Post on 21-Jun-2020
Newsletter 2015-31 August 7, 2015 APPROVAL OF EMERGENCY RULE RESTORES CONSTRUCTION CHANGE ORDERS TO PREVIOUS PROCESS On Friday, July 31, 2015 at 2:58 p.m., Secretary of State Natalie Tennant signed Decision 8-15 to approve an emergency rule amendment to Title 148, Series1 – Purchasing Division --which clarifies that change orders related to government construction contracts do not require prior approval. For years, contracting agencies were required to file construction change orders with the Purchasing Division in a timely fashion, but prior approval was not required. This action effectively restores the approval process for construction change orders to the previous process. The emergency rule became necessary on July 1, 2015 when amendments to Series 1 went into effect, which govern, among other things, change orders for contracts approved by the Purchasing Division. The amendments provided that all change orders must be approved by the Purchasing Division and Attorney General (as to form) prior to commencement of work. If work was performed by a contractor prior to final approval, the contractor could not get paid for costs associated with the change order. The CAWV has been meeting with state officials since May to explain that, due to the unique nature of construction contracts, the required prior approval of change orders would require lengthy stoppages of work on active construction sites that would prove costly and unfeasible and would lead to increased costs for the taxpayer, state government agencies, contractors and others. While the emergency rule, filed July 23, 2015 by Secretary of Administration Jason Pizatella and signed July 31 by Secretary of State Tennant, makes it clear that change orders related to government contracts do not require prior approval, all change orders must be approved by the Purchasing Division and the Attorney General’s office before any money is encumbered. Therefore, contractors should be certain that change orders ordered by the architect/engineer and owner have a high probability of being approved and paid for before agreeing to perform any change order work. “I am appreciative of the efforts of a number of people who have worked to find a solution to this issue, including Secretary Pizatella, Secretary Tennant, Attorney General Patrick Morrisey, Legislative Auditor Aaron Allred, and state Purchasing and contracting agency officials,” said CAWV President Dan Cooperrider. “Without their help, the emergency rule could not have been developed and approved so quickly.” President Cooperrider noted that construction projects throughout the state could have come to a halt because contractors could not take the risk of not being paid for work performed on a change order. “No one benefits from having the project shut down while waiting for a change order to go through the prior approval process,” the president stated, “especially if there was a situation that required immediate action to address a safety or environmental issue, much like what we have on Abandoned Mine Lands (AML) projects.”
If the rule had not been changed, quantities at the end of the project could not have been adjusted. For example, if a project had estimated 500,000 cubic yards of excavation and actual yardage was 550,000, if a change order had not been approved prior to completion of the project the contractor would not have gotten paid for the additional 50,000 cubic yards. The only remedy was going to be to file with the West Virginia Court of Claims and hope the court would agree to the additional cost. Since all Court of Claims decisions must be approved by the West Virginia Legislature, contractors could be waiting over a year for their money. “I am glad this issue has come to a successful resolve,” said President Cooperrider. For a complete copy of Title 148, Series 1, click on the link below. The new amended language in 6.8.f. – Timing of Work – is underlined. http://apps.sos.wv.gov/adlaw/csr/readfile.aspx?DocId=26916&Format=PDF 6.8.f. Timing of Work. Spending units must not permit vendors to perform work that the spending unit anticipates will be added to a contract through a change order until such time as the change has been formally approved by the Purchasing Division and the Attorney General’s office, encumbered by the Purchasing Division, and mailed to the vendor. This subsection related to timing of work does not apply to government construction contract executed pursuant to W.Va. Code 5-22-1, et seq. If anyone has any questions, please call Mike Clowser at (304) 342-1166 or mclowser@cawv.org. PRESIDENT COOPERRIDER SEEKING MEMBERS TO SERVE ON COMMITTEES The CAWV’s committees and task forces are the driving forces in addressing many of the issues affecting CAWV members and the contracting industry. President Dan Cooperrider is currently seeking volunteers to participate. The sign-up form is attached to this week’s Newsletter. Members are urged to print the form and pass out copies to their employees who would like to participate. Committee functions are included on the form to assist members in deciding which committee to serve on. If you have questions about the committees or task forces, please call Pat McDonald for details at (304) 342-1166 or pmcdonald@cawv.org. CAWV President Dan Cooperrider has appointed the following committee chairpersons for 2015-2016: Budget and Finance Committee …………….….… C.R. Neighborgall, Neighborgall Construction Company Education Committee…................…………………………………………Blake Stevens, G & G Builders, Inc. Joint Architects Committee ………………………………………...…Derick Foster, Paramount Builders, LLC Joint Concrete Committee ……………………………………………....Phil Browne, Rumble Ready Mix, Inc. Joint Cooperative Committee …………………………......Nate Orders, Orders Construction Company, Inc. Joint Cooperative Utility Sub Committee…………Tim Spradling, Benchmark Construction Company, Inc. Joint Cooperative Construction Sub Committee……………..… John Boyle, Mountaineer Contractors, Inc. Joint Cooperative Asphalt Sub Committee………………………………... Ed Phares, J. F. Allen Company Joint Cooperative Specifications Sub Committee……… Nate Orders, Orders Construction Company, Inc. Joint Cooperative Publications Sub Committee………………...…Rick Johnson, West Virginia Paving, Inc. Joint Cooperative Aggregate Sub Committee…………………………………....….Doug Canterbury, Boxley Joint Cooperative Concrete Sub Committee……………….……..Shannon Hapuarachy, SMH Construction Joint Utilities Committee …………………………… Tim Spradling, Benchmark Construction Company, Inc. Legislative Committee ……………………………….…………………………… Scott Pierson, Pipe Plus, Inc. Membership Committee ………………………………………………………Roger Thomas, Kelly Paving, Inc. Program Committee …………………………………………………………..Doug Meeks, Brewer & Company Public Relations Committee …………………….…Kimberly Ridenhour, Instant Growth Hydroseeding, LLC
Safety and Crime Prevention Committee …………………………………………...…Rob LaFon, Famco, Inc. Strategic Planning Committee ……………………………… Dan Flesher, Trimble Engineers & Constructors Young Contractors Committee ……………………………………….………Josh Booth, Highway Safety, Inc. CAWV MEMBERS RECEIVE SPECIAL DISCOUNT ON AGC ENVIRONMENTAL CONFERENCE It’s not too late to register for AGC’s 2015 Contractors Environmental Conference happening near West Virginia on Sept. 2-3 in Arlington, Va. As CAWV members, AGC of America is offering a special 15% discount on registration. Members should use SPECIAL15CEC when registering. For members interested in any aspect of environmental compliance or sustainability on a construction jobsite, this conference is a great opportunity to connect with peers from across the country in a non-competitive environment. The conference features a special update on water quality trading using the Chesapeake Bay TMDL as an example. The conference will also be talking about everything from stormwater to endangered species; from federal jurisdiction over waters of the U.S. to what general contractors need to know about asbestos, lead and PCBs. For Sustainability managers, AGC is providing roundtable discussions on EPDs, emerging rating systems, green codes and more. Check out the conference website at http://meetings.agc.org/cec and be sure to use the SPECIAL15CEC discount code when registering. !CAWV DISCOUNT PROGRAM EXPANDED TO INCLUDE OFFICE DEPOT Office Depot and OfficeMax have merged into one and now CAWV Members can save up to 80% on over 93,000 products. Great for your printing, cleaning and all of your office supply needs. Shop online or in any Office Depot or OfficeMax store. Enjoy FREE next-day delivery on online orders over $50. Shop online or print off a FREE in-store Purchasing Card at: http://www.officediscounts.org/agc.html SAVE THE DATE FOR NATIONAL PURCHASING PARTNERS (NPP) WEBINAR AUGUST 20 – OFFERED AT NO COST TO CAWV MEMBERS The CAWV Education Series sponsored by BrickStreet Insurance will be hosting a webinar on Thursday, August 20, at 11:00 a.m. This webinar will educate members on the benefits of participation in the NPP Discount Program that is available with CAWV Membership. Members will learn how to sign up for money saving programs from companies such as Verizon Wireless, Fastenal, Staples, Expedia and several others. Many CAWV members are currently saving thousands of dollars annually with the CAWV / NPP Discount Program. Members will receive webinar registration information early next week and will be able login and participate free of charge. Contact Pat McDonald at (304) 342-1166 or pmcdonald@cawv.org with questions. CAWV MEMBERS ENJOY KINGS ISLAND OUTING Nearly 200 CAWV members and guests attended the association’s family outing at Kings Island on Friday, July 24. Members had the opportunity to spend Friday sharing time with fellow members at the association’s luncheon, which was held at the park’s sheltered picnic area. The CAWV would like to thank everyone who came out to join us. CAWV TO HOST MARSHALL TAILGATE OCTOBER 3 Come and join fellow CAWV members and Marshall fans for the 10th Annual CAWV Marshall Tailgate. The CAWV will be hosting this event on the West Lot before Marshall takes on Old Dominion on October 3. The tailgate will begin at 1:30 p.m. and will be open until kickoff at 3:30
p.m. All members, company staff and employees are welcome. Members who are interested in sponsoring this event or who need additional information should contact Wendy Long at (304) 342-1166 or email long@cawv.org. Game tickets are available by calling the Marshall Ticket office at 1-800-THE-HERD or online at www.herdzone.com. If your company would like to sponsor this event, please contact Wendy Long at (304) 342-1166. VOLUME DUES REPORTS NOW DUE First and Second Quarter volume dues reports for General Contractors are now due; a reminder was mailed this week. Please make every effort to return the report in a timely manner to the CAWV office at 2114 Kanawha Blvd, East, Charleston, WV 25311. For questions, please contact Wendy Long at (304) 342-1166 or long@cawv.org.
