10/13/16-FV28.6 104 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Roberts Road over Snow Brook, Br. #078/114 (Municipal Managed Project)
$0.00 $617,922.75 $154,480.69$772,403.44Eaton
15997
Complete/Final Audit
4/24/2017
FV39.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, McGaw Bridge Road over Baboosic Brook, Br. #116/137 (Municipal Managed Project)
$0.00 $1,591,131.98 $397,783.00$1,995,426.18Merrimack $6,511.20
13923
Complete/Final Audit
10/27/2017
FY12>17 per Town request-FV28.3 20 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bean Road over Baboosic Brook, Br. #072/155 (Municipal Managed Project)
$0.00 $1,213,056.78 $303,264.20$1,516,320.98Merrimack
29736
Complete/Final Audit
9/18/2017
Transdate 10-23-14-FV86.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Deerfield Road over Back Creek, Br. #102/085(New) (Municipal Managed Project)
$0.00 $75,350.94 $18,837.74$265,188.68Nottingham $171,000.00
15720
Complete/Final Audit
8/27/2015
Former culvert -FEMA-Inspection Date 8-25-10; PO #4000912-Line 2-FV86.0 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Union Road over Nubanusit River, Br. #057/108 (Municipal Managed Project)
$0.00 $1,463,626.51 $365,906.63$1,829,533.14Peterborough
14935
Complete/Final Audit
8/7/2017
FV21.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2016 Page 1
(Page 21 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2016 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2016 Programmed Total
FY 2015 Balance $0.00 $1,907,630.97
$4,000,000.00 $6,804,000.00
$0.00 $6,374,014.93 $1,593,503.77
FY 2016 Appropriation
FY 2016 Funds Available $4,000,000.00 $8,711,630.97
Minus FY 2016 Programmed Total $0.00 $4,582,972.45
$4,000,000.00 $4,128,658.52Sub-total
($4,000,000.00)
$0.00
$0.00 $4,128,658.52FY 2016 Balance
$8,199,783.40
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2016.
$232,264.70
Number of Projects for FY 2016 By Funding Source
Funding or Managed By Tally
State/Municipal 4
State/Municipal/Other 2
6Total Number of projects
Managed By Tally
Number of Projects for FY 2016 By Managing Lead
Municipality 6
6Total Number of projects
FY 2016 Page 2
(Page 22 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2017 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Morrill Hill Road over Elbow Brook, Br. #127/106 (Municipal Managed Project)
$0.00 $520,843.20 $130,210.80$651,054.00Andover
14573
Under Construction
41.0 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Wallace Road over Riddle Brook, Br. #130/117 (Municipal Managed Project)
$0.00 $223,064.42 $55,766.10$278,830.52Bedford
20000
Complete/Final Audit
8/8/2016
Br. Insp. 5/2/11-FV72.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Whittier Street over Cocheco River, Br. #111/132 (Municipal Managed Project)
$2,665,646.00 $300,000.00 $741,411.50$4,056,627.50Dover $349,570.00
15402
Under Construction
PE+ROW SAB 80/20 CON MOBRR 80/202 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Echo Valley Farm Road over Griffin Brook, Br. #156/103 (Municipal Managed Project)
$0.00 $324,821.19 $81,205.30$406,026.49EPSOM
15766
Complete/Final Audit
6/29/2018
FV47.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, String Bridge Road over Squamscott River, Br. #102/074, 103/074 (Municipal Managed Project)
$0.00 $1,022,265.60 $255,566.40$1,454,582.00Exeter $176,750.00
15399
Complete/Awaiting Audit
71.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Melendy Road over First Brook, Br. #114/083 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Hudson
13353
Complete/Final Audit
6/30/2016
Substituted with project 40940-FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Buffalo Road over Unnamed Brook, Br. #128/073(6/12/06) (Municipal Managed Project)
$0.00 $63,244.40 $15,811.10$316,222.01Rumney $237,166.51
26504
Complete/Final Audit
10/11/2017
FEMA funding-FV18.8 12 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2017 Page 1
(Page 23 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2017 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2017 Programmed Total
FY 2016 Balance $0.00 $4,128,658.52
$4,000,000.00 $6,804,000.00
$2,665,646.00 $2,454,238.81 $1,279,971.20
FY 2017 Appropriation
FY 2017 Funds Available $4,000,000.00 $10,932,658.52
Minus FY 2017 Programmed Total $0.00 $4,290,833.60
$4,000,000.00 $6,641,824.92Sub-total
($4,000,000.00)
$0.00
$0.00 $6,641,824.92FY 2017 Balance
$7,163,342.52
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2017.
$763,486.51
Number of Projects for FY 2017 By Funding Source
Funding or Managed By Tally
State/Municipal 5
5Total Number of projects
Managed By Tally
Number of Projects for FY 2017 By Managing Lead
Municipality 5
5Total Number of projects
FY 2017 Page 2
(Page 24 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2018 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Hillside Avenue over Dead River, Br. #232/066 (Municipal Managed Project)
$0.00 $593,381.23 $148,345.31$747,512.54Berlin $5,786.00
15792
Bid Stage
Totals provided by HEB-Awaiting Notice of Award55.3 C3 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Dunklee Road over Bow Bog Brook, Br. #182/113 (Municipal Managed Project)
$0.00 $384,160.00 $96,040.00$480,200.00Bow
40346
Under Design
Tran date 4/10/1545.0 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Breezy Hill Road over Massasecum River, Br. #170/129(Closed) (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Bradford
16106
Complete/Final Audit
12/9/2015
Project Cancelled15.3 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Old Route 110 over Upper Ammonoosuc River, Br. #042/043 (Municipal Managed Project)
$0.00 $1,472,040.00 $368,010.00$1,840,050.00Dummer
15815
Under Construction
46.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Belknap Mountain Road over Gunstock Brook, Br. #184/098 (Municipal Managed Project)
$0.00 $71,677.64 $17,919.41$89,597.05Gilford
15890
Complete/Final Audit
8/28/2017
Br. Inspection 4/15/11; PO #4003779-1-FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Spring Road Culvert over Mount Crescent Brook, Br. #027/112(Culvert) (Municipal Managed Project)
$0.00 $109,466.55 $35,459.45$606,304.00Gorham $461,378.00
41396
Bid Stage
Replacement of culvert-FEMA-SAB starts at PD-Awaiting AwardRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Bypassed Historic over Merrimack River (Lilac Bridge), Br. #083/150 (Municipal Managed Project)
$0.00 $700,000.00 $175,000.00$875,000.00Hooksett
29655
Under Construction
Bridge demolitionN/A BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, County Road over Second Brook, Br. #126/083 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Hudson
13354
Complete/Final Audit
Moved from FY06>FY08>10>13>16>18 Replace with new project 40940-FV49.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Central Street over First Brook, Br. #110/086 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Hudson
40940
Complete/Final Audit
Trans date 5/5/16-Project did not use SAB-FV54.3 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2018 Page 1
(Page 25 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2018 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, NH 12 over Beaver Brook, Br. #137/059 (Municipal Managed Project)
$0.00 $1,973,129.21 $493,282.30$2,466,411.51Keene
26505
Under Construction
51.9 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, NH 10 (Winchester Street) over Ash Swamp Brook, Br. #118/051 (Municipal Managed Project)
$0.00 $784,127.18 $196,031.79$980,158.97Keene
29340
Under Design
31.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, US 4 & NH 10 Over Mascoma River, Br. #120/115 (Municipal Managed Project)
$0.00 $1,103,515.66 $275,878.92$1,379,394.58Lebanon
14552
Bid Stage
76.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Oak Street over Sugar River, Br. #103/136 (Municipal Managed Project)
$1,595,421.60 $320,000.00 $478,855.40$2,394,277.00Newport
16109
Bid Stage
PE and ROW=SAB MOBRR=Con only;47.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Barton Road Bridge over Eastman Brook, Br. #092/103 (Municipal Managed Project)
$0.00 $304,548.09 $76,137.02$380,685.11Piermont
16193
Complete/Final Audit
11/26/2017
Br. Inspection 9/10/12; PO #4001792-FV88.0 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2018 Programmed Total
FY 2017 Balance $0.00 $6,641,824.92
$4,000,000.00 $13,608,000.00
$1,595,421.60 $7,816,045.56 $2,360,959.60
FY 2018 Appropriation
FY 2018 Funds Available $4,000,000.00 $20,249,824.92
Minus FY 2018 Programmed Total $0.00 $6,050,110.25
$4,000,000.00 $14,199,714.67Sub-total
($4,000,000.00)
$0.00
$0.00 $14,199,714.67FY 2018 Balance
$12,239,590.76
Federal Adjustment:Federal share used on other State bridges since State share sufficient to meet requests for aid in 2018.
