APPENDIX 2

8 March 2005

Mr David Kelly Development Manager, Sydney ReadyMix Holdings Pty Ltd Po Box 400 Parramatta NSw 2124

Dear David,

Yours sincerely

Mark Owens Manager, Sydney Operations Australian Rail Track Corporation

AUSTRALIAN ]RAIL TRACK CORPORATION LTD

Re: Letter of advice regarding line capacity on Main South corridor

Further to our discussions regarding the Readymix Development application and subsequent Environmental Impact Statement for the proposed Readymix Lynwood Quarry site at Marulan, this letter is to advise the line capacity availability to accommodate future ReadyMix service operation on the Main South line .

ARTC, have reviewed the current corridor capacity and are able to advise that there is capacity on the Main South corridor to accommodate the transfer of these services on ARTC territory .

Please do not hesitate to contact me for any further information or clarification regarding this matter .

AUSTRALIAN RAIL TRACK CORPORATION LTD ABN: 75 081455 754 Off Sir Donald Bradman Dr, Passenger Rail Terminal Rd, Mile End SA 5031, P.O. Box 10343, Gouger Street, Adelaide SA 5000

Te : (08) 8217 4366

Fax: (08) 8217 4578