CONTRACTORS ASSOCIATION OF WEST VIRGINIACALENDAR OF EVENTS
2015
September 17-20
Apshalt Pavement Association
Annual Meeting
Snowshoe Mountain Resort
Snowshoe, West Virginia
September 27-29
ARTBA Annual Convention
Hilton Philadelphia Penn Landing
Philadelphia, PA
October 1
CAWV Board of Directors MeetingMarshall University Engineering Complex
Huntington, WV
October 1
CAWV Regional MeetingMarshall University Engineering Complex
Huntington, WV
October 3
CAWV Marshall Tailgate
Marshall vs. Old Dominion
West Lot
Huntington, WV
October 8
Joint Construction Sub Committee
CAWV Headquarters
Charleston, WV
October 30
YCC Golf Outing
TBA
Charleston, WV
December 1
CAWV Holiday Open House
CAWV Headquarters
Charleston, WV
2016
January 18
Transportation Day
West Virginia State Capitol
Charleston, WV
February 7-10
NAPA National Conference
La Quinta Resort & Club
La Quinta, CA
February 12-16
CAWV Midyear Meeting
The Grand Floridian Resort & Spa
Walt Disney World
Orlando, Florida
March 9-11
AGC Annual Convention
San Antonio Grand Hyatt
San Antonio, TX
March 23-24
EXPO
Charleston Civic Center
Charleston, West Virginia
July 7-10
CAWV Annual Meeting
The Greenbrier
White Sulphur Springs, WV
2017
January 27 - February 1
CAWV Midyear Meeting
Hyatt Regency Aruba
Palm Beach, Aruba
CAWV 2015-2016COMMITTEE APPOINTMENT
I am glad to accept an appointment to a Chapter Committee. Please rank committee preference with numerals (1) (2) (3).
____ EducationPromote interest and develop programs forconstruction education at all levels.
_____ Joint Architects Contractors work with architects, building owners,and funding agencies to ensure and improveconstruction procedures and programs.
_____ Joint ConcreteWork with WVDOH & FHWA to ensure andimprove concrete construction procedures onhighway projects/ programs.
_____ Joint CooperativeWork with WVDOH & FHWA to ensure andimprove construction procedures on highwayprojects/programs.
Joint Cooperative Sub Committees
_____ Asphalt_____ Concrete _____ Construction _____ Publications_____ Specifications_____ Utility
____ Joint Utilities Work with Engineers, suppliers, regulatory andfunding agencies to ensure and improve utilityconstruction in WV.
____ Legislative To review, monitor and promote necessarylegislative activities of the CAWV
_____ MembershipMonitor and recommend action on the recruitmentof new members and the retention of currentmembers.
_____ ProgramResearch/recommend meeting locations as well as todevelop program and meeting activities.
_____ Public RelationsImprove CAWV and construction industry’s image aswell as increase public education.
_____ SafetyTo improve construction industry performancethrough prevention and effective safety programs.
_____ Young ContractorsTo provide guidance knowledge to future leaders ofthe construction industry.
PLEASE SHARE THIS WITH EVERYONE IN YOUR ORGANIZATION
The following standing committees are appointed by the President and/or By Laws: Budget & Finance, Executive and Strategic Planning
Name______________________________________________________________________________________________
Company___________________________________________________________________________________________
Address_____________________________________________________________________________________________
City____________________________________________________________________State______________________Zip
Phone_________________________________________Email__________________________________________________
PLEASE RETURN FORM TO CAWV STAFF MEMBER ORREPLY VIA FAX TO: (304) 342-1074
August 7, 2015
**Plans in CAWV Physical Plan Room ^ Plans in Internet Plan Room (IPR) at www.isqft.com # CAWV Listed as plan holder but plans not yet received
The CAWV posts all projects announced in the Newsletter along with plans and specifications on www.isqft.com. Users of the service receive real-time updates as details are changed, plans, specifications and addenda are uploaded and bidders added. Users are also able to track projects of interest. The iSqFt Project Identification Number, found below, can be used for fast access to each project. For more information, contact Cheryl Clark at (304) 342-1166 or email planroom@cawv.org
8/10 New
Renovation, Plaza Area, Big Sandy Superstore Arena
Fox Engineering, PLLC (304) 532-5677
2422781
8/10 Dorm HVAC Replacement, Charleston Job Corps Center
Becky Hudson (304) 414-6526
2445499
8/10 **^Secondary Parking Lot, Beckley Sanitary Board
The Thrasher Group, Inc. (304) 431-7800
2443079
8/10 ^Roof Replacement, Pavilion/ Ice Rink, Canaan Valley State Park
Angela Negley (304) 558-3397 (DNR1600000013)
2439891
8/10 **^Swimming Pool Renovations, Lewis Wetzel Park, New Martinsville
Hays Landscape Architecture Studio, Ltd.(740) 695-6505
2435811
8/10 ^Exterior Siding Replacement - Marlinton Ranger District Office
www.fbo.gov and solicitation number AG-3434-S-15-0019
2423852
8/11 **^Repair/ Refurbish, Tennis Courts, Coonskin Park
Kanawha County Commission (304) 357-0115
2448402
8/11 **^University Avenue/Oakland Street Traffic Signal, Morgantown
CTL Engineering, Inc. (304) 292-1135
2445348
8/11 **^Additions/ Renovations, Crichton Elementary School, Greenbrier County
The Thrasher Group, Inc. (304) 624-4108
2435244
8/11 New
^Morgantown High School Press Box Williamson Shriver Architects (304) 345-1060
2427689
8/11 **^Wells-Boone/Guest River Road Sewer Line Extension, Wise, Virginia
Thompson & Litton (276) 328-2161
2435107
8/11 Building 88 – Players Club Roof Replacement, Charleston
Guy Nisbet (304) 558-2402 (GSD1600000001)
2429635
8/12 **^HVAC Improvements, Tri-State Airport, Huntington
Kimley-Horn & Associates stacey.baker@kimley-horn.com
2438335
8/12 New
^Sewer Lift Station Replacement, Grayson, Kentucky
Allison Pack (304) 399-5046 www.fbo.gov W9123715T0124
2445524
8/12 A/E, Tucker Boulder Park Tucker County Foundation (304) 478-2930
2444507
8/12 Design-Build, Communications Center, Berkeley County
Jim Thompson, Clerk of the Works (304) 582-0145
2436053
8/12 **^Lynn Camp Water Line Extension, Vansant, Virginia
Thompson & Litton (276) 328-2161
2435105
8/12 Subcontractor – FBI Data Center Reno, Clarksburg
Mike Hommer (763) 522-2100 2429636
8/13 Construction Manager at Risk, Coliseum Complex, WVU
WVU Purchasing Department (304)293-8475
2451052
8/13 EOI, Architectural/ Engineering Services, City of Hinton
City of Hinton (304) 466-3255
2452048
8/13 Forest Clearing Development, R. D. Bailey WMA, Wyoming County
Angela Negley (304) 558-3397 (DNR1600000019)
2447327
8/13 ^ Storm Sewer Rehabilitation, CIPP, City of Charleston
City of Charleston (304) 348-8014
2445154
8/13 **^T-Hangar Building Construction, Fairmont- Marion County Airport
CDI Infrastructure, LLC (304) 344-3600
2439923
8/13 New
^Morgan County Landfill Erosion Repair Beth Collins (304) 558-2157 (DEP1500000081)
2358882
8/13 **^Renovations, South Branch Career/Technical Center, Petersburg
Williamson Shriver Architects, Inc. (304) 345-1060
2439551
8/13 **^Radio-Read Water Meters, Buckhannon James Hollen (304) 472-1651 2434774 8/13 New
^Davis Coal and Coke - DEP17233, Tucker County
Beth Collins (304) 558-2157 (DEP1500000106)
2395784
8/13 Subcontractor - Health Professions Education Building, University of Pikeville
Codell Construction Co. Travis Curry (859) 744-222
2437303
8/13 **^Dewey Reed AML Reclamation, Pike County, Kentucky
Carolyn L. Turner (502) 782-0344
2437504
8/13 Building Demolition, Ashland Community and Technical Center
Josh Morgan (502) 564-3155 2437423
8/14 ^MALSR Road Slide Repair and Stream Restoration, Tri-State Airport
Kimley-Horn & Associates (303) 228-2300
2448881
8/14 ^Shop Building, Sutton Lake Matthew Wilson (304) 399-5297 www.fbo.gov W91237-15-T-0132
2448792
8/16 New
**^South Charleston Landfill Closure Beth Collins (304) 558-2157 (DEP1500000107)
2396351
8/17 Water Meters, Morgantown Utility Board Morgantown Utility Board (304) 292-8443
2448931
8/17 Stone Contract, Morgantown Utility Board Morgantown Utility Board (304) 292-8443
2448932
8/17 New
#Practice Facility Renovations, WVU Gateway Engineers, Inc. (412) 787-1994
2443214
8/17 Old Magistrates Court Parking Lot, Hancock County
Hancock County Commission (304) 564-3311
2445498
8/17 Roof Repairs/Replacement, Raleigh County 4-H Building
Raleigh County Commission (304) 255-9146
2448843
8/17 Cleaning/Painting, Maclin Hall Exterior, WVUIT WVU Purchasing Department (304)293-9778
2444487
8/18 EOI, Engineering Services, Greenbrier Valley Conservation District
Greenbrier Valley Conservation District (304) 285-3118
2452016
8/18 New
**^Renovations Building 5 & 6, WV State Capitol ZMM Architects (304) 342-0159 (GSD1600000002)
2431855
8/18 ^Water Supply, Greater Tazewell WTP to Pocahontas-Phase II and III
Thompson & Litton (276) 328-2161
2448671
8/18 New
Restoration of Head Houses, Harpers Ferry Linn Architects (610) 566-7044 (RMA1500000008)
2423056
8/18 **^New Ceredo-Kenova Elementary School, Wayne County
ZMM Architects & Engineers, Inc. (304) 342-0159
2436193
8/18 *^Cherry Glade Phase 2 Road Construction, Garrett County, Maryland
Garrett County Commissioners (301) 334-5003
2435208
8/18 **^Burnsville Contract #1 – Water System Improvements and Water Line Ext.