$467,164.00
Number of Projects for FY 2018 By Funding Source
Funding or Managed By Tally
State/Municipal 13
State/Municipal/Other 1
14Total Number of projects
Managed By Tally
Number of Projects for FY 2018 By Managing Lead
Municipality 14
14Total Number of projects
FY 2018 Page 2
(Page 26 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2019 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Horace Greeley Road over Pulpit Brook, Br. #060/158 (Municipal Managed Project)
$0.00 $1,137,928.09 $284,482.02$1,422,410.11Amherst
20231
Under Construction
Awaiting Notice of Award54.3 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, New Boston Rd over Beaver Brook, Br. #109/090 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Amherst
20243
Complete/Final Audit
Project Canceled61.6 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Mallego Road over Mallego Brook, Br. #139/116 (Municipal Managed Project)
$0.00 $993,280.00 $142,600.00$1,241,600.00Barrington $105,720.00
41398
Under Design
45.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Drew Road over Drew Brook, Br. #167/101(New) (Municipal Managed Project)
$0.00 $241,903.09 $60,475.77$302,378.86Derry
16118
Complete/Final Audit
8/2/2018
Culvert Replaced w/Bridge; Inspected 7/22/11; FVRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, North Shore Road over Tributary I to Beaver Lake Outlet, Br. #099/129(New) (Municipal Managed Project)
$0.00 $326,962.40 $81,740.60$408,703.00Derry
41400
Under Design
Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Ossipee Lake Road over Danforth Bay Outlet, Br. #115/074 (Municipal Managed Project)
$0.00 $510,796.64 $127,699.16$638,495.80Freedom
15987
Under Design
48.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Old Lakeshore Road over Gunstock River, Br. #106/099 (Municipal Managed Project)
$0.00 $340,000.00 $85,000.00$425,000.00Gilford
21107
Under Design
21.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Stage Road over Brook, Br. #106/041 (Municipal Managed Project)
$0.00 $617,406.40 $154,351.60$771,758.00Gilmanton
16232
Under Design
40.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Stage Road over Nighthawk Hollow Brook, Br. #122/041 (Municipal Managed Project)
$0.00 $1,398,988.00 $349,747.00$1,748,735.00Gilmanton
16233
Under Design
50.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, South Road over Minnewawa Brook, Br. #061/060 (Municipal Managed Project)
$0.00 $630,079.60 $157,519.90$787,599.50Harrisville
16114
Bid Stage
38.5 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2019 Page 1
(Page 27 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2019 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Clark Pond Road over Clark Brook, Br. #147/109(Closed) (Municipal Managed Project)
$0.00 $138,000.00 $34,500.00$690,000.00Haverhill $517,500.00
41724
Under Negotiations
Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Valley Cross Road over Wildcat Brook, Br. #153/066 (Municipal Managed Project)
$0.00 $692,800.00 $173,200.00$866,000.00Jackson
40808
Under Negotiations
52.4 12 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Roxbury Street over Beaver Brook, Br. #140/077 (Municipal Managed Project)
$0.00 $663,200.00 $165,800.00$829,000.00Keene
15854
Under Design
18.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, NH 12A over BMRR, Br. #062/117 (Municipal Managed Project)
$6,144,000.00 $28,000.00 $1,543,000.00$7,715,000.00Lebanon
13558A
Under Design
MOBRR and SABRemarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Goffs Falls Road over B&MRR, Br. #188/092(func obsol) (Municipal Managed Project)
$0.00 $1,380,000.00 $345,000.00$1,725,000.00Manchester
15401
Under Design
FY201852.5 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bedford Road over Baboosic Brook, Br. #113/159 (Municipal Managed Project)
$0.00 $3,707,352.80 $926,838.20$4,634,191.00Merrimack
15841
Bid Stage
88 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Sand Hill Road over Brook, Br. #154/129 (Municipal Managed Project)
$0.00 $80,000.00 $20,000.00$100,000.00Newport
20006
43.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bow Lake Road over Shelburne Brook, Br. #095/113 (Municipal Managed Project)
$0.00 $484,800.00 $121,200.00$606,000.00Northwood
41397
Under Design
26.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Shaw Road over Kelly Brook, Br. #089/135 (Municipal Managed Project)
$0.00 $468,240.00 $117,060.00$585,300.00Pittsfield
14972
Under Design
75.5 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Westville Road over Little River, Br. #122/072 (Municipal Managed Project)
$0.00 $822,449.10 $205,612.27$1,108,061.37Plaistow $80,000.00
23117
Bid Stage
71.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2019 Page 2
(Page 28 of 46)Report Date: 9/4/2018 8:11:57 AM
With Bridge Detail
FiscalYear: 2019 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, South Policy Street over Porcupine Brook, Br. #083/062 (Municipal Managed Project)
$0.00 $512,571.19 $128,142.80$748,149.66Salem $107,435.67
15989
Complete/Final Audit
8/2/2018
Br. Inspected 2/14/12- FV36.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Quaker Whiteface Road over Whiteface River, Br. #203/138 (Municipal Managed Project)
$0.00 $434,169.60 $108,542.40$542,712.00Sandwich
16014
Bid Stage
PO #400379337.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Huckins Road over Brook, Br. #125/090 (Municipal Managed Project)
$0.00 $244,000.00 $61,000.00$305,000.00Strafford
14790
97.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Rabbitt Hollow Road over Perry Brook, Br. #120/072
$0.00 $530,800.00 $132,700.00$663,500.00Swanzey
41696
Awaiting Town Action
85.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Covered Bridge Road over Mill Brook, Br. #183/107 (Municipal Managed Project)
$0.00 $540,784.80 $135,196.20$675,981.00Thornton
15938
Under Construction
43.5 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Hazen Road over Johns River, Br. #159/098 (Municipal Managed Project)
$0.00 $140,000.00 $35,000.00$175,000.00Whitefield
16025
40.5 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, King Brook Road over King Brook, Br. #074/060 (Municipal Managed Project)
$0.00 $240,000.00 $60,000.00$300,000.00Wilton
15767
Under Design
41.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Castle Hill Road over Beaver Brook, Br. #057/051 (Municipal Managed Project)
$0.00 $640,000.00 $160,000.00$800,000.00Windham
41632
Under Design
38.8 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Pleasant Valley Road over Heath Brook, Br. #116/072 (Municipal Managed Project)
$0.00 $885,345.60 $221,336.40$1,106,682.00Wolfeboro
40617
Bid Stage
38.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2019 Page 3
(Page 29 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2019 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2019 Programmed Total
FY 2018 Balance $0.00 $14,199,714.67
$4,000,000.00 $6,804,000.00
$6,144,000.00 $18,829,857.31 $6,137,744.32
FY 2019 Appropriation
FY 2019 Funds Available $4,000,000.00 $21,003,714.67
Minus FY 2019 Programmed Total $4,680,000.00 $19,778,839.73
($680,000.00) $1,224,874.94Sub-total
$0.00
$0.00
($680,000.00) $1,224,874.94FY 2019 Balance
$31,922,257.30
Federal Adjustment:Exceeded Appropriation, Balance Forward to 2020.