The Thrasher Group, Inc. (304) 624-4108
2432575
8/18 **^Burnsville Contract #2 - Route 5 and New Town Tank Rehab
The Thrasher Group, Inc. (304) 624-4108
2432620
8/18 **^Western Brambleton District Park Improvements, Loudoun County
Christopher Presley (703) 777-0394
2431827
8/18 ^A/E, Intersection Plan, Frostburg, Maryland Allegany County (301) 722-6360 2443430 8/19 **^Metal Roof Retrofit, Hagar 19, Hagerstown,
Maryland Washington County Purchasing (240) 313-2330
2443429
8/19 ^Roof Replacements, Jackie Withrow Hospital Robert Kilpatrick (304) 558-0067 (JWH1600000001)
2448751
8/19 ^Design Build, Magic Island Splash Pad, Charleston
City Manager (304) 348-8014
2441848
8/19 **^Mill Creek Water System Improvements, Randolph County
Potesta & Associates (304) 342-1400
2435279
8/20 **^Alternative School, Beaver Creek, Martin, Kentucky
Matt Wilson (304) 399-5297 www.fbo.gov W9123715B0005
2444576
8/20 **^Drainage Mitigation, WV Turnpike, Mercer County
HNTB Corporation (304) 760-1833
2448624
8/20 **^Culvert Retrofit, WV Turnpike HNTB Corporation (304) 760-1817
2444450
8/20 **^Bridge Deck Replacement, Ghent, Raleigh County
HNTB Corporation (304) 760-1833
2423169
8/20 ^Bridge Painting, WV Turnpike HNTB Corporation (304) 760-1840
2445152
8/20 ^Steel Plates, District 6 Misty Delong (304) 558-8802 (DOT1600000008)
2443482
8/20 ^Structural Steel, District 4 Misty Delong (304) 558-8802 (DOT1600000007)
2443483
8/20 **^ Subcontractors: FMC Dialysis Center, Man GC: Del Company (828) 324-1284
2453250
8/20 **^Western Conveyance, Water/Wastewater Extension, Garrett County, Maryland
Garrett County Commissioners (301) 334-5003
2435204
8/24 ^Consulting Services, Earl M. Vickers, Memorial Bridge, Fayette County
Michael Lilly @ doh.consultantservices@wv.gov
2448431
8/24 ^Consulting Services, Mill Creek Bridge, Jackson County
Michael Lilly @ doh.consultantservices@wv.gov
2448457
8/25 **^Perimeter Fence, Coonskin Complex (ADJ1600000004)
Crystal Rink (304) 558-2402 Michael Baker (304) 769-0821
2445625
8/25 ^Window/Window Wall Replacements, WV National Guard Armories
Crystal Rink (304) 558-2402 (ADJ1600000002)
2443485
8/25 **^Prestressed Concrete Box Beams, Bird Run Bridge
Misty Delong (304) 558-8802 (DOT1600000009)
2443461
8/25 New
**^Glen Avenue Mine Drainage Project DEP17128, Harrison County
Beth Collins (304) 558-2157 (DEP1500000096)
2387323
8/25 New
Parking Garage – VA Medical Center, Clarksburg
Rebecca Besten (304) 623-3461 www.fbo.com VA24415B0738
2429355
8/26 Bridge Approach, City of Pikeville Summit Engineering (859) 264-9860
2450860
8/26 A/E, Sanitary Sewer Improvements, Greenbrier County PSD 2
Kevin Williams (304) 438-9283 2435209
8/26 Industrial Lane Sanitary Sewer Rehabilitation, Washington County, Maryland
Board of County Commissioners (240) 313-2330
2448733
8/26 ^Design-Build, Rt.722 Transit Connector Bridge, Loudoun County
Christopher Bresley (703) 777-0394
2437365
8/27 Re-Roof, Greenbo Lodge Kitchen, Greenup, Kentucky
Commonwealth of Kentucky (502) 564-3155
2450891
8/27 **^Fire Suppression Improvements, Phase II, Harrison County Courthouse
The Thrasher Group, Inc. (304) 624-4108
2445415
8/27 A/E, State Park Model Cabin Renovation Guy Nisbet (304) 558-2596 (DNR1600000001)
2443460
8/27 New
**^Sovern Run (England) Refuse Portals, Preston County
Beth Collins (304) 558-2157 (DEP1500000104)
2395337
8/28 **^Maintenance Garage, Town of Lonaconing Rummel, Klepper & Kahl, LLP (304) 788-3370
2445595
8/31 **^Renovations, Ritchie Elementary School, Ohio County
M & G Architects & Engineers (304) 242-8248
2448459
9/1 Wheeling LAASF Concrete Apron Rehabilitation
Crystal Rink (304) 558-2402 Charleston Blueprint (ADJ1600000006)
2451051
9/1 Roof Replacements, Mercer County Schools Mercer County Schools (304) 487-1551
2448935
9/2 **^ HVAC Upgrade, Glidden Hall, Ohio University
Pickering Associates (740) 593-3327
2452338
9/2 Roof Replacement, WV National Guard Annex, Charleston
Crystal Rink (304) 558-2402 (ADJ1600000007)
2452124
9/2 **^Energy Marketing Company Reclamation – Barbour County
Civil Engineering Consultants (614) 540-6633(DEP1600000002)
2429208
9/2 **^Renovations, President's Residence, Marshall University
Edward Tucker Architects (304) 697-4990
2451967
9/2 **^Wolfpen (Carpenter) Portals – Kanawha County
Potesta & Associates, Inc. (304) 342-1400 (DEP1600000001)
2429207
9/2 Williamstown AASF#1, HVAC Renovations Crystal Rink (304) 558-2402 (ADJ1600000005)
2452308
9/8 Large Equipment Rental, State of West Virginia Laura Hooper (304) 558-0468 (GSD1600000005)
2450812
9/8 **^Blakes Creek / Eastwood Sewer Extension, Nitro WWTP, Contract 1
S & S Engineers, Inc. (304) 342-7168
2449910
9/8 **^Belt Filter Press / Building Replacement, Nitro WWTP, Contract 2
S & S Engineers, Inc. (304) 342-7168
2449914
9/9 Forced Main Repairs, City of Piedmont The Thrasher Group, Inc. (304) 624-4108
2452231
9/9 New
**^Reclamation: Decondor Coal Company Inc. U-147-82 OSR, Preston County
Beth Collins (304) 558-2157 (DEP1500000094)
2386349
9/10 Braxton County RETI Conference Center Omni Associates (304) 367-1417 2450765 9/15 **^Reclamation: Indore (Osborne) Portals -
DEP17246, Clay County Beth Collins (304) 558-2157 (DEP1600000004)
2439728
9/17 Reclamation: City of War Portals - DEP17264 Beth Collins (304) 558-2157 (DEP1600000008)
2453084
9/30 **^Reclamation: Switzer (Ellis) Drainage – DEP17251
Beth Collins (304) 558-2157 (DEP1600000006)
2446593
2015 WVDOH LETTING SCHEDULE
August 18 October 6 August 25 November 17
September 15 December 8
BB 2015-31 August 7, 2015
RENOVATION, RITCHIE ELEMENTARY SCHOOL, OHIO COUNTY (iSqFt Project ID# 2448459) Bids will be accepted until 1:00 PM on 8/31/2015 for general renovations to the Ritchie Elementary School, Wheeling. A mandatory pre-bid meeting will be held on 8/11/2015 at 1:00 PM at the Ritchie Elementary School, 3700 Wood Street, Wheeling. Bids should be submitted to Ohio County Schools, 2203 National Road, Wheeling, WV 26003 (304)243-0431. Plans and specifications are available from M & G Architects & Engineers, 1027 Mt. deChantal Road, Wheeling, WV 26003 (304)242-8248. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. RENOVATIONS, PRESIDENT'S RESIDENCE, MARSHALL UNIVERSITY (iSqFt Project ID# 2451967) Bids will be accepted until 3:00 PM on 9/2/2015 for removal and replacement of existing cabinetry, hardware, countertops, appliances, fixtures, tile, walls, doors and trim for kitchen and five bathrooms in the home of the Marshall University President and converting existing hobby room into a dressing room. A mandatory pre-bid meeting will be held on 8/19/2015 at 10:00 AM at 1040 Thirteenth Street, Huntington. Bids should be submitted to Marshall University, 102 Old Main Building, Room 125, Huntington, WV 25755 (304)696-2823. Plans and specifications are available from Edward Tucker Architects, 1401 Sixth Avenue, Huntington, WV 25701 (304)697-4990. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. SHOP BUILDING, SUTTON LAKE (iSqFt Project ID# 2448792) Bids will be accepted until 4:00 PM on 8/14/2015 for construction and installation of a rectangular post frame building at the maintenance compound below Sutton Dam. Bids should be submitted to US Army Corps of Engineers - Huntington District, Matthew Wilson, 502 8th Street, Huntington, WV 25701 (304)399-5297. Plans and specifications are available from www.fbo.gov and solicitation number W91237-15-T-0132. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. ROOF REPAIRS/REPLACEMENT, RALEIGH COUNTY 4-H BUILDING (iSqFt Project ID# 2448843) Bids will be accepted until 4:00 PM on 8/17/2015 for removal and disposal of old wall scuppers and roof membrane material and install new scuppers and collector boxes, new downspouts, flashing as needed, and other necessary roof repairs for the 4-H building. Bids should be submitted to Raleigh County Commission, 116 ½ North Herber Street, Beckley, WV 25801 (304)255-9146. Plans and specifications are available from Raleigh County Commission, 116 ½ North Herber Street, Beckley, WV 25801 (304)255-9146. Documents are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com.
ROOF REPLACEMENTS, JACKIE WITHROW HOSPITAL (iSqFt Project ID# 2448751) Bids will be accepted until 1:30 PM on 8/19/2015 for removal of existing roofs and installation of new roofs, insulation and EPDM membrane roofing systems for the staff dining hall and D-wing buildings at Jackie Withrow Hospital facility. A mandatory pre-bid meeting and facility tour was held on 8/6/2015 at 1:00 PM at Jackie Withrow Hospital, A100 conference room, 105 South Eisenhower Drive, Beckley. Bids should be submitted to www.wvOasis.gov and solicitation number JWH1600000001. For additional information contact State of WV, Bob Kilpatrick, 2019 Washington Street, East, P. O. Box 50130, Charleston, WV 25305-0130 (304)558-0067. Plans and specifications are available from www.wvOasis.gov. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. ROOF REPLACEMENTS, MERCER COUNTY SCHOOLS (iSqFt Project ID# 2448935) Bids will be accepted until 11:00 AM on 9/1/2015 for replacement of the kitchen and cafeteria roof sections at Spanishburg Elementary School. A mandatory pre-bid meeting will be held on 8/18/2015 at 10:00 AM at Spanishburg Elementary School, 8544 Beckley Road, Spanishburg. Bids should be submitted to Mercer County Board of Education, 1403 Honaker Avenue, Princeton, WV 24740 (304)487-1551. Plans and specifications are available from Mercer County Board of Education, 1403 Honaker Avenue, Princeton, WV 24740 (304)487-1551. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. ROOF REPLACEMENT, WV NATIONAL GUARD ANNEX, CHARLESTON (iSqFt Project ID# 2452124) Bids will be accepted until 1:30 PM on 9/2/2015 for installation of approximately 27,515 SF of fully adhered EPDM roofing system, downspouts and down spouts for the WV National Guard Annex, Charleston. A mandatory pre-bid meeting will be held on 8/19/2015 at 10:00 AM at WV National Guard Charleston Annex, 1740 Coonskin Drive, Charleston. Bids should be submitted to www.wvOasis.com and solicitation number ADJ1600000007. For additional information contact State of WV, Crystal Rink, 2019 Washington Street East, Charleston, WV 25311 (304)558-2402. Plans and specifications are available from www.wvOasis.gov . Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. CONSTRUCTION MANAGER AT RISK, COLISEUM COMPLEX, WVU (iSqFt Project ID# 2451052) Statement of Qualifications will be accepted until 3:00 PM on 8/13/2015 for Request for Qualifications from Construction Management firms to perform pre-construction as well as construction management “at risk” (CM-R) services for the West Virginia University Projects, located on the Coliseum Complex campus, Jerry West Boulevard, Morgantown. Proposals should be submitted to WVU Purchasing, Contracts and Payment Services, Robert Beck, One Waterfront Place, Morgantown, WV 26506-6024 (304)293-8475. Plans and specifications are available from WVU Facilities Management, 979 Rawley Lane, P. O. Box 6572, Morgantown, WV 26506 (304)293-2878. Documents are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com.
BRAXTON COUNTY RETI CONFERENCE CENTER (iSqFt Project ID# 2450765) Bids will be accepted until 11:00 AM on 9/10/2015 for construction of the RETI Conference Center, Sutton. A mandatory pre-bid meeting will be held on 8/20/2015 at 10:00 AM at the Braxton County Tech. Center, 89 Richard D. Minnich Drive, Room 101, Sutton. Bids should be submitted to Braxton County Development Authority, 89 Richard D. Minnich Drive, Room 101, Sutton, WV 26601 (866)832-3535. Plans and specifications are available from Omni Associates, 1543 Fairmont Avenue, Suite 201, Fairmont, WV, 26554, (304)367-1417. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. WILLIAMSTOWN AASF#1, HVAC RENOVATIONS (iSqFt Project ID# 2452308) Bids will be accepted until 1:30 PM on 9/2/2015 for renovation of the HVAC systems at the Williamstown AASF#1, 387 Aviation Drive, Williamstown. A mandatory pre-bid meeting will be held on 8/14/2015 at 10:00 AM at 387 Aviation Drive, Williamstown. Bids should be submitted to www.wvOasis.gov and solicitation number ADJ1600000005. For additional information contact State of WV, Crystal Rink, 2019 Washington Street East, Charleston, WV 25311 (304)558-2402. Plans and specifications are available from www.wvOasis.gov . Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. HVAC UPGRADE, GLIDDEN HALL, OHIO UNIVERSITY (iSqFt Project ID# 2452338) Bids will be accepted until 2:00 PM on 9/2/2015 for HVAC upgrade for Glidden Hall, Ohio University, Athens, Ohio. A pre-bid meeting will be held on 8/18/2015 at 2:00 PM at Ohio University, 160 West Union Street Office Center, Suite 302, Athens, Ohio. Bids should be submitted to Ohio University, 160 West Union Street, Building 19, Suite 279, Athens, OH 45701 (740)593-2727. Plans and specifications are available from Pickering Associates, 2099 East State Street, Athens, OH 45701 (740)593-3327. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. SUBCONTRACTORS: FMC DIALYSIS CENTER, MAN (iSqFt Project ID# 2453250) Request for subcontractors for the interior up fit of an approximately 7,835 SF dialysis center in Man until 2:00 PM on 8/20/2015. Proposals should be submitted to Del Company, P. O Box 3224, Hickory, NC 28603 (828)324-1284. Plans and specifications are available from Del Company, Ty Weiss, P. O Box 3224, Hickory, NC 28603 (828)324-1284. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com.