$810,655.67
Number of Projects for FY 2019 By Funding Source
Funding or Managed By Tally
Federal/State/Municipal 1
State/Municipal 29
State/Municipal/Other 1
31Total Number of projects
Managed By Tally
Number of Projects for FY 2019 By Managing Lead
Municipality 30
Not Applicable to Date 1
31Total Number of projects
FY 2019 Page 4
(Page 30 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2020 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, West Street over Great Brook, Br. #173/075 (Municipal Managed Project)
$0.00 $717,879.60 $179,469.90$906,670.50Antrim $9,321.00
29468
Under Construction
44.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Hannah Nutter Road over Big River, Br. #149/073 (Municipal Managed Project)
$0.00 $815,280.00 $203,820.00$1,019,100.00Barnstead
16020
Under Design
81.9 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Cider Mill Road over McQuade Brook, Br. #079/128 (Municipal Managed Project)
$0.00 $543,507.20 $135,876.80$679,384.00Bedford
21193
Under Construction
MJ Estimate64.5 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Catesby Lane over McQuade Brook, Br. #102/098(New) (Municipal Managed Project)
$0.00 $480,000.00 $120,000.00$600,000.00Bedford
21684
Under Negotiations
Culvert replacementRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Church Street over Tioga River, Br. #103/072 (Municipal Managed Project)
$0.00 $97,600.00 $24,400.00$122,000.00Belmont
22872
Awaiting Town Action
Town Repair Bridge/Town will replace in 202068.3 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Potato Road over Indian River, Br. #147/055 (Municipal Managed Project)
$0.00 $496,000.00 $124,000.00$620,000.00Canaan
41399
Under Design
48.8 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, North Pembroke Road over Soucook River, Br. #183/156(J-Owned) (Municipal Managed Project)
$0.00 $520,000.00 $130,000.00$650,000.00Concord
14841A
Under Design
Concord-Pembroke Project55.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Hooksett Turnpike over Bela Brook, Br. #200/015 (Municipal Managed Project)
$0.00 $496,000.00 $124,000.00$620,000.00Concord
15877
Under Design
30.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Birchdale Road over Bela Brook, Br. #193/027 (Municipal Managed Project)
$0.00 $496,000.00 $124,000.00$620,000.00Concord
15878
60.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, So. New Boston Road over So. Br. Piscataquog River, Br. #149/058 (Municipal Managed Project)
$0.00 $1,069,600.00 $267,400.00$1,337,000.00Francestown
15765
Under Design
FY 2016>2047.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2020 Page 1
(Page 31 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2020 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Crystal Lake Road over Nelson Brook, Br. #174/094 (Municipal Managed Project)
$0.00 $1,257,600.00 $314,400.00$1,572,000.00Gilmanton
16234
Under Design
50.8 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Bunker Hill Road over Needle Shop Brook, Br. #140/099 (Municipal Managed Project)
$0.00 $265,000.00 $70,000.00$335,000.00Hill
41661
Under Negotiations
58.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Academy Street over Durkee Brook, Br. #121/037 (Municipal Managed Project)
$0.00 $540,000.00 $135,000.00$675,000.00Laconia
26706
Under Negotiations
37.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Townhouse Road over Northeast Pond, Br. #168/152 (Municipal Managed Project)
$0.00 $560,000.00 $140,000.00$1,400,000.00Milton $700,000.00
40658
Under Negotiations
Owned by Milton, NH and ME DOT, NHDOT managing9.1 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Coon Brook Road over South Branch Sugar River, Br. #147/036 (Municipal Managed Project)
$0.00 $471,135.20 $117,783.80$588,919.00Newport
29763
Under Construction
Substituted w/ #14969-Awaiting Notice of Award73.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Main Street over Contoocook River, Br. #092/089 (Municipal Managed Project)
$4,000,000.00 $501,600.00 $1,125,400.00$5,627,000.00Peterborough
14933
Under Design
Also see #14772A15.0 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Wellington Road over Converseville Brook, Br. #154/069 (Municipal Managed Project)
$0.00 $584,000.00 $146,000.00$730,000.00Rindge
22652
In Process
69.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bluff Street Extension over Widow Harris Brook, Br. #116/116 (Municipal Managed Project)
$0.00 $646,724.00 $161,681.00$808,405.00Salem
20228
Bid Stage
PO#400360638.4 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bluff Street over Hittytity Brook, Br. #094/119 (Municipal Managed Project)
$0.00 $83,035.90 $20,758.98$103,794.88Salem
20229
Complete/Final Audit
5/8/2014
Only paying PE. Received Form 4 and Mylars-FV45.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Frescoln Road over Rocky Branch, Br. #108/070 (Municipal Managed Project)
$0.00 $616,000.00 $154,000.00$770,000.00Wentworth
40648
59.5 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2020 Page 2
(Page 32 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2020 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2020 Programmed Total
FY 2019 Balance ($4,004,988.00) $1,224,874.94
$4,000,000.00 $6,804,000.00
$4,000,000.00 $11,256,961.90 $3,817,990.48
FY 2020 Appropriation
FY 2020 Funds Available ($4,988.00) $8,028,874.94
Minus FY 2020 Programmed Total $0.00 $6,072,835.90
($4,988.00) $1,956,039.04Sub-total
$0.00
$0.00
($4,988.00) $1,956,039.04FY 2020 Balance
$19,784,273.38
Federal Adjustment:Exceeded Appropriation, Balance Forward to 2021.
$709,321.00
Number of Projects for FY 2020 By Funding Source
Funding or Managed By Tally
State/Municipal 10
State/Municipal/Other 1
11Total Number of projects
Managed By Tally
Number of Projects for FY 2020 By Managing Lead
Municipality 11
11Total Number of projects
FY 2020 Page 3
(Page 33 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2021 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Rehabilitation, Hill Road over Darby Brook, Br. #059/134 (Municipal Managed Project)
$0.00 $184,000.00 $46,000.00$230,000.00Alstead
40649
27.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Drewsville Road over Darby Brook, Br. #058/132 (Municipal Managed Project)
$0.00 $136,000.00 $34,000.00$170,000.00Alstead
40650
Under Negotiations
72.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Jenkins Road over McQuade Brook, Br. #136/066(New) (Municipal Managed Project)
$0.00 $117,479.82 $29,369.95$146,849.77Bedford
21685
Complete/Final Audit
12/4/2013
Culvert replacement - Br. Inspection 1/15/2013Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Harvey Swell Road over East Branch, Br. #190/109 (Municipal Managed Project)
$0.00 $177,549.60 $44,387.40$221,937.00Colebrook
40651
Under Design
69.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Bear Rock Road over West Branch Mohawk River, Br. #167/120 (Municipal Managed Project)
$0.00 $457,573.60 $114,393.40$571,967.00Colebrook
40652
Under Design
40.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Province Road over South Branch of Baker River, Br. #156/053(New) (Municipal Managed Project)
$0.00 $184,000.00 $46,000.00$920,000.00Dorchester $690,000.00
42092
New BridgeRemarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Martin Road over Piscassic River, Br. #155/133 (Municipal Managed Project)
$0.00 $416,000.00 $104,000.00$520,000.00Fremont
23793
Under Design
Transdate 7/6/201116.1 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Nutting Road over Contoocook River, Br. #159/094 (Municipal Managed Project)
$0.00 $540,000.00 $135,000.00$675,000.00Jaffrey
41401
Under Negotiations
46.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Nute Road over Bellamy River, Br. #056/072 (Municipal Managed Project)
$0.00 $592,000.00 $148,000.00$740,000.00Madbury
24226
Under Design
38.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Ramp E (Canal St) over BMRR, Br. #107/071 (Municipal Managed Project)
$0.00 $340,000.00 $85,000.00$425,000.00Manchester
24211
Transdate9/11/1274 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2021 Page 1
(Page 34 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2021 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Rehabilitation, Salmon Street EB over RD, BMRR, Merrimack River Ramp-Amoskeag Bridge, Br. #107/072 (Municipal Managed Project)
$0.00 $508,000.00 $127,000.00$635,000.00Manchester
24212
Under Negotiations
Transdate 9/11/1267.6 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Queen City Bridge (US 3, NH 3A) over I-293, BMRR, Merrimack River, Br. #151/065 (Municipal Managed Project)
$4,680,000.00 $520,000.00 $1,300,000.00$6,500,000.00Manchester
28336
Under Design
MOBRR Funded 80% Fed 20% City73.8 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Archertown Road over Jacobs Brook, Br. #080/120 (Municipal Managed Project)
$0.00 $992,000.00 $248,000.00$1,240,000.00Orford
41151
Under Design
49.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Shannon Road over Providence Hill Brook, Br. #122/160 (Municipal Managed Project)
$0.00 $91,517.86 $22,879.46$114,397.32Salem
26486
Complete/Final Audit
5/28/2014
Br. Inspected 10/30/14-FV66.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Christian Hill Road over NHRR, Br. #098/122 (Municipal Managed Project)
$0.00 $1,280,000.00 $320,000.00$1,600,000.00Swanzey
41403
16.0 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Stage Coach Road over Burton Pond Outlet, Br. #086/142 (Municipal Managed Project)
$0.00 $171,600.00 $42,900.00$214,500.00Wilton
26201
29.2 03P Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2021 Page 2
(Page 35 of 46)Report Date: 9/4/2018 8:11:58 AM
With Bridge Detail
FiscalYear: 2021 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2021 Programmed Total
FY 2020 Balance ($4,988.00) $1,956,039.04
$4,000,000.00 $6,804,000.00
$4,680,000.00 $6,707,720.88 $2,846,930.21
FY 2021 Appropriation
FY 2021 Funds Available $3,995,012.00 $8,760,039.04
Minus FY 2021 Programmed Total $0.00 $6,628,203.02
$3,995,012.00 $2,131,836.02Sub-total
$0.00
$0.00
$3,995,012.00 $2,131,836.02FY 2021 Balance
$14,924,651.09 $690,000.00
Number of Projects for FY 2021 By Funding Source
Funding or Managed By Tally
State/Municipal 14
State/Municipal/Other 1
15Total Number of projects
Managed By Tally
Number of Projects for FY 2021 By Managing Lead
Municipality 14
Not Applicable to Date 1
15Total Number of projects
FY 2021 Page 3
(Page 36 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2022 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Comstock Road over Darby Brook, Br. #046/141 (Municipal Managed Project)
$0.00 $744,000.00 $186,000.00$930,000.00Alstead
40661
52.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Mont Vernon Rd over Ceasars Brook, Br. #112/071 (Municipal Managed Project)
$0.00 $732,000.00 $183,000.00$915,000.00Amherst
40654
Under Design
86.0 NPR Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Craig Road over Brook, Br. #117/093 (Municipal Managed Project)
$0.00 $176,000.00 $44,000.00$220,000.00Antrim
14942
Under Negotiations
FY13>14>2249.9 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Griffin Mill Road over Maple Falls Brook, Br. #095/127 (Municipal Managed Project)
$0.00 $240,000.00 $60,000.00$300,000.00Auburn
29316
Under Negotiations
20.5 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Greenhill Rd over Isinglass River, Br. #109/162 (Municipal Managed Project)
$0.00 $1,597,821.60 $399,455.40$1,997,277.00Barrington
26722
Under Design
69.1 C2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Beals Road over Baboosic Brook, Br. #105/055 (Municipal Managed Project)
$0.00 $672,908.92 $168,227.23$841,136.15Bedford