RE-ROOF, GREENBO LODGE KITCHEN, GREENUP, KENTUCKY (iSqFt Project ID# 2450891) Bids will be accepted until 2:00 PM on 8/27/2015 for complete removal and replacement of approximately 2,750 SF of existing built-up roofing systems located over the kitchen. A pre-bid meeting will be held on 8/13/2015 at 11:00 AM at Greenbo Lake State Park, 965 Lodge Road, Greenup, KY. Bids should be submitted to Commonwealth of Kentucky, 403 Wapping Street, 2nd Floor Bush Building, Frankfort, KY 40601 (502)564-3155. Plans and specifications are available from Commonwealth of Kentucky, 403 Wapping Street,
2nd Floor Bush Building, Frankfort, KY 40601 (502)564-3155. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. EOI, ARCHITECTURAL/ ENGINEERING SERVICES, CITY OF HINTON (iSqFt Project ID# 2452048) Expression of Interest from architectural and engineering firms will be accepted until 4:00 PM on 8/13/2015 to provide all professional services, master planning, conceptual design, contract documents and construction administration for all civil projects to be determined in the master plan. Proposals should be submitted to City of Hinton, 322 Summers Street, Hinton, WV 25951 (304)466-3255. For additional information contact City of Hinton, Cris Meadows, 322 Summers Street, Hinton, WV 25951 (304)466-3255. Documents are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. FCC HAZELTON - REPLACEMENT CHILLER (Bid 7/31/2015) General Civil Company ............................................................................................. $324,700 Quality Mechanical Contracting ................................................................................. 338,420 Diversified Mechanical LTD....................................................................................... 489,640 Integritas Systems, LLC ............................................................................................ 516,700 General & Mechanical Services ................................................................................ 673,312 PRESSURE BOILERS INSPECTION, CLEANING, MAINTENANCE (Bid 7/30/2015) Casto Technical Services ........................................................................................ $34,965 Nitro Mechanical ....................................................................................................... 42,988 *CAWV Member in bold type
August 7, 2015
HIGHWAY WORK ZONES..................CAUTION! CAUTION! CAUTION! Even when all traffic control measures are taken, a confused or unaware driver can crash through a work site, or a daydreaming worker can step into the path of a speeding vehicle. Some drivers take reckless chances by running stop signs or changing lanes without signaling. These unsafe acts jeopardize other drivers who may lose control of their vehicle while avoiding a collision. When work site involves moving traffic, safety awareness should be at its peak, to protect both the public and the crew. Some helpful tips to better prepare are: Planning: All traffic control must be carefully planned and approved by governing authorities before work begins. The person responsible for this planning should drive through the traffic pattern before any work starts to ensure that the public will understand how to control their vehicles appropriately. If there is any possibility of driver confusion in the pattern, change it. Signage: The Manual on Uniform Traffic Control Devices and local or state regulations should be followed for proper signage and barricading. Place initial warning signs a minimum of 1,000 feet from traffic revisions. All signs and related equipment should be in good condition and highly visible. In some cases, independent traffic safety contractors handle warning signs and barricades. Barricades: Devices which guide traffic such as cones, barrels, etc., should be highly visible and spaced relatively close together, so drivers will not deviate from an assigned traffic flow. All such barriers should be made of material that will cause little or no damage if a vehicle contacts it. Safety Gear: All employees should wear hard hats and must wear high-visibility orange or day-glow vests. When working at night, the vest should have light-reflective strips. Flaggers: Roadside construction sites must have at least one individual assigned to traffic control. A highly visible sign paddle should be used during daylight hours. It should be octagonal in shape, at least 18 inches across, and have letters at least six inches high that say STOP on one side and SLOW on the other. Flaggers should have two-way radios. When flaggers are present, a sign indicating this must be placed a minimum of 500 feet from the beginning of the detour. Vehicles: All construction vehicles should be equipped with backing alarms, two-way radios, and Slow Moving Vehicle signs when appropriate. Ideally, they should be painted a highly visible color and many jurisdictions also require flashing yellow beacons. All operators must be qualified and trained to operate the equipment they are using. If a vehicle is parked along-side the road, orange safety cones should be placed around it to alert drivers. Night Work: If work is done at night, the entire site must be illuminated. Increase warning distances in areas of fast-moving traffic as light fails. Flaggers should have orange-cone flashlights and barricades should be equipped with flashing lights. Any excavations or utility accesses should be taped off and barricaded with flashing warning lights. Training: All company employees and subcontractors involved in the project must receive an initial safety orientation, informing them of the potential hazards of the project, including traffic safety. Changes or unusual conditions should be communicated to workers immediately.
The Associated General Contractors (AGC) of America is collaborating with ClickSafety, an OSHA-authorized provider, to deliver a wide range of construction related safety courses online for members at a 10% discount. To view the full course catalog, and for information on ordering, visit: www.cawv.org then
click on the Safety link.
MU 2015-31 August 7, 2015
WATER AND WASTEWATER/SEWER CONTRACTS FOR 2015 The following is the WV Water and Wastewater/Sewer Contract Data through July 2015.
Water Wastewater-
Sewer
Total
Total # Projects Amount # Projects Amount # Projects Amount
July 2015 9 7.16 5 4.18 14 11.34
2014 3 10.4 4 6.9 7 17.34
June 2015 6 7.95 1 .030 7 7.98
2014 6 5.27 4 8.51 10 13.78
May 2015 11 7.23 1 19.58 12 26.81
2014 12 10.84 6 3.07 18 13.91
April 2015 8 32.10 3 1.95 11 34.04
2014 2 2.596 6 4.87 8 7.47
March 2015 8 7.84 7 24.09 15 31.93
2014 16 25.58 3 .845 19 26.42
Feb 2015 3 1.84 2 1.77 5 3.616
2014 4 2.68 4 1.045 8 3.73
Jan 2015 5 8.45 2 .906 7 9.36
2014 6 7.70 1 2.34 7 10.046
TOTAL # OF PROJECTS TOTAL AMOUNT
Y-T-D Total for 2015 71 125.12 Y-T-D Total for 2014 77 92.47
(Reported in Millions) REGISTRATION OPEN FOR FIRST-EVER AGC UTILITY CONFERENCE AT ICUEE AGC of America will be hosting its first ever Utility Infrastructure Conference, Sept. 29–Oct. 1 in Louisville, Kentucky. Contractors, owners and key industry constituents involved in every aspect of utility infrastructure construction will be able to participate in high-quality education sessions, the premier utility construction equipment expo, and networking opportunities. This year’s conference will be co-located with the International Construction and Utility Equipment Exposition (ICUEE), which is the largest industry event focused exclusively on the utility infrastructure market, with over 17,000 industry
professionals attending ICUEE 2013. All conference session will take place inside the Kentucky Exposition Center in Louisville, Kentucky. Sessions will focus on the challenges Kokosing Industrial Inc. faced while constructing the Columbus, OH HRT facility and how they overcame those challenges, the challenges and opportunities in managing a multi-generational workforce, and how OSHA’s new Confined Space Entry final rule will impact utility construction contractors. AGC will also host a legislative and regulatory update on the Expo Demo Stage, and will partner with the Common Ground Alliance for an Underground Damage Prevention lunch. For more information, please contact Scott Berry at (703) 837-5321 or berrys@agc.org or visit http://icuee.com/visit/register to register. BLAKES CREEK / EASTWOOD SEWER EXTENSION, NITRO WWTP, CONTRACT 1 (iSqFt Project ID# 2449910) Bids will be accepted until 1:30 PM on 9/8/2015 for installation of approximately 8,650 LF of 8" PVC, 9,400 LF of 6" PVC, 150 LF of 8" DIP, 1,000 LF of 6" DIP gravity sewer lines, 3,500 LF of 4" PVC, 160 manholes, 3 pump stations, 3 grinder pump stations, 1,700 LF of 4" PVC, 3,400 LF of 3" PVC, 200 LF of 1¼" HDPE force mains to discharge into the existing sewer system, 580 LF of 30” HDPE stormsewer, 720 LF of 24” HDPE stormsewer, relining of 2,300 LF of 42” brick sewer line, replacement of an existing pump station No. 6 and other appurtenances necessary to complete this project. Additive Alternate A includes the installation of approximately 685 LF of 6" PVC, 115 LF of 6" DIP gravity sewer lines, 90 LF of 4" PVC sewer lateral, 7 manholes and other appurtenances necessary to complete Contract 1 for the City of Nitro. A mandatory pre-bid meeting will be held on 8/25/2015 at 1:30 PM at the City of Nitro, City Hall, 20th Street & 2nd Avenue, Nitro. Bids should be submitted to Nitro Regional Wastewater Utility, 20th Street & 2nd Avenue, P. O. Box 607, Nitro, WV 25143 (304)755-3669. Plans and specifications are available from S & S Engineers, Inc., 501 Eagle Mountain Road, Charleston, WV 25311 (304)342-7168. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. BELT FILTER PRESS / BUILDING REPLACEMENT, NITRO WWTP, CONTRACT 2 (iSqFt Project ID# 2449914) Bids will be accepted until 1:30 PM on 9/8/2015 for replacement of existing belt filter press with a new 2.2 meter belt filter press system, complete with air compressor, wash water booster pump, control panel, polymer system, sludge pump, sludge cake conveyor, lime system, construction of a new 48’x56’ belt filter press building, modification to existing effluent parshall flume structure and other appurtenances necessary to complete Contract 2 for the City of Nitro. A mandatory pre-bid meeting will be held on 8/25/2015 at 1:30 PM at the City of Nitro, City Hall, 20th Street & 2nd Avenue, Nitro. Bids should be submitted to Nitro Regional Wastewater Utility, 20th Street & 2nd Avenue, P. O. Box 607, Nitro, WV 25143 (304)755-3669. Plans and specifications are available from S & S Engineers, Inc., 501 Eagle Mountain Road, Charleston, WV 25311 (304)342-7168. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. FORCE MAIN REPAIRS, PEARL STREET, CITY OF PIEDMONT (iSqFt Project ID# 2452231) Bids will be accepted until 4:00 PM on 9/9/2015 for repairs of 830 LF seeding and mulching, reclamation, erosion and sediment control, 30 LF driveway repair, 6” minimum compaction crushed run stone, 800 LF gravel roadway shoulder repair 6” minimum compaction crushed run stone, 830 LF 6” restrained Joint PVC or 6” IPS HDPE (DR-17, 125 PSI Min.) force main, connection of new 6” force main to existing 6” cast iron force main. A mandatory pre-bid meeting will
be held on 8/28/2015 at 9:30 AM at 52 Second Street, Piedmont. Bids should be submitted to City of Piedmont, 52 Second Street, Piedmont, WV 26750 (304)355-2621. Plans and specifications are available from The Thrasher Group, Inc., 600 White Oaks Boulevard, P.O. Box 940, Bridgeport, WV 26330 (304)624-4108. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. WATER METERS, MORGANTOWN UTILITY BOARD (iSqFt Project ID# 2448931) Bids will be accepted until 3:00 PM on 8/17/2015 for purchase and delivery of 5/8" x 3/4" water meters for Morgantown Utility Board. Bids should be submitted to Morgantown Utility Board, 278 Greenbag Road, P. O. Box 852, Morgantown, WV 26507-0852 (304)292-8443. For additional information contact Morgantown Utility Board, 278 Greenbag Road, P. O. Box 852, Morgantown, WV 26507-0852 (304)292-8443. Documents are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. INDUSTRIAL LANE SANITARY SEWER REHABILITATION, WASHINGTON COUNTY, MARYLAND (iSqFt Project ID# 2448733) Bids will be accepted until 2:00 PM on 8/26/2015 for placement of excavation, clearing and grubbing, erosion and sediment control and wetland plantings for the Industrial Lane Sanitary Sewer project. A pre-bid meeting will be held on 8/12/2015 at 10:30 AM at the Washington County Division of Environmental Management Public Meeting Room, 116323 Elliott Parkway, Williamsport, Maryland. Bids should be submitted to Board of County Commissioners of Washington County, 100 West Washington Street, Room 320, Hagerstown, MD 21740-4735 (240)313-2330. Plans and specifications are available from Board of County Commissioners of Washington County, 100 West Washington Street, Room 320, Hagerstown, MD, 21740-4735 (240)313-2330. Documents are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. WATER SUPPLY, GREATER TAZEWELL WTP TO POCAHONTAS-PHASE II AND III, VIRGINIA (iSqFt Project ID# 2448671) Bids will be accepted until 2:00 PM on 8/18/2015 for Contract I –construction of Pump Station No. 1, replacement of the Pocahontas Water Meter, and all related appurtenances; and Contract II –construction of Pump Station No. 2 and all related appurtenances. A pre-bid meeting was held on 8/4/2015 at 10:00 AM at the Tazewell County Public Service Authority, 273 Tazewell Mall Circle, Tazewell, VA 24630. Bids should be submitted to Tazewell County PSA, 273 Mall Circle Road, P. O Box 190, Tazewell, VA 24630 (276)988-1822. Plans and specifications are available from Thompson & Litton, 103 East Main Street, Wise, VA 24293 (276)328-2161. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. BARRIER C WATERLINE REPLACEMENT - KANAWHA COUNTY (Bid 7/30/2015) Kanawha Stone Company ...................................................................................... $574,100 Orders Construction Company, Inc. ..................................................................... 579,391 McCoy Construction Company .............................................................................. 647,000 Triton Construction, Inc. ....................................................................................... 653,500 WWTP IMPROVEMENTS, WILLIAMSTOWN (Bid 7/23/2015) C. J. Hughes Construction Company .................................................................... $209,222 J. F. Allen Company................................................................................................ 382,192
WHITE OAKS BUSINESS PARK PHASE II CONTRACT #3- UTILITY PACKAGE (Bid 7/29/2015) (Bid totals based on the selection of Additive Alternate #2) Green River Group, LLC ......................................................................................... $865,426 Pro Contracting, Inc. ................................................................................................ 877,915 Anderson Excavating, LLC .................................................................................... 948,862 D & M Contracting .................................................................................................... 957,834 Cove Run Contracting, LLC ...................................................................................... 992,601 J. F. Allen Company............................................................................................... 1,039,623 Mountaineer Contractors, Inc. ............................................................................. 1,205,743 Bear Contracting. LLC ........................................................................................... 1,296,440
ALLEGHANY COUNTY WASTEWATER IMPROVEMENTS, VIRGINIA (Bid 7/29/2015)
Division 1
Hammond-Mitchell, Inc. ......................................................................................... $1,943,892 Orders Construction Company, Inc. ................................................................... 1,949,600 E. C. Pace Company .............................................................................................. 3,192,500
Division 2 Littleton & Associates, Inc. ...................................................................................... $997,000 Montvale Construction ............................................................................................. 1,165,000 Orders Construction Company, Inc. .................................................................... 1,330,000
*CAWV Members in bold type
HH 2015-31 August 7, 2015
HIGHWAY CONTRACTS FOR SEVEN MONTHS The following is the WVDOH Monthly Project Letting Data for January 1 –July 31, 2015. For the complete listing of project data, dating back to 2000, log onto the CAWV website at www.cawv.org, click Newsletter and then WVDOH letting data. RESURFACING BRIDGE GRADING OTHER TOTAL
#Proj Amount #Proj Amount #Proj Amount #Proj Amount #Proj Amount
July 2015 13 5.17 3 5.46 0 0 14 5.84 30 16.48 2014 48 19.95 3 2.50 0 0 9 5.28 60 27.73 June 2015 18 13.51 1 1.06 0 0 20 9.15 39 23.73 2014 28 33.96 4 3.12 0 0 9 11.97 41 49.05 May 2015 34 28.03 3 9.61 1 174.45 13 11.54 51 223.67 2014 12 5.97 1 1.28 1 18.15 16 5.28 30 30.68 April 2015 31 34.14 6 3.39 1 5.70 6 2.59 44 45.81 2014 22 18.45 3 .389 0 0 23 4.98 48 27.32 Mar 2015 19 11.65 4 4.03 2 4.18 7 7.72 32 27.59 2014 14 8.81 4 2.69 1 0.2 17 7.43 36 19.13 Feb 2015 1 .842 1 6.05 0 0 9 6.66 11 7.85 2014 9 2.8 5 22.44 1 0.43 13 5.84 28 31.52 Jan 2015 4 2.43 4 6.05 0 0 5 .952 13 9.43 2014 7 7.08 1 .465 0 0 3 1.37 11 8.92
TOTAL # OF PROJECTS TOTAL $ AMOUNT
Y-T-D Total for 2015 220 354.52
Y-T-D Total for 2014 254 194.35
($ Amounts in Millions) SENATOR CREATES WEBSITE TO TACKLE ROAD CONCERNS A West Virginia legislator is taking a new approach to tackling road concerns. This week, Sen. Daniel Hall, D-West Virginia, is unveiling a new site called 'Fix the Roads WV.' He said the new site is designed to fast-track constituent complaints. "This is a way for me to document all of these concerns and keep them together. And then I can follow up with highways as we go to see when and where they're going to fix the problems," said Sen. Hall. Sen. Hall said he is fed up with pot holes and fallen rocks, such as those seen on Route 99, that are costing his constituents money many do not have to fix. "You go across there at your own peril. There are boulders falling across white lines that have been there for months.” For Sen. Hall, though, the website is just the beginning. He is already considering his next step. "I wonder if we need to just start privatizing going forward. If highways can't keep up, we need to start
contracting some of this work to those who can get it done quickly." For a link to Hall's website, visit http://fixtheroadswv.com/ Members should support Senator Hall’s efforts by going on his website. WVDOH AUDIT CONTRACT TO BE AWARDED It is expected the West Virginia Legislature is about to award a $540,000 contract with Deloitte and Touche to conduct a performance audit of the West Virginia Division of Highways. The legislature passed a bill to require an audit of the DOH and its ten districts that must be completed by December 31. The firm is to conduct “an independent assessment of the DOH’s organizational structure, programs and operations, and determine whether they are operating effectively and efficiently in carrying out the mission of the DOH.” Some legislators have said it is premature to talk about additional highway funding until the audit is complete. The bill as it was introduced in the legislature had a completion date of February 1, 2016. The CAWV objected noting that there would not be enough time in the 2016 to implement any recommendations the audit may make, thus delaying funding action even further. The bill was amended to have the audit completed in this calendar year. DRAINAGE MITIGATION, WV TURNPIKE, MERCER COUNTY (iSqFt Project ID# 2448624) Bids will be accepted until 3:00 PM on 8/20/2015 for drainage mitigation for the WV Turnpike, Mercer County. Bids should be submitted to WV Parkways Authority, 3310 Piedmont Road, P. O. Box 1469, Charleston, WV 25325. Plans and specifications are available from HNTB, 41 Mission Way, Scott Depot, WV 25560 (304)760-1833. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. REPAIR/ REFURBISH, TENNIS COURTS, COONSKIN PARK (iSqFt Project ID# 2448402) Bids will be accepted until 11:00 AM on 8/11/2015 for repair and refurbish of six regulation tennis courts at Coonskin Park, Charleston. Bids should be submitted to Kanawha County Commission, 407 Virginia Street East, Second Floor, Suite 229, P. O. Box 3627, Charleston, WV 25301 (304)357-0115. Plans and specifications are available from Kanawha County Commission, 407 Virginia Street East, Second Floor, Suite 229, P. O. Box 3627, Charleston, WV 25301 (304)357-0115. Plans and specifications are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. MALSR ROAD SLIDE REPAIR AND STREAM RESTORATION, TRI-STATE AIRPORT (iSqFt Project ID# 2448881) Bids will be accepted until 10:00 AM on 8/14/2015 for repair of slide and reconstruction of Medium Intensity Approach Lighting System with Runway Alignment Indicator Road and stream restoration at Tri-State Airport, Huntington. A pre-bid meeting was held on 8/7/2015 at 9:00 AM at the Private Aircraft Terminal Conference Room, 1449 Airport Road, Huntington. Bids should be submitted to Tri-State Airport Authority, 1449 Airport Road, Huntington, WV 25704 (304)453-2801. Plans and specifications are available from Kimley-Horn and Associates, 13221 Woodland Park Road, Herndon, VA 20171 (303)228-2300. Plans and specifications have been requested for the CAWV Physical Planroom and Internet Planroom at www.isqft.com.