24217
Under Design
Need design exception letter35.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Lashua Road over Macoma River, Br. #122/136 (Municipal Managed Project)
$0.00 $0.00 $0.00$0.00Canaan
26703
Transdate 4/26/13-Replaced with new project23.90 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Clark Pond Road over Clark Pond Brook, Br. #101/152 (Municipal Managed Project)
$0.00 $285,444.00 $71,361.00$356,805.00Canaan
26704
Transdate 4/26/13Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Pleasant Street over Mohawk River, Br. #050/099 (Municipal Managed Project)
$0.00 $320,000.00 $80,000.00$400,000.00Colebrook
40655
88.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Province Road over Bucks Brook, Br. #151/055 (Municipal Managed Project)
$0.00 $136,000.00 $34,000.00$680,000.00Dorchester $510,000.00
42091
FEMA55.4 06 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2022 Page 1
(Page 37 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2022 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, George Street over Beaver Brook, Br. #142/092 (Municipal Managed Project)
$0.00 $552,000.00 $138,000.00$690,000.00Keene
40653
Under Negotiations
26.6 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Court Street over Durkee Brook, Br. #113/036 (Municipal Managed Project)
$0.00 $640,000.00 $160,000.00$800,000.00Laconia
40656
Under Design
53.1 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Trues Brook Road over Bloods Brook, Br. #066/059 (Municipal Managed Project)
$0.00 $1,035,931.80 $258,982.95$1,294,914.75Lebanon
24221
Under Design
31 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Old Bridge Street over Beaver Brook, Br. #109/081 (Municipal Managed Project)
$0.00 $756,000.00 $189,000.00$945,000.00Pelham
29450
Under Design
37.7 10 Remarks:Red List: FSR: WT: No Outlet: NoYes
Repair/Replacement of Bridge, Tully Brook Road over Tully Brook, Br. #155/066 (Municipal Managed Project)
$0.00 $520,000.00 $130,000.00$650,000.00Richmond
29056
Once we receive est. from Br. Design, send est. to Town-Sent to BD 2/27/1476.63 15 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Buffalo Road over Brook, Br. #093/082 (Municipal Managed Project)
$0.00 $360,000.00 $90,000.00$450,000.00Rumney
27162
52.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Crane Hill Road over Gale River, Br. #202/128 (Municipal Managed Project)
$0.00 $692,000.00 $173,000.00$865,000.00Sugar Hill
24218
Under Design
Estimated FY12 Update Est. 3/22/1234.5 6 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2022 Page 2
(Page 38 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2022 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2022 Programmed Total
FY 2021 Balance $0.00 $2,131,836.02
$4,000,000.00 $6,804,000.00
$0.00 $9,460,106.32 $2,365,026.58
FY 2022 Appropriation
FY 2022 Funds Available $4,000,000.00 $8,935,836.02
Minus FY 2022 Programmed Total $0.00 $9,460,106.32
$4,000,000.00 ($524,270.30)Sub-total
$0.00
$0.00
$4,000,000.00 ($524,270.30)FY 2022 Balance
$12,335,132.90 $510,000.00
Number of Projects for FY 2022 By Funding Source
Funding or Managed By Tally
State/Municipal 16
State/Municipal/Other 1
17Total Number of projects
Managed By Tally
Number of Projects for FY 2022 By Managing Lead
Municipality 17
17Total Number of projects
FY 2022 Page 3
(Page 39 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2023 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Thornton Ferry Rd over Beaver Brook, Br. #145/106 (Municipal Managed Project)
$0.00 $1,320,000.00 $330,000.00$1,650,000.00Amherst
40657
Under Design
85.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Grist Mill Hill Road over Indian River, Br. #172/070 (Municipal Managed Project)
$0.00 $400,000.00 $100,000.00$500,000.00Canaan
41406
Under Design
71.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Washington Street over Swift River, Br. #164/063 (Municipal Managed Project)
$0.00 $1,360,000.00 $340,000.00$1,700,000.00Conway
41402
94.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Potter Road over Snow Brook, Br. #058/130 (Municipal Managed Project)
$0.00 $498,784.00 $124,696.00$623,480.00Eaton
41404
Under Design
Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, NH 120 Parking Lot, ped over NHRR(ABD), Br. #121/117 (Municipal Managed Project)
$0.00 $897,280.00 $224,320.00$1,121,600.00Lebanon
24222
66.1 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, US 3 over Baboosic Brook, Br. #118/135 (Municipal Managed Project)
$0.00 $2,656,000.00 $664,000.00$3,320,000.00Merrimack
29174
Under Negotiations
50.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Tucker Mill Road over Mid Br Piscataquog River, Br. #087/150 (Municipal Managed Project)
$0.00 $460,000.00 $115,000.00$575,000.00New Boston
15505
FY 2013>2389 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Clothespin Bridge Road over Blackwater River, Br. #121/103 (Municipal Managed Project)
$0.00 $1,476,000.00 $369,000.00$1,845,000.00Webster
40810
Under Negotiations
41.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2023 Page 1
(Page 40 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2023 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2023 Programmed Total
FY 2022 Balance $0.00 ($524,270.30)
$4,000,000.00 $6,804,000.00
$0.00 $9,068,064.00 $2,267,016.00
FY 2023 Appropriation
FY 2023 Funds Available $4,000,000.00 $6,279,729.70
Minus FY 2023 Programmed Total $0.00 $9,068,064.00
$4,000,000.00 ($2,788,334.30)Sub-total
$0.00
$0.00
$4,000,000.00 ($2,788,334.30)FY 2023 Balance
$11,335,080.00
Number of Projects for FY 2023 By Funding Source
Funding or Managed By Tally
State/Municipal 8
8Total Number of projects
Managed By Tally
Number of Projects for FY 2023 By Managing Lead
Municipality 8
8Total Number of projects
FY 2023 Page 2
(Page 41 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2024 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Lawrence Road over Blackwater River, Br. #098/093 (Municipal Managed Project)
$0.00 $1,948,000.00 $487,000.00$2,435,000.00Andover
41407
Under Design
47.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Bond Street over Nissitissit River, Br. #088/074 (Municipal Managed Project)
$0.00 $352,000.00 $88,000.00$440,000.00Brookline
41408
Under Negotiations
71.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, Mount Orne Road over Connecticut River; Mount Orne Covered Bridge, Br. #039/105 (Municipal Managed Project)
$0.00 $240,000.00 $60,000.00$300,000.00Lancaster
22192
Under Construction
Completed repairs in March 20122.0 BRC Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Freshet Road over Johnson Creek, Br. #160/086 (Municipal Managed Project)
$0.00 $480,000.00 $120,000.00$600,000.00Madbury
41462
Under Negotiations
73.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Rehabilitation, Salmon Street WB over RD, BMRR, Merrimack River-Amoskeag Bridge, Br. #106/072 (Municipal Managed Project)
$0.00 $420,000.00 $105,000.00$525,000.00Manchester
24206
Transdate9/11/201267.2 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Brooklyn Street over Roaring Brook, Br. #108/114(Closed) (Municipal Managed Project)
$0.00 $126,055.55 $31,513.89$157,569.44Northumberland
14234
Complete/Final Audit
4/4/2017
Project cancelled-did not move forward with construction-FV37 BRC Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Lull Road over Peacock Brook, Br. #082/045 (Municipal Managed Project)
$0.00 $236,000.00 $59,000.00$295,000.00Weare
14338
Under Design
54.2 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2024 Page 1
(Page 42 of 46)Report Date: 9/4/2018 8:11:59 AM
With Bridge Detail
FiscalYear: 2024 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
FY 2024 Programmed Total
FY 2023 Balance $0.00 ($2,788,334.30)
$0.00 $0.00
$0.00 $3,802,055.55 $950,513.89
FY 2024 Appropriation
FY 2024 Funds Available $0.00 ($2,788,334.30)
Minus FY 2024 Programmed Total $0.00 $4,204,380.80
$0.00 ($6,992,715.10)Sub-total
$0.00
$0.00
$0.00 ($6,992,715.10)FY 2024 Balance
$4,752,569.44
Number of Projects for FY 2024 By Funding Source
Funding or Managed By Tally
State/Municipal 7
7Total Number of projects
Managed By Tally
Number of Projects for FY 2024 By Managing Lead
Municipality 7
7Total Number of projects
FY 2024 Page 2
(Page 43 of 46)Report Date: 9/4/2018 8:12:00 AM
With Bridge Detail
FiscalYear: 2025 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Old Canaan Road over Spruce Brook, Br. #052/059(New) (Municipal Managed Project)
$0.00 $528,380.80 $132,095.20$660,476.00Barrington
41410
Under Negotiations
Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Page Road over Bela Brook, Br. #065/140 (Municipal Managed Project)
$0.00 $628,000.00 $157,000.00$785,000.00Bow
24223
Bid Stage
52.5 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Birchdale Road over White Brook, Br. #092/136 (Municipal Managed Project)
$0.00 $686,442.80 $171,610.70$858,053.50Bow
24225
Under Construction
69.7 E2 Remarks:Red List: FSR: WT: No Outlet: NoYes
Bridge Replacement, Center Street over Harry Brook, Br. #129/116 (Municipal Managed Project)
$0.00 $636,000.00 $159,000.00$795,000.00Goffstown
41597
84.9 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Old County Farm Road over Blood Brook, Br. #060/118 (Municipal Managed Project)
$0.00 $176,000.00 $44,000.00$220,000.00Wilton
15768
Sent to Bridge Design 5/3/165.3 03F Remarks:Red List: FSR: WT: No Outlet: NoYes
FY 2025 Programmed Total
FY 2024 Balance $0.00 ($6,992,715.10)
$0.00 $0.00
$0.00 $2,654,823.60 $663,705.90
FY 2025 Appropriation
FY 2025 Funds Available $0.00 ($6,992,715.10)
Minus FY 2025 Programmed Total $0.00 $176,000.00
$0.00 ($7,168,715.10)Sub-total
$0.00
$0.00
$0.00 ($7,168,715.10)FY 2025 Balance
$3,318,529.50
Number of Projects for FY 2025 By Funding Source
Funding or Managed By Tally
State/Municipal 1
1Total Number of projects
Managed By Tally
Number of Projects for FY 2025 By Managing Lead
Municipality 1
1Total Number of projects
FY 2025 Page 1
(Page 44 of 46)Report Date: 9/4/2018 8:12:00 AM
With Bridge Detail
FiscalYear: 2026 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, River Road over Bow Bog Brook, Br. #184/127 (Municipal Managed Project)
$0.00 $728,240.00 $182,060.00$910,300.00Bow
24224
Under Design
96.8 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Phase I & II: Shaker Blvd over Knox River, Br. #120/115 (Municipal Managed Project)
$0.00 $240,000.00 $60,000.00$300,000.00Enfield
13592
Moved from FY02>04>08>10>11>12>2631.8 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Rehabilitation, US 3 (Elm Street) over B&MRR, Br. #144/075 (Municipal Managed Project)
$0.00 $640,000.00 $160,000.00$800,000.00Manchester
15837
63.2 NPR Remarks:Red List: FSR: WT: No Outlet: NoNo
Bridge Replacement, Gregg Mill Road over South Branch Piscataquog River, Br. #132/138 (Municipal Managed Project)
$0.00 $620,000.00 $155,000.00$775,000.00New Boston
14771
FY 2012>14>2662.4 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2026 Programmed Total
FY 2025 Balance $0.00 ($7,168,715.10)
$0.00 $0.00
$0.00 $2,228,240.00 $557,060.00
FY 2026 Appropriation
FY 2026 Funds Available $0.00 ($7,168,715.10)
Minus FY 2026 Programmed Total $0.00 $2,228,240.00
$0.00 ($9,396,955.10)Sub-total
$0.00
$0.00
$0.00 ($9,396,955.10)FY 2026 Balance
$2,785,300.00
Number of Projects for FY 2026 By Funding Source
Funding or Managed By Tally
State/Municipal 4
4Total Number of projects
Managed By Tally
Number of Projects for FY 2026 By Managing Lead
Municipality 4
4Total Number of projects
FY 2026 Page 1
(Page 45 of 46)Report Date: 9/4/2018 8:12:00 AM
With Bridge Detail
FiscalYear: 2027 Projects Authorized for Construction
Project Name/Num.