WHEELING LAASF CONCRETE APRON REHABILITATION (iSqFt Project ID# 2451051) Bids will be accepted until 1:30 PM on 9/1/2015 for rehabilitation of selected areas of the concrete parking apron at the Limited Army Aviation Support Facility at the Ohio County Airport, Wheeling. A mandatory pre-bid meeting will be held on 8/18/2015 at 11:00 AM at the Wheeling LAASF Airport, 538 Girtys Point Road, Wheeling. Bids should be submitted to www.wvOasis.gov and solicitation number ADJ1600000006. For additional information contact State of WV, Crystal Rink, 2019 Washington Street East, Charleston, WV 25311 (304)558-2402. Plans and specifications are available from Charleston Blueprint, Reprographic, 1203 Virginia Street, East, Charleston, WV 25301 (304)343-1063. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. RECLAMATION: CITY OF WAR PORTALS - DEP17264 (iSqFt Project ID# 2453084) Bids will be accepted until 1:00 PM on 9/17/2015 for restoration, reclamation, and repair for the City of War portals. A mandatory pre-bid meeting will be held on 8/25/2015 at 10:00 AM at the portals. Bids should be submitted to www.wvOasis.gov and solicitation number DEP1600000008. For additional information contact State of WV, Beth Collins, 1900 Kanawha Boulevard, East, Charleston, WV 25305 (304)558-2157. Plans and specifications are available from www.wvOasis.gov. Plans and specifications are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. STONE CONTRACT, MORGANTOWN UTILITY BOARD (iSqFt Project ID# 2448932) Bids will be accepted until 3:00 PM on 8/17/2015 for the annual stone contract for Morgantown Utility Board. Bids should be submitted to Morgantown Utility Board, 278 Greenbag Road, P. O. Box 852, Morgantown, WV 26507-0852 (304)292-8443. For additional information contact Morgantown Utility Board, Tammy Kennedy, 278 Greenbag Road, P. O. Box 852, Morgantown, WV 26507-0852 (304)292-8443. Documents are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. LARGE EQUIPMENT RENTAL, STATE OF WEST VIRGINIA (iSqFt Project ID# 2450812) Proposals will be accepted until 1:30 PM on 9/8/2015 for an open end contract for the lease of large construction equipment from organizations to be used by the General Services Division throughout the State of WV. Proposals should be submitted to www.wvOasis.gov and solicitation number GSD1600000005. For additional information contact State of WV, Laura Hooper, 2019 Washington Street, East, Charleston, WV 25305 (304)558-0468. Documents are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. CONSULTING SERVICES, MILL CREEK BRIDGE, JACKSON COUNTY (iSqFt Project ID# 2448457) Proposals from consulting firms will be accepted until 4:00 PM on 8/24/2015 for renovation study and development of contract plans for the renovation of the northbound and southbound bridges carrying Interstate 77 over Mill Creek and Jackson County Route 5/9. The existing bridges are 261 feet long by 41 feet wide and are located 0.15 miles south of the United States Route 33 interchange. Proposals should be submitted to Division of Highways, Michael D. Lilly, 1334 Smith Street, Charleston, WV 25301 or email to doh.consultantservices@wv.gov . Documents are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com.
CONSULTING SERVICES, EARL M. VICKERS, MEMORIAL BRIDGE, FAYETTE COUNTY (iSqFt Project ID# 2448431) Proposals from consulting firms will be accepted until 4:00 PM on 8/24/2015 for renovation study and development of contract plans for the renovation of structures carrying West Virginia Route 6 over the Kanawha River, CSX Railroad tracks, United States Route 60, West Virginia Route 61, and 4th and 5th Avenues, Montgomery. The project shall include the main river span, approach spans, and ramp bridges. The existing main river span is 1,665 feet long by 28 feet wide and connects US Route 60 with West Virginia Route 61 in the City of Montgomery. Bids should be submitted to Division of Highways, Michael D. Lilly, 1334 Smith Street, Charleston, WV 25301 or email to doh.consultantservices@wv.gov. Documents are available in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. EOI, ENGINEERING SERVICES, GREENBRIER VALLEY CONSERVATION DISTRICT (iSqFt Project ID# 2452016) Expression of Interest for engineering services for Greenbrier Valley Conservation District will be accepted until 4:00 PM on 8/18/2015 for channel restoration, debris removal, agricultural practices, Geotechnical analysis, hazardous material disposal, site reclamation, stream bank stabilization, utility relocation and watershed dam maintenance and repair. Proposals should be submitted to Greenbrier Valley Conservation District, Gene Saurborn, 179 Northridge Drive, Lewisburg, WV 24901 (304)285-3118. For additional information contact Greenbrier Valley Conservation District, Gene Saurborn, 179 Northridge Drive, Lewisburg, WV, 24901 (304)285-3118. Documents are expected in the CAWV Physical Planroom and Internet Planroom at www.isqft.com. BRIDGE APPROACH, CITY OF PIKEVILLE, KENTUCKY (iSqFt Project ID# 2450860) Bids will be accepted until 2:00 PM on 8/26/2015 for construction of a new bridge across the Levisa Fork and CSX Railroad and approximately 775 LF of approach roads for the City of Pikeville, Kentucky. The bridge is a 628 foot, 4-span PCI beam structure. A pre-bid meeting will be held on 8/12/2015 at 10:00 AM at the Pikeville City Hall, 243 Main Street, Pikeville, KY. Bids should be submitted to City of Pikeville, Pikeville City Hall, 243 Main Street, Pikeville, KY 41501 (606)437-5100. Plans and specifications are available from Summit Engineering, 111 Pike Street, Pikeville, KY 41501. Plans and specifications have been requested for the CAWV Physical Planroom and Internet Planroom at www.isqft.com. RECLAMATION: FAIRMONT (DAC) S, CS, P (Bid 7/30/2015) Howard Concrete Pumping Company, Inc. ............................................................... $730,004 Coastal Drilling East, LLC ........................................................................................ 1,514,425 BEULAH CHAPEL PORTALS DEP17208, MONONGALIA COUNTY (Bid 8/4/2015) Green Mountain Company ...................................................................................... $205,000 Pineville Paving & Excavating, Inc. ...................................................................... 232,255 Breakaway, Inc. ....................................................................................................... 244,940 Williams Excavating, LLC .......................................................................................... 250,201 Solid Rock Excavating, Inc. ...................................................................................... 251,365 McCourt & Son Construction .................................................................................... 257,036 J. F. Allen Company ................................................................................................ 319,959