Description / Improvement CurrentEstimate
FederalShare
StateShare
Town / City Share
ClosedProjects
OtherShare
Status /Completion Date
Bridge Replacement, Hartshorn Road over Hartshorn Brook, Br. #102/165
$0.00 $532,000.00 $133,000.00$665,000.00Milford
42087
Under Negotiations
97.0 E2 Remarks:Red List: FSR: WT: No Outlet: NoNo
FY 2027 Programmed Total
FY 2026 Balance $0.00 ($9,396,955.10)
$0.00 $0.00
$0.00 $532,000.00 $133,000.00
FY 2027 Appropriation
FY 2027 Funds Available $0.00 ($9,396,955.10)
Minus FY 2027 Programmed Total $0.00 $0.00
$0.00 ($9,396,955.10)Sub-total
$0.00
$0.00
$0.00 ($9,396,955.10)FY 2027 Balance
$665,000.00
FY 2027 Page 1
(Page 46 of 46)Report Date: 9/4/2018 8:12:00 AM
With Bridge Detail
Bridge Estimates Issued to Municipalities - Awaiting Town Action to Raise Funds and Request Construction Aid 152 Projects Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Grout Hill Road over Cold River, Br. #147/067
Acworth $0.00 $480,000.00 $120,000.00$600,000.002 Projects
2/24/2005
Bridge Replacement, Allen Road over Cold River, Br. #164/114
$0.00 $900,000.00 $225,000.00$1,125,000.005/26/2017
Bridge Replacement, Drake Hill Road over Meadow Brook, Br. #213/094
Albany $0.00 $603,200.00 $150,800.00$754,000.001 Project
7/1/2023
Bridge Replacement, Brock Road over Brock Brook, Br. #100/116
Alexandria $0.00 $280,000.00 $70,000.00$350,000.001 Project
8/7/2002
Bridge Replacement, Hill Road over Bradley Brook, Br. #104/078
Andover $0.00 $196,000.00 $49,000.00$245,000.005 Projects
7/30/1996
Bridge Rehabilitation, Last Street over Sucker Brook, Br. #216/139
$0.00 $116,000.00 $29,000.00$145,000.007/30/1996
Bridge Replacement, Hoyt Road over Sucker Brook, Br. #197/146(Closed)
$0.00 $120,000.00 $30,000.00$150,000.007/30/1996
Repair/Replacement of Bridge, Tucker Mountain Road over Sucker Brook, Br. #180/147
$0.00 $140,000.00 $35,000.00$175,000.007/30/1996
Bridge Replacement, Taunton Hill Road over Mountain Brook, Br. #125/129
$0.00 $180,000.00 $45,000.00$225,000.007/30/1996
Bridge Replacement, Auburn-Preston Brook Culvert on Raymond Road, Br. #118/136(New)
Auburn $0.00 $196,000.00 $49,000.00$245,000.001 Project
3/19/1998
22872
Bridge Replacement, Church Street over Tioga River, Br. #103/072(Municipal Managed Project)
Belmont
1 Project
7/1/2019
Page 1 of 11Printed: 9/4/2018 8:14:01 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Johnson Hill Road over West Branch Brook, Br. #104/141
Bradford $0.00 $260,000.00 $65,000.00$325,000.004 Projects
9/14/2004
Bridge Replacement, Blaisdell Lake Road over stream, Br. #168/165, 168/162
$0.00 $344,000.00 $86,000.00$430,000.009/14/2004
Bridge Replacement, West (Meadow) Road over Hoyt Brook, Br. #098/117
$0.00 $240,000.00 $60,000.00$300,000.006/23/2009
Bridge Replacement, Water Street over West Branch Brook, Br. #126/150
$0.00 $704,000.00 $176,000.00$880,000.005/26/2017
Bridge Replacement, Dupaw Gould Road over Lancy Brook, Br. #065/085
Brookline $0.00 $896,000.00 $224,000.00$1,120,000.001 Project
5/26/2017
Bridge Replacement, Miclon Road over Conner Brook, Br. #112/116
Campton $0.00 $276,000.00 $69,000.00$345,000.002 Projects
7/20/2000
Bridge Replacement, Miclon Road over Conner Brook, Br. #114/121
$0.00 $296,000.00 $74,000.00$370,000.007/20/2000
Repair/Replacement of Bridge, Transfer Station Road over Orange Brook, Br. #191/080
Canaan $0.00 $452,000.00 $113,000.00$565,000.001 Project
7/1/2020
Bridge Replacement, Chestnut Flat Road over Little Sugar River, Br. #071/115(CLOSED)
Charlestown $0.00 $420,000.00 $105,000.00$525,000.001 Project
11/17/1998
Bridge Rehabilitation, Plains Road over Sugar River, Br. #091/118
Claremont $0.00 $508,000.00 $127,000.00$635,000.002 Projects
5/26/2017
Bridge Replacement, Myrtle Street over Concord-Claremont R W, Br. #123/090
$0.00 $916,000.00 $229,000.00$1,145,000.005/31/2017
Bridge Replacement, Little Blakely Road over Mohawk River, Br. #125/069
Colebrook $0.00 $332,000.00 $83,000.00$415,000.001 Project
12/4/2002
Repair/Replacement of Bridge, Bungy Road over East Branch Summers Stream, Br. #228/109
Columbia $0.00 $220,000.00 $55,000.00$275,000.002 Projects
11/30/1999
Repair/Replacement of Bridge, Meriden Hill Road over Lyman Brook, Br. #054/032
$0.00 $508,000.00 $127,000.00$635,000.009/18/2013
Bridge Replacement, Clark Camp Road over Mill Brook, Br. #151/122
Cornish $0.00 $280,000.00 $70,000.00$350,000.001 Project
10/8/2008
Page 2 of 11Printed: 9/4/2018 8:14:02 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Hurlburt Road over Brook, Br. #125/130
Dalton $0.00 $260,000.00 $65,000.00$325,000.001 Project
10/18/2011
Bridge Replacement, Phase II: Forbes Mountain Road over Wild Meadow Brook, Br. #103/100
Danbury $0.00 $700,000.00 $175,000.00$875,000.001 Project
5/30/2006
Repair/Replacement of Bridge, NH 28 (Rockingham Road) over Tributary G to Beaver Brook, Br. #078/090(New)
Derry $0.00 $548,000.00 $137,000.00$685,000.003 Projects
8/24/2012
Bridge Replacement, North High Street over Shields Brook, Br. #053/110(New)
$0.00 $588,000.00 $147,000.00$735,000.008/24/2012
Bridge Replacement, North Shore Road over Taylor Brook, Br. #163/080(New)
$0.00 $390,701.60 $97,675.40$488,377.007/1/2017
Bridge Replacement, Durham Point Road over Crommet Creek, Br. #150/065
Durham $0.00 $684,000.00 $171,000.00$855,000.001 Project
10/14/2003
Bridge Rehabilitation, Granite Road over South River, Br. #166/082
Effingham $0.00 $480,000.00 $120,000.00$600,000.002 Projects
6/25/2008
Bridge Replacement, Stevens Road over Brook, Br. #181/072
$0.00 $336,000.00 $84,000.00$420,000.006/25/2008
Bridge Replacement, Boy's Camp Road over Bicknell Brook, Br. #172/112
Enfield $0.00 $640,000.00 $160,000.00$800,000.001 Project
12/9/2004
Repair/Replacement of Bridge, Main Street over Lamprey River, Br. #109/055
Epping $0.00 $520,000.00 $130,000.00$650,000.002 Projects
7/1/2010
Bridge Replacement, Blake Road over Lamprey River, Br. #059/054
$0.00 $844,000.00 $211,000.00$1,055,000.007/6/2010
Bridge Replacement, Cass Road over Little Suncook River, Br. #128/120, 128/121
Epsom $0.00 $524,000.00 $131,000.00$655,000.002 Projects
5/9/2002
Bridge Replacement, River Road over Deer Brook, Br. #065/072
$0.00 $460,000.00 $115,000.00$575,000.0011/10/2010
Bridge Rehabilitation, Phase II: Templeton Turnpike over Priest Brook, Br. #147/054
Fitzwilliam $0.00 $276,000.00 $69,000.00$345,000.001 Project
6/30/2003
Page 3 of 11Printed: 9/4/2018 8:14:02 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Old County Road over Collins Brook, Br. #091/142
Francestown $0.00 $740,000.00 $185,000.00$925,000.001 Project
5/30/2017
Bridge Rehabilitation, Scribner Road over Exeter River, Br. #106/076
Fremont $0.00 $468,000.00 $117,000.00$585,000.001 Project
7/6/2011
Bridge Replacement, MummeryRoad East over Cold Brook, Br. #083/090
Goshen $0.00 $528,000.00 $132,000.00$660,000.001 Project
5/30/2017
Bridge Rehabilitation, Wild Meadows Road over Brook, Br. #210/107(Municipal Managed Project)
Grafton $0.00 $368,000.00 $92,000.00$460,000.001 Project
10/26/2011
Bridge Replacement, Olde Farm Road over Skinner Brook, Br. #107/113
Grantham $0.00 $796,000.00 $199,000.00$995,000.004 Projects
7/30/2008
Bridge Replacement, Olde Farms Road over Sawyer Brook, Br. #083/108
$516,000.00 $0.00 $129,000.00$645,000.007/30/2008
Bridge Rehabilitation, Miller Pond Rd/Skinner Brook, Br. #105/128
$0.00 $96,000.00 $24,000.00$120,000.007/30/2008
Bridge Replacement, Frye Lane over Stony Brook, Br. #108/147
$0.00 $320,000.00 $80,000.00$400,000.007/6/2010
Repair/Replacement of Bridge, Wilton Road over Souhegan River, Br. #075/114
Greenville $0.00 $2,576,000.00 $644,000.00$3,220,000.001 Project
7/17/2013
Bridge Replacement, Old Stage Road over Taylor River, Br. #086/123(CLOSED)
Hampton $0.00 $332,000.00 $83,000.00$415,000.001 Project
10/25/1995
Bridge Replacement, Mill Road over Moose Brook, Br. #121/116(CLOSED)
Hancock $0.00 $216,000.00 $54,000.00$270,000.003 Projects
9/9/1998
Bridge Replacement, Middle Road over Small Brook, Br. #107/074
$0.00 $68,000.00 $17,000.00$85,000.003/2/2007
Bridge Replacement, Old Dublin Rd #62 over Hosley Brook, Br. #095/090(Municipal Managed Project)
$0.00 $524,000.00 $131,000.00$655,000.0011/29/2011
Bridge Rehabilitation, School House Lane over Mink Brook, Br. #108/066
Hanover $0.00 $80,000.00 $20,000.00$100,000.001 Project
5/6/1998
Page 4 of 11Printed: 9/4/2018 8:14:02 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Bunker Hill Road over Needle Shop Brook
Hill $0.00 $596,000.00 $149,000.00$745,000.001 Project
5/31/2017
Bridge Replacement, Stowe Mountain Road over Shedd Brook, Br. #053/103(New)
Hillsborough $0.00 $872,000.00 $218,000.00$1,090,000.002 Projects
7/1/2019
Bridge Replacement, Bog Road (Melody Rd) over Sand Brook, Br. #152/095
$0.00 $776,000.00 $194,000.00$970,000.007/16/2013
Bridge Replacement, Stickney Hill Road over Boutwell Mill Brook, Br. #178/039
Hopkinton $0.00 $392,000.00 $98,000.00$490,000.002 Projects
7/1/2020
Bridge Rehabilitation, East Penacook Road over Blackwater River, Br. #134/166
$0.00 $480,000.00 $120,000.00$600,000.005/31/2017
Bridge Replacement, Dundee Road over Mill Brook, Br. #198/046
Jackson $0.00 $468,000.00 $117,000.00$585,000.003 Projects
7/22/2004
Bridge Rehabilitation, Wilson Road over Great Brook, Br. #157/079
$0.00 $420,000.00 $105,000.00$525,000.005/11/2009
Bridge Rehabilitation, Melloon Road over Wildcat Brook, Br. #135/122
$0.00 $280,000.00 $70,000.00$350,000.005/11/2009
Bridge Replacement, Beaver Street over Beaver Brook, Br. #140/079(Municipal Managed Project)
Keene $0.00 $524,000.00 $131,000.00$655,000.001 Project
7/1/2018
Bridge Rehabilitation, Messer Street over Winnpesaukee River, Br. #122/058
Laconia $0.00 $760,000.00 $190,000.00$950,000.002 Projects
8/18/2010
Bridge Replacement, Hilliard Road over Pickerel Cove Brook, Br. #112/147(New)
$0.00 $448,800.00 $96,000.00$544,800.001/7/2024
Bridge Replacement, McGary Hill Road over Otter Brook, Br. #218/076
Lancaster $0.00 $240,000.00 $60,000.00$300,000.001 Project
11/3/2005
Bridge Rehabilitation, Riverside Drive over Mascoma River, Br. #154/113
Lebanon $0.00 $655,520.00 $163,880.00$819,400.001 Project
5/26/2017
Page 5 of 11Printed: 9/4/2018 8:14:02 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Schrenk Road over Cold Brook, Br. #117/156
Lempster $0.00 $224,000.00 $56,000.00$280,000.003 Projects
6/17/1996
Bridge Replacement, Mountain Road over Ashuelot River, Br. #148/067
$0.00 $640,000.00 $160,000.00$800,000.0011/10/2010
Bridge Replacement, Keyes Hollow Road over Cold River, Br. #055/151
$0.00 $540,000.00 $135,000.00$675,000.0011/10/2010
Bridge Replacement, East Madison Road over Frost Brook, Br. #111/082
Madison $0.00 $552,000.00 $138,000.00$690,000.001 Project
1/21/2011
Bridge Replacement, Bodwell Road over Cohas Brook, Br. #209/155
Manchester $0.00 $696,000.00 $174,000.00$870,000.001 Project
11/1/2012
Bridge Replacement, Lewis Road over Ashuelot River, Br. #104/039
Marlow $0.00 $580,000.00 $145,000.00$725,000.001 Project
12/6/2005
Bridge Rehabilitation, US 3 over Souhegan River - Chamberlain Bridge, Br. #116/120
Merrimack $0.00 $172,000.00 $43,000.00$215,000.001 Project
7/1/2017
Bridge Replacement, Ridge Road over Jones Brook, Br. #082/109
Middleton $0.00 $360,000.00 $90,000.00$450,000.002 Projects
11/20/1998
Bridge Replacement, Silver Street Road over Outlet of Sunrise Lake, Br. #058/033
$0.00 $292,000.00 $73,000.00$365,000.0011/20/1998
Bridge Replacement, Mason Road over Great Brook, Br. #089/106
Milford $0.00 $548,000.00 $137,000.00$685,000.001 Project
5/26/2017
Bridge Replacement, Hopper Road over Salmon Falls River, Br. #064/167
Milton $0.00 $360,000.00 $90,000.00$450,000.004 Projects
11/13/1998
Bridge Rehabilitation, Church Street over Salmon Falls River, Br. #077/163
$0.00 $404,000.00 $101,000.00$505,000.0011/23/1998
Bridge Replacement, Allen Hastings Way over Jones Brook, Br. #104/109(Closed)
$0.00 $312,000.00 $78,000.00$390,000.0011/13/1998
Bridge Replacement, Winding Road over Lyman Brook, Br. #190/101
$0.00 $864,000.00 $216,000.00$1,080,000.005/30/2017
Bridge Replacement, Murdough Hill Road over brook, Br. #073/098
Nelson $0.00 $288,000.00 $72,000.00$360,000.001 Project
9/9/1998
Page 6 of 11Printed: 9/4/2018 8:14:03 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Rehabilitation, Coolidge Woods Road over Blake Brook, Br. #055/074
New Hampton $0.00 $180,000.00 $45,000.00$225,000.003 Projects
12/26/2006
Bridge Replacement, Coolidge Woods Road over Wallace Brook, Br. #035/051
$0.00 $344,000.00 $86,000.00$430,000.0011/8/2006
Bridge Replacement, Brook Road over Blake Brook, Br. #061/069
$0.00 $380,000.00 $95,000.00$475,000.0012/14/2009
Bridge Replacement, Mountain Road over Andrew Brook, Br. #094/080
Newbury $0.00 $212,000.00 $53,000.00$265,000.003 Projects
9/4/1998
Bridge Replacement, Mountain Road over unnamed brook, Br. #078/039
$0.00 $132,000.00 $33,000.00$165,000.009/4/1998
Bridge Replacement, Mountain Road over Andrew Brook, Br. #100/090
$0.00 $260,000.00 $65,000.00$325,000.009/4/1998
Bridge Replacement, New Road over Boston and Maine RR, Br. #130/083
Newfields $0.00 $672,000.00 $168,000.00$840,000.001 Project
10/19/2011