CAMDEN (HARTLEY) DANGEROUS SLIDE (Bid 8/5/2015) Green Mountain Company ...................................................................................... $483,000 Breakaway, Inc. ....................................................................................................... 574,704 Pineville Paving & Excavating ............................................................................... 583,025 McCourt & Son Construction, Inc. ............................................................................. 595,037 Eastern Arrow Corporation .................................................................................... 640,534 Williams Excavating LLC ........................................................................................... 690,930 HOPEWELL CHURCH REFUSE / DRAINAGE DEP17143 (Bid 7/30/2015) J. F. Allen Company ................................................................................................ $498,438 Green Mountain Company ...................................................................................... 598,000 Williams Excavating LLC ........................................................................................... 606,813 Breakaway, Inc. ........................................................................................................ 748,887 21" PRESTRESSED CONCRETE BOX BEAMS, SWITCHBACK, MCDOWELL COUNTY (Bid 7/31/2015) Carr Concrete Company .......................................................................................... $79,884 Eastern Vault Company, Inc. .................................................................................. 118,596 *CAWV Members in bold type
WV Department of Transporation August 4, 2015 Letting Results
Call # Description Counties Bidder Name Bid Amount
1 EXCHANGE ROAD BRAXTON MEADOWS STONE & PAVING, INC. $229,591J. F. ALLEN COMPANY $250,348WEST VIRGINIA PAVING, INC. $264,430
2 CENTRALIA ROAD BRAXTON J. F. ALLEN COMPANY $228,313MEADOWS STONE & PAVING, INC. $230,217WEST VIRGINIA PAVING, INC. $231,072
3 HAL GREER TRAFFIC SIGNAL CABELL BAYLISS & RAMEY, INC. $169,491DAVIS H. ELLIOT CONSTRUCTION COMPANY, INC. $173,020
4 WALKERSVILLE-ARNOLD ROAD LEWIS J. F. ALLEN COMPANY $253,112WEST VIRGINIA PAVING, INC. $283,794
5 KEGLEY - BEESON MERCER WEST VIRGINIA PAVING, INC. $305,434
6 MT. TABOR - BECKLEY RALEIGH WEST VIRGINIA PAVING, INC. $672,938
7 CLEAN AND PAINT TUCKER ELITE INDUSTRIAL PAINTING, INC. $397,440ST. GEORGE BRIDGE KMX PAINTING, INC. $411,127
EAGLE INDUSTRIAL PAINTING, LLC $439,362NORTH STAR PAINTING COMPANY, INC. $442,748TITAN INDUSTRIAL SERVICES $447,710M&J CONSTRUCTION COMPANY OF PINELLAS COUNTY INC $453,478K.V.K. CONTRACTING, INC. $474,000SPECIALTY GROUPS, INC. $499,633SOUTHERN ROAD & BRIDGE, LLC $638,734APBN, INC. $668,510OLYMPUS PAINTING CONTRACTORS, INC. $851,615
8 ALEXANDER ROAD UPSHUR J. F. ALLEN COMPANY $233,676WEST VIRGINIA PAVING, INC. $241,157
9 BIG SANDY RIVER- WAYNE WEST VIRGINIA PAVING, INC. $980,726CEDAR RUN ROAD
10 EAGLE SCHOOL ROAD BERKELEY JEFFERSON ASPHALT PRODUCTS CO., INC. $208,895W & L CONSTRUCTION & PAVING INC. $218,857
11 SPRING AVE-FT RUN RD HARDY WEST VIRGINIA PAVING, INC. $886,977
12 MILFORD STREET HARRISON MOUNTAINEER CONTRACTORS, INC. $498,984J. F. ALLEN COMPANY $588,345BEAR CONTRACTING, LLC $698,513
13 WESTON-JANE LEW ROAD LEWIS J. F. ALLEN COMPANY $402,256WEST VIRGINIA PAVING, INC. $418,433MOUNTAINEER CONTRACTORS, INC. $445,015
14 GARRETTS BEND LINCOLN WEST VIRGINIA PAVING, INC. $404,919
15 WV 7 MONONGALIA GUARDRAIL MONONGALIA GREEN ACRES CONTRACTING COMPANY, INC. $344,520PDK CONSTRUCTION, INC. $367,971PENN LINE SERVICE, INC. $505,463
16 BEMIS TRUSS BRIDGE RANDOLPH THE OHIO BRIDGE CORPORATION DBA U.S. BRIDGE $1,288,763BILCO CONSTRUCTION CO., INC. $1,460,428ORDERS CONSTRUCTION COMPANY, INC. $1,573,223TRITON CONSTRUCTION INC $1,580,000KANAWHA STONE COMPANY, INC. $1,644,790R. K. CONSTRUCTION, INC. $1,677,936PAULS CONCRETE, INC. $2,229,981
17 LYNN CREEK ROAD TO WAYNE WEST VIRGINIA PAVING, INC. $622,712
WV Department of Transporation August 4, 2015 Letting Results
GERMAN RIDGE
18 TOM'S CREEK TO CRAIG ROAD WAYNE WEST VIRGINIA PAVING, INC. $396,012
19 VAN CAMP ROAD RESURFACING WETZEL KLUG BROS., INC. $504,534KELLY PAVING, INC. $514,999THE LASH PAVING COMPANY $568,087
20 ARDEN NOLLVILLE RD BERKELEY JEFFERSON ASPHALT PRODUCTS CO., INC. $400,987W & L CONSTRUCTION & PAVING INC. $452,644
21 AUGUSTA HILL RESURFACING HAMPSHIRE WEST VIRGINIA PAVING, INC. $663,383BELT PAVING, INC. $703,862
22 LEETOWN ROAD JEFFERSON JEFFERSON ASPHALT PRODUCTS CO., INC. $611,120W & L CONSTRUCTION & PAVING INC. $692,837
23 SNOWDEN ROAD LINCOLN WEST VIRGINIA PAVING, INC. $272,564TO BULGER ROAD
24 EAST GRAFTON ROAD MARION MOUNTAINEER CONTRACTORS, INC. $155,553BEAR CONTRACTING, LLC $164,751J. F. ALLEN COMPANY $166,754DODD GENERAL CONTRACTORS CORPORATION $170,234
25 BRINK ROAD MARION J. F. ALLEN COMPANY $1,219,747MOUNTAINEER CONTRACTORS, INC. $1,225,516BEAR CONTRACTING, LLC $1,331,387DODD GENERAL CONTRACTORS CORPORATION $1,659,106
26 ROCK ROAD SLIP + 1 MERCER SMH CONSTRUCTION COMPANY, INC. $434,043BBR DRILLING COMPANY, INC. $467,558
27 ELDERSVILLE ROAD BROOKE KELLY PAVING, INC. $149,003THIN OVERLAY THE LASH PAVING COMPANY $160,003
28 WASHINGTON PIKE THIN OVERLAY BROOKE KELLY PAVING, INC. $163,065THE LASH PAVING COMPANY $181,843
29 GREEN VALLEY ROAD CABELL WEST VIRGINIA PAVING, INC. $186,622
30 WEST MUD RIVER ROAD CABELL WEST VIRGINIA PAVING, INC. $167,371 TO MILTON
31 OYLER AVE BRIDGE BEAM REPAIR FAYETTE CIVIL CONSTRUCTION, INC. $130,127ADVANTAGE STEEL & CONSTRUCTION, LLC $163,665
32 US 19 HARRISON GUARDRAIL HARRISON GREEN ACRES CONTRACTING COMPANY, INC. $65,258PDK CONSTRUCTION, INC. $66,226PENN LINE SERVICE, INC. $89,798
33 WAR - CUCUMBER ROAD MCDOWELL WEST VIRGINIA PAVING, INC. $470,086
34 WHEELING - WARWOOD OHIO KELLY PAVING, INC. $269,083THIN OVERLAY THE LASH PAVING COMPANY $285,310
35 WEST BETHLEHEM BLVD. THIN O/L OHIO KLUG BROS., INC. $120,009KELLY PAVING, INC. $135,199THE LASH PAVING COMPANY $147,713
36 GLEN WHITE - CRAB ORCHARD RALEIGH WEST VIRGINIA PAVING, INC. $354,201
37 TYLER HIGHWAY THIN OVERLAY TYLER KLUG BROS., INC. $476,015KELLY PAVING, INC. $558,089
38 SISTERVILLE +3 RESURFACING MARSHALL, KLUG BROS., INC. $1,778,245TYLER, WETZEL KELLY PAVING, INC. $2,088,105
THE LASH PAVING COMPANY $2,488,508
WV Department of Transporation August 4, 2015 Letting Results
39 D10 2016 REM GUARDRAIL / DISTRICT 10 GREEN ACRES CONTRACTING COMPANY, INC. $1,388,600 INSTALL / REPL GDRL, FENCE
40 HARRISON COUNTY LINE - HARRISON J. F. ALLEN COMPANY $1,951,674LOST CREEK ROAD M.P. 109.51 MOUNTAINEER CONTRACTORS, INC. $2,105,960
BEAR CONTRACTING, LLC $2,497,814
41 TURKEY CREEK - ANSTED FAYETTE STEVE MARKS CONSTRUCTION, LLC dba MARKS DRILLING $498,242SMH CONSTRUCTION COMPANY, INC. $548,130
42 FRANCES CREEK RD #1 LINCOLN BILCO CONSTRUCTION CO., INC. $140,357THAXTON CONSTRUCTION COMPANY, INC., OF SISSONVILLE $154,292PAULS CONCRETE, INC. $169,115BBR DRILLING COMPANY, INC. $172,274STEVE MARKS CONSTRUCTION, LLC dba MARKS DRILLING $227,138
43 FRANCES CREEK RD #2 LINCOLN BILCO CONSTRUCTION CO., INC. $128,320THAXTON CONSTRUCTION COMPANY, INC., OF SISSONVILLE $129,556STEVE MARKS CONSTRUCTION, LLC dba MARKS DRILLING $138,379PAULS CONCRETE, INC. $157,280BBR DRILLING COMPANY, INC. $166,872MCCOY CONSTRUCTION COMPANY $192,000
*CAWV Members in bold type