Bridge Replacement, Greenwood Road over Dodge Brook, Br. #097/139(Closed)
Newport $0.00 $300,000.00 $75,000.00$375,000.001 Project
12/26/2006
Repair/Replacement of Bridge, Old Canterbury Road over Narrows Brook, Br. #045/100
Northwood $0.00 $104,000.00 $26,000.00$130,000.001 Project
5/26/2017
Repair/Replacement of Bridge, Town Road #100 over Archertown Brook, Br. #114/113(Culvert)
Orford $0.00 $611,200.00 $152,800.00$764,000.002 Projects
5/24/2018
Bridge Replacement, Grimes Hill Road over Indian Pond Brook, Br. #120/173
$0.00 $456,000.00 $114,000.00$570,000.005/31/2017
Bridge Replacement, Bean Mountain Road over Lovell River, Br. #075/262(Force Acct DOT-Br. Maint)
Ossipee $0.00 $80,000.00 $20,000.00$100,000.003 Projects
5/28/1999
Bridge Replacement, Paddy Acre Road over Brook, Br. #147/233
$0.00 $152,000.00 $38,000.00$190,000.009/11/2002
Bridge Replacement, Valley Road over Dan Hole River, Br. #123/233
$0.00 $204,000.00 $51,000.00$255,000.005/14/2004
Bridge Replacement, Moeckel Road over Golden Brook, Br. #124/131(CLOSED)
Pelham $0.00 $268,000.00 $67,000.00$335,000.001 Project
8/8/2000
Page 7 of 11Printed: 9/4/2018 8:14:03 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Rehabilitation, Buck Street over Hartford Brook, Br. #182/106
Pembroke $0.00 $140,000.00 $35,000.00$175,000.001 Project
12/20/2005
Bridge Rehabilitation, Cate Street over Hodgson Brook, Br. #198/107
Portsmouth $0.00 $260,000.00 $65,000.00$325,000.005 Projects
9/18/2000
Bridge Rehabilitation, Woodbury Ave over Hodgson Brook, Br. #204/101
$0.00 $228,000.00 $57,000.00$285,000.009/20/2000
Repair/Replacement of Bridge, Pierces Island Road over Little Harbor, Br. #241/069
$0.00 $2,000,000.00 $500,000.00$2,500,000.0011/28/2000
Repair/Replacement of Bridge, Maplewood Ave over North Mill Road, Br. #231/103
$0.00 $880,000.00 $220,000.00$1,100,000.0011/2/2000
Bridge Rehabilitation, Coakley Road over Hodgson Brook, Br. #191/110
$0.00 $132,000.00 $33,000.00$165,000.009/18/2000
29055
Bridge Replacement, Whipple Hill Road over Roaring Brook, Br. #065/083(Municipal Managed Project)
Richmond $0.00 $892,000.00 $223,000.00$1,115,000.001 Project
7/1/2020
Bridge Rehabilitation, Converseville Road over Converseville Brook, Br. #153/073
Rindge $0.00 $180,000.00 $45,000.00$225,000.001 Project
10/3/2003
Repair/Replacement of Bridge, Rochecter Neck Road over Isinglass River, Br. #225/139
Rochester $0.00 $0.00 $0.00$0.001 Project
5/31/2017
Bridge Replacement, Old Mill Lane over Rollins Brook, Br. #090/052
Rollinsford $0.00 $772,000.00 $193,000.00$965,000.001 Project
5/30/2017
Bridge Replacement, Old Route 25 over Creamery Brook, Br. #076/087(6/12/06)
Rumney $0.00 $300,000.00 $75,000.00$375,000.005 Projects
1/30/2007
Bridge Rehabilitation, Old Route 25 over Emerald Brook, Br. #100/060
$0.00 $80,000.00 $20,000.00$100,000.003/2/2007
Bridge Replacement, East Rumney Road over Brook, Br. #202/100(6/12/06)
$0.00 $240,000.00 $60,000.00$300,000.001/30/2007
Bridge Replacement, Old Route 25 over Stewart Brook, Br. #077/085(6/12/06)
$0.00 $308,000.00 $77,000.00$385,000.001/30/2007
Bridge Rehabilitation, Sand Hill Road over Baker River, Br. #079/092
$0.00 $200,000.00 $50,000.00$250,000.002/4/2009
Page 8 of 11Printed: 9/4/2018 8:14:03 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Repair/Replacement of Bridge, Bridge Street over Spicket River, Br. #115/097(Municipal Managed Project)
Salem
1 Project
Bridge Replacement, Chapman Road over Patterson Brook, Br. #219/072
Sanbornton $0.00 $280,000.00 $70,000.00$350,000.001 Project
6/23/2009
Bridge Rehabilitation, Durgin Bridge Road over Cold River, Br. #226/119
Sandwich $0.00 $64,000.00 $16,000.00$80,000.002 Projects
11/20/2009
Bridge Rehabilitation, Basket Street over Bearcamp River, Br. #157/101
$0.00 $160,000.00 $40,000.00$200,000.005/16/2011
Bridge Rehabilitation, Whitehall Road over Powwow River, Br. #099/062
South Hampton $0.00 $204,000.00 $51,000.00$255,000.002 Projects
10/5/1999
Bridge Replacement, Hilldale Ave over Powwow River, Br. #069/066
$0.00 $1,260,000.00 $315,000.00$1,575,000.005/30/2017
Bridge Replacement, Star Lake Road over Star Lake Outlet, Br. #092/052
Springfield $0.00 $260,000.00 $65,000.00$325,000.003 Projects
7/7/2008
Bridge Replacement, George Hill Road over Gove Brook, Br. #071/138
$0.00 $300,000.00 $75,000.00$375,000.007/7/2008
Bridge Rehabilitation, George Hill Road over Bog Brook, Br. #064/152
$0.00 $140,000.00 $35,000.00$175,000.007/7/2008
Bridge Replacement, Barn Door Gap Road over Big River, Br. #057/135
Strafford $0.00 $940,000.00 $235,000.00$1,175,000.001 Project
5/30/2017
Bridge Replacement, Tetu Road over Stratford Bog Brook, Br. #124/086
Stratford $0.00 $228,000.00 $57,000.00$285,000.001 Project
3/15/2005
Bridge Replacement, Joslyn Road over Merriam Brook, Br. #090/090
Surry $0.00 $552,000.00 $138,000.00$690,000.001 Project
7/6/2010
41696
Bridge Rehabilitation, Rabbitt Hollow Road over Perry Brook, Br. #120/072
Swanzey
1 Project
7/1/2018
Page 9 of 11Printed: 9/4/2018 8:14:04 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Chocura Lake Road over Chocura Lake Outlet, Br. #069/157(Municipal Managed Project)
Tamworth $0.00 $360,000.00 $90,000.00$450,000.002 Projects
12/30/1998
Bridge Rehabilitation, Bryant Road over Mill Brook, Br. #145/118
$0.00 $180,000.00 $45,000.00$225,000.0012/30/1998
Bridge Replacement, Powers Road over Blood Brook, Br. #107/117
Temple $0.00 $368,000.00 $92,000.00$460,000.002 Projects
11/3/2008
Bridge Replacement, North Road over Brook, Br. #110/143
$0.00 $432,000.00 $108,000.00$540,000.0011/4/2008
Bridge Replacement, Sodom Road over Melvin River, Br. #134/089
Tuftonboro $0.00 $188,000.00 $47,000.00$235,000.002 Projects
5/30/2017
Bridge Replacement, Tuftonboro Neck Road over Winter Harbor, Br. #241/099
$0.00 $724,000.00 $181,000.00$905,000.005/31/2017
Bridge Replacement, Neal Mine Road over Little Sugar River, Br. #062/046
Unity $0.00 $536,000.00 $134,000.00$670,000.005 Projects
7/1/2013
Bridge Rehabilitation, Cold Pond Rd over Little Suger River, Br. #092/040
$0.00 $284,000.00 $71,000.00$355,000.007/5/2011
Bridge Replacement, South Slack Rd over Little Sugar River, Br. #101/046
$0.00 $580,000.00 $145,000.00$725,000.0010/31/2012
Bridge Replacement, Quaker City Rd over Little Suger River, Br. #086/039
$0.00 $584,000.00 $146,000.00$730,000.0010/31/2012
Bridge Replacement, Stage Road over Little Sugar River(Municipal Managed Project)
$0.00 $820,000.00 $205,000.00$1,025,000.0010/31/2012
Bridge Rehabilitation, Canal Road over Great East Lake Outlet, Br. #186/118(Municipal Managed Project)
Wakefield $0.00 $360,000.00 $90,000.00$450,000.003 Projects
2/19/2010
Bridge Replacement, Old Walefield Road over Pine Brook, Br. #096/032
$0.00 $756,000.00 $189,000.00$945,000.001/21/2011
Bridge Replacement, Maple Street over Branch River, Br. #290/064
$0.00 $704,000.00 $176,000.00$880,000.008/1/2013
Page 10 of 11Printed: 9/4/2018 8:14:04 AM Awaiting Town Action
PROJECT NAMEPROJ #
DESCRIPTION / IMPROVEMENT CURRENT ESTIMATE
FEDERAL SHARE
STATE SHARE TOWN / CITY SHARE
TRANDATE
Bridge Replacement, Wentworth Road over Houghton Brook, Br. #213/076
Walpole $0.00 $308,000.00 $77,000.00$385,000.001 Project
10/13/2003
Bridge Replacement, Breezy Point Road over Baker River, Br. #154/122
Warren $0.00 $500,000.00 $125,000.00$625,000.002 Projects
6/27/2000
Bridge Replacement, Studio Road over Brook, Br. #134/100
$0.00 $212,000.00 $53,000.00$265,000.006/27/2000
Bridge Replacement, Smith Pond Road over Shedd Brook, Br. #180/046(Municipal Managed Project)
Washington $0.00 $456,000.00 $114,000.00$570,000.001 Project
11/29/2011
Repair/Replacement of Bridge, West Branch Road over Mad River, Br. #126/123(Municipal Managed Project)
Waterville Valley $0.00 $360,000.00 $90,000.00$450,000.001 Project
1/21/2011
Bridge Replacement, Rowentown Road over Rocky Branch, Br. #111/068
Wentworth $0.00 $636,000.00 $159,000.00$795,000.001 Project
7/1/2019
Bridge Rehabilitation, Makinen Road over Mill Brook, Br. #151/125
Westmoreland $0.00 $380,000.00 $95,000.00$475,000.004 Projects
3/8/2006
Bridge Replacement, Spofford Road over Partridge Brook, Br. #138/038
$0.00 $248,000.00 $62,000.00$310,000.001/4/2006
Bridge Replacement, South Village Road over Mill Brook, Br. #167/120
$0.00 $220,000.00 $55,000.00$275,000.003/8/2006
Bridge Replacement, River Road South over Partridge Brook, Br. #089/100
$0.00 $1,040,000.00 $260,000.00$1,300,000.001/21/2011
Bridge Replacement, Frye Mill Road over Burton Pond Outlet, Br. #080/145
Wilton $0.00 $252,000.00 $63,000.00$315,000.001 Project
3/2/2007
Bridge Replacement, Bridge Street over Ashuelot River, Br. #122/096
Winchester $0.00 $800,000.00 $200,000.00$1,000,000.002 Projects
9/15/2004
Bridge Replacement, Burt Hill Road over Pouchaug Brook, Br. #081/022
$0.00 $704,000.00 $176,000.00$880,000.007/1/2021
152 Projects Awaiting Town Action $516,000.00 $66,317,421.60 $16,692,155.40$83,525,577.00EstimateTotal For
Page 11 of 11Printed: 9/4/2018 8:14:04 AM Awaiting Town Action
PROJECT NAME DESCRIPTION / IMPROVEMENT REMARKS
REQUESTS FOR ESTIMATES - WORK IN PROGRESS
Sent to BD 10/20/14-Est.send to PCA dated 11/6/14Repair/Replacement of Bridge, Forest Road over Great Brook, Br. #105/035Acworth
Sent to BD 1/25/17Repair/Replacement of Bridge, Brook Road over Joe English Brook, Br. #063/118Amherst
Sent to BD 12/12/17Repair/Replacement of Bridge, Antrim Road over Monadnock Mill Canal, Br. #095/093
Bennington
Sent to BD 2/10/17Repair/Replacement of Bridge, Iron Works Road over Turkey River, Br. #190/067Concord
Sent BD 2/10/17Repair/Replacement of Bridge, Washington Street over Canal Inlet, Br. #048/082Concord
Sent to BD 2/7/17Repair/Replacement of Bridge, Walker Brook Road over Frazier Brook, Br. #178/057
Danbury
Sent to BD 2/7/17Repair/Replacement of Bridge, Bohonnon Road over Wild Meadow Brook, Br. #112/108
Danbury
Req to BD to update estimate on 11/7/14-NDYBridge Replacement, Paulson Road over Brook, Br. #101/125Farmington
Req to BD to update estimate on 11/7/14-NDYBridge Replacement, Sheepboro Road over Berry's River, Br. #142/050Farmington
Sent to BD 3/12/14-Est sent to PCA dated 11/06/14Repair/Replacement of Bridge, Russell Station Road over Rand Brook, Br. #114/062
Francestown
Sent to BD 8/4/17Repair/Replacement of Bridge, Bickford Hill Road over Ham Branch, Br. #055/101Franconia
Sent to BD 12/28/16Repair/Replacement of Bridge, Summit AvenueGilford
Sent to BD 11/10/16Repair/Replacement of Bridge, School House Road over Brook, Br. #151/089Greenfield
Sent to Bridge Design 4/18/16Repair/Replacement of Bridge, Sculptured Rocks Road over Atwell Brook, Br. #123/057
Groton
Sent to BD 9/18/13-Est. sent to PCA dated 11/3/14Repair/Replacement of Bridge, Broad Cove Road over Dolf Brook, Br. #154/136Hopkinton
Page 1 of 3Printed: 9/4/2018 8:15:50 AM
PROJECT NAME DESCRIPTION / IMPROVEMENT REMARKS
REQUESTS FOR ESTIMATES - WORK IN PROGRESS
Sent to Bridge Design 5/13/2016Repair/Replacement of Bridge, NH111 WB over MERRIMACK RIVER, Br. #109/068Hudson
Sent to Bridge Design 5/13/2016Repair/Replacement of Bridge, NH111 EB over MERRIMACK RIVER, Br. #110/068Hudson
Sent to BD 2/1/18Repair/Replacement of Bridge, Summit Road over Black Brook, Br. #091/099Keene
Sent to BD 2/1/18Repair/Replacement of Bridge, Ferry Brook Road over Ferry Brook, Br. #173/135Keene
Sent to BD 2/1/18Repair/Replacement of Bridge, Whitcomb Mills Road over White Brook, Br. #079/080
Keene
Sent to BD 2/1/18Repair/Replacement of Bridge, Church Street over Beaver Brook, Br. #140/075Keene
Sent to BD 2/1/18Repair/Replacement of Bridge, Maple Avenue over Black Brook, Br. #090/101Keene
Sent to BD 2/21/17Repair/Replacement of Bridge, Wilton Road over Souhegan River, Br. #052/135Milford
Sent to BD 2/21/17Repair/Replacement of Bridge, NH Rte 13 (Purgatory Rd) over Souhegan River, Br. #073/154
Milford
Sent to Bridge Design 4/18/16Repair/Replacement of Bridge, Old Canterbury Road over Narrows Brook, Br. #045/100
Northwood
Sent to BD 12/21/17Repair/Replacement of Bridge, Powers Bridge Road over Brook, Br. #091/067Peterborough
Sent to BD 12/21/17Repair/Replacement of Bridge, Morrison Road over Contoocook River, Br. #081/069Peterborough
Sent to BD 12/21/17Repair/Replacement of Bridge, Slab Road over Otter Brook, Br. #132/134Peterborough
Sent to BD 5/4/17Repair/Replacement of Bridge, Colby Hill Road over Bloods Brook, Br. #157/121Plainfield
Sent to BD 1/8/15-NDYRepair/Replacement of Bridge, Portland Street over Wardley Brook, Br. #121/121Rochester
Page 2 of 3Printed: 9/4/2018 8:15:50 AM
PROJECT NAME DESCRIPTION / IMPROVEMENT REMARKS
REQUESTS FOR ESTIMATES - WORK IN PROGRESS
Sent to BD 1/8/15-NDYRepair/Replacement of Bridge, Lowell Street over Willow (Wardley) Brook, Br. #148/121
Rochester
Sent to BD 1/8/15-NDYRepair/Replacement of Bridge, Four Rod Road over Rickers Brook, Br. #114/046Rochester
Sent to BD 2/1/18Repair/Replacement of Bridge, Rye Harbor Road over Brook, Br. #135/075Rye
Sent to BD 4/28/15-Site visit complete, working on est.Repair/Replacement of Bridge, Bradford Road over Wenell Brook, Br. #071/052Sunapee
Sent to Bridge Design 5/3/16Repair/Replacement of Bridge, Temple Road over Blood Brook, Br. #063/105Wilton
Page 3 of 3Printed: 9/4/2018 8:15:50 